The Department of Defense is seeking a contractor to deliver, install, and verify performance of a Desiccant Machine at Tinker Air Force Base, Oklahoma, under a Total Small Business Set-Aside. This opportunity is classified under NAICS 333998 and PSC 3695, focusing on equipment necessary for conducting vacuum and pressure tests on the F107 engine. Interested small businesses should note that this is a Combined Synopsis/Solicitation, indicating that they will need to track the notice for potential bidding opportunities.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Page 1 of 10
STATEMENT OF WORK
For
P26-005 Desiccant Machine
PREPARED BY:
OC-ALC/OBCA
6 May 2026
-- 1 of 10 --
PREAMBLE
Commander's Safety Intent
The safety of everyone on Tinker AFB is our top priority. All Individuals must accept
personal responsibility for safety and seek opportunities for improving the safety of
our work environment. Everyone working on Tinker AFB is challenged to find, fix
(if able) and report all hazards and near misses. It is our shared duty to take every
reasonable step and precaution to prevent accidents and preserve the health/safety of
each Contractor and Government employee.
1. SCOPE
The 76th PMXG is requesting the utilization of funds for delive1y, installation, and
perfonnance verification of the Desiccant Machine in Building ■ at Tinker Air Force
Base, OK. The Contractor shall provide all labor, equipment, parts, incidentals,
consumables, transportation, and any other items necessaiy to provide the Desiccant
Machine.
Delive1y, installation, and performance verification shall be accomplished within 10
business days of delive1y. The Contractor shall be responsible for ensuring all services,
paiis and components provided under this contract are in accordance with {IAW) the te1ms
and conditions outlined in this Statement of Work (SOW).
2. BACKGROUND
that need to be addressed. As
nts are becoming -
.Add�
, has led to frequent
This machine is - for perfo1ming vacuum and pressure tests on the Fl 07 engine,
ensuring its inte� identifying possible leaks. Due to its - role in production
�' a more reliable, simplified, and modernized solution is required to -
- improve efficiency, and ensure sustained suppo1i for future operations.
3. REQUIREMENTS
3.1 SUBJECT: Item Description, P26-005 Desiccant Machine
1. 76 PMXG is requesting the utilization of funds for Desiccant Machine with the
following specifications.
2. The requested descriptions/specifications ai·e outlined below.
Vacuum Test Engine
Page 2 of 10
-- 2 of 10 --
Page 3 of 10
• Connect apparatus to F107 engine and adjust pressure to 27.7 +/- 0.3 inches of
H2O.
• Maintain pressure for 5 seconds before recording the flow rate.
• Shall be able to detect flow rate as little ≤ 0 ± 0.010 scfm.
Pressure Test Engine
• Connect apparatus to F107 engine and adjust pressure to 27.7 +/- 0.3 inches of
H2O.
• Maintain pressure for 5 seconds before recording the flow rate.
• Shall be able to detect flow rate as little as 0.045 scfm.
Size of Engine
Engine Length: 49.35”, Width: 15.56”, Height: 23.61”
System Performance Requirements
• System shall be capable of vacuum and pressure calibration using internal
regulators and indicator gauges.
Calibration and Communication
• The Contractor shall provide calibration instruction and allow calibration of the
system using in house apparatus (PMEL).
• The system shall include ports for data acquisition and communication, enabling
monitoring of flow and pressure during test operations.
• Flow and pressure gauges must be accurate to detect flow rate and is clearly
readable.
Safety and Electrical
• The entire assembly shall operate on standard 110V AC power and include a
grounded plug.
• The system shall include proper grounding mechanisms to prevent static
discharge during operation.
• Emergency shutoff functionality shall be included.
Control and Regulation Requirements
• The system shall include clearly labeled and accessible valves/ switches to control
including but not limited to
Vacuum Pump
Shop Air
Vacuum Regulator
Pressure Regulator
Mode Selector Valve
Instrument Power
• Control logic must support Mode 1 (vacuum) and Mode 2 (Pressure) operations.
• The operator interface shall be simple and intuitive, providing no more than two
selectable options: Vacuum Test or Pressure Test.
-- 3 of 10 --
Page 4 of 10
• If implemented as a software interface, the selection process shall be limited to
two inputs only (e.g. two buttons, two menu options, or toggle), with no
unnecessary sub menus or advanced settings.
• The system shall include a fail safe default state that ensures the system powers
on in a neutral/ off condition until one of the two modes is selected.
Document and Deliverables
• Contractor shall deliver:
Operator Manual
Calibration Procedure
Wiring and Pneumatic Diagram
Training Material
• Contractor shall also perform an onside demonstration and functional check
with government personnel upon delivery to meet all requirements of the
Statement of Work (SOW).
Data Acquisition and Communication
• The current setup has two connections, "SWAGELOK PAT D-QF 4-B-316" on
the inlet cover and a "9/16-18 thread" on the engine service island.
• The new apparatus connections shall include AN4- hose connections with
stainless braided hosing.
• The connections on the hosing shall be SWAGELOK QC-4 quick connect
fittings, featuring KEY 1 (as one hose for pressure) to SWAGELOK SS-QF4-B-
4PF connection (the engine side) and Key 2 (second hose for vacuum), with the
other end being AN6 to AN4 reducer male to male.
• All hosing shall be a minimum of 5 ft in length.
• To connect apparatus to base airline a 1/4 NPT (male) quick connect is necessary.
3. Contractor shall provide delivery, installation, and performance verification for the
Desiccant Machine IAW the Statement of Work (SOW).
3.2 Installation
3.2.1 The Contractor shall be responsible for equipment delivery to Building at Tinker
AFB, OK 73145.
3.3 Performance Verification/Acceptance Testing – After installation, the contractor
shall demonstrate that the Desiccant Machine meets or exceeds all OEM specifications,
and the requirements listed in section 3.1 of this SOW. Contractor shall be present for
entirety of acceptance testing. The length of time for Acceptance testing should not exceed
one (1) day.
-- 4 of 10 --
Page 5 of 10
4. GENERAL REQUIREMENTS
4.1 Hours of Operation – The Contractor shall perform the work required under this
contract during the following days and hours: Mond…