127EAW26Q0037 - Dark Canyon Culvert Repair
AGRICULTURE, DEPARTMENT OF
Notice type
Combined Synopsis/Solicitation
Solicitation #
127EAW26Q0037
NAICS
237990
PSC
Z1KB
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
July 27, 2026
Response due
August 25, 2026
Place of performance
Hayfork, CA
Description
1
US Department of Agriculture (USDA)
Statement of Work
-- 1 of 6 --
2
Contents
Project .......................................................................................................................................................................3
General Information ....................................................................................................................................................3
1.0 Scope of Work ...................................................................................................................................................3
2.0 Background .......................................................................................................................................................3
3.0 Location ............................................................................................................................................................3
4.0 Estimated Start Date / Period of Performance ......................................................................................................3
5.0 Drawings and Specifications ...............................................................................................................................4
6.0 Restrictions on Work ..........................................................................................................................................4
7.0 Camping and Housing ........................................................................................................................................4
8.0 Required Submittals ...........................................................................................................................................4
Contractor Requirements .............................................................................................................................................4
9.0 Technical Requirements / Tasks ..........................................................................................................................4
10.0 Government Furnished…………………………………………………………………………………………………...….4/5
11.0 Deliverables / Schedule ....................................................................................................................................5
12.0 Travel ..............................................................................................................................................................6
13.0 Contractor’s Key Personnel ...............................................................................................................................6
14.0 Site Visit ..........................................................................................................................................................6
-- 2 of 6 --
3
Project
DARK CANYON CULVERT REPAIR
General Information
1.0 Scope of Work
Project consists of furnishing all labor, equipment, tools, transportation, incidentals, inspection, quality control and supplies necessary
to complete the Dark Canyon culvert and road repair. Culvert repair materials have been supplied to the Government by Contech
Engineered Solutions and shall be provided to the Contractor (see list of Government-provided materials in the attached Drawings and
Exhibits). All other necessary materials (aggregate base, structural backfill, concrete, etc.) shall be provided by the Contractor.
The Dark Canyon Culvert was damaged in May 2025, most likely due to the insufficient compaction of structural backfill during
initial installation. The Contractor shall repair the existing 26'-0" span, 16'-7" rise single radius arch multi-plate culvert per the
guidance of the manufacturer of both the original structure and the Government-provided culvert repair materials, Contech Engineered
Solutions. This includes two (2) concrete collars at the joints of the original and repair materials. After the culvert has been repaired
and road subgrade has been reconstructed to match the legacy design grades and elevations in the attached Drawings and Exhibits, an
aggregate base surface course will be placed and compacted. Lastly, for stabilization, hydraulic seeding and mulch will be placed on
fill slopes and other areas of disturbance.
All work shall be in accordance with the contract requirements. Contractor shall, without additional expense to the government, be
responsible for obtaining any necessary licenses and/or permits which comply with any federal, state, municipal laws, codes, and
regulations applicable to the performance of the work.
Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, and other such debris.
Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting
Officer at least five days in advance of moving equipment in so that arrangements can be made for inspections.
Contractor is responsible for temporary traffic control and construction signs shall be in accordance with the latest version of
MUTCD.
2.0 Background
Dark Canyon Multi-plate pipe arch culvert was built back in 1999/2000. The pipe arch experienced a catastrophic failure in May of
2025 when a multiplate seam failed and caused a large sinkhole to appear the full width of the roadway. This was determined to likely
be caused by insufficient compaction of structural backfill during installation. The forest, while consulting with Contech Engineered
Solutions, removed the backfill and removed the damaged pipe arch materials and came up with a fix consisting of adjoining the end
sections of old pipe with the new middle section of pipe with concrete collars at the joints tying the pipe arch together as one unit.
Working with Contech the Forest has the necessary multi-plate steel and components needed to rebuild the pipe arch, which will be
Government provided property under this contract.
3.0 Location
The project is located within the Hayfork R…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 237990)
Y--Cauldron Linn Recreation Site Improvements
INTERIOR, DEPARTMENT OF THE · Solicitation · due July 24, 2026
Galena 2024 Event PL84-99 Flood Repair
DEPT OF DEFENSE · Solicitation · due August 13, 2026
Tainter Gates Sandblasting
INTERNATIONAL BOUNDARY AND WATER COMMISSION: US-MEXICO · Solicitation · due August 3, 2026
Y--Boat Ramp Replacement Project at Kirwin NWR