Alpha Controller Upgrade
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
Notice type
Special Notice
Solicitation #
80NSSC26937078Q
NAICS
541330
PSC
K099
Posted
August 25, 2026
Response due
August 27, 2026
Description
NASA AMES 150MW POWER SUPPLY
LABVIEW – NATIONAL INSTRUMENTS UPGRADE
STATEMENT OF WORK
Final Configuration & Factory Acceptance Testing and Field
Commissioning
1. Background
This Statement of Work combines the activities previously identified as Phase 2B (Final
Configuration and Factory Acceptance Testing) and Phase 3 (Field Commissioning) into a
single continuous scope for completion of the NASA Ames 150MW Power Supply
LabVIEW/National Instruments Upgrade.
2. Objectives
Complete the final LabVIEW software configuration.
Validate functional equivalency between the legacy and replacement systems.
Develop and utilize a benchtop simulator for benchmarking and verification.
Complete Factory Acceptance Testing (FAT).
Install and commission the upgraded primary and backup systems in Building N238.
Demonstrate successful operation through Dummy Load and Arc Heater testing.
Turn over a fully operational system with documentation.
3. Assumptions
Existing protective systems remain outside the LabVIEW control system.
No functional changes beyond those required to maintain equivalency.
Facility access, operators, and maintenance personnel will be available as required.
Existing I/O will be reconnected to the replacement hardware.
4. Phase 2B – Final Configuration and Factory Acceptance Testing
4.1 Work Planning
Develop detailed work plans, schedules, conduct project meetings, and coordinate all
activities.
4.2 Simulator Development
Develop a benchtop simulator capable of reproducing the required power supply inputs,
outputs, feedback, permissives, interlocks, and firing-angle commands for benchmarking.
4.3 Final Software Configuration
Correct migration issues, improve diagnostics, reduce host latency, relocate applicable logic
to the RT controller, perform subsystem testing, and validate functional equivalency.
-- 1 of 3 --
4.4 Hardware Validation
Load and verify the upgraded application on the replacement hardware and backup
workstation.
4.5 Factory Acceptance Testing
Prepare FAT procedures, perform unwitnessed FAT, conduct witnessed FAT with NASA
participation, document deficiencies, implement corrections, and issue the final FAT report.
4.6 Documentation
Prepare O&M documentation, program files, licensing information, startup/shutdown
procedures, troubleshooting guidance, and as-tested configuration records.
5. Phase 3 – Field Commissioning
5.1 Preparation
Prepare equipment, installation checklists, wiring diagrams, energization procedures, and
coordinate installation.
5.2 Field Installation
Install the Host workstation, PXI/RT hardware, reconnect field I/O, verify communications,
and perform system checkout.
5.3 Primary System Testing
Perform Dummy Load and Arc Heater runs using the primary workstation and controller.
Record and submit test data.
5.4 Backup System Commissioning
Upgrade the backup workstation, verify functionality, perform Dummy Load and Arc Heater
testing, and synchronize software baselines.
5.5 Closeout
Submit commissioning reports, Dummy Load data, Arc Heater data, and final project
documentation.
6. Deliverables
Benchmarking Report
Factory Acceptance Test Procedures and Reports
Installed Primary and Backup PXI/RT Systems
Installed Primary and Backup Host Workstations
Dummy Load Test Results
Arc Heater Test Results
O&M Manuals
Final Program Files
-- 2 of 3 --
Commissioning Report
Final Closeout Documentation
7. Acceptance Criteria
The work shall be considered complete following successful completion of FAT, installation,
commissioning, Dummy Load testing, Arc Heater testing, submission of all required
documentation, correction of deficiencies, and Government acceptance.
8. Pricing
Pricing shall identify Phase 2B engineering, software development, FAT, documentation,
and simulator development separately from Phase 3 field installation, commissioning,
testing, travel, labor, and materials.
-- 3 of 3 --
Source: SAM.gov, as posted. Verify the current solicitation before responding.