Fort Lee Vehicle Recovery Range construction project
DEPT OF DEFENSE
Notice type
Solicitation
Solicitation #
W9123626BA006
NAICS
236220
PSC
Y1PZ
Set-aside
8a Competed
Posted
June 18, 2026
Response due
July 28, 2026
Place of performance
Fort Lee, VA
What this opportunity is
The DEPT OF DEFENSE is buying construction services for the Fort Lee Vehicle Recovery Range, which includes building concrete turning pads and site improvements. This 8a Competed set-aside suits small businesses certified under the 8(a) program. As a Solicitation notice, contractors should track the opportunity and prepare to bid, and they must submit questions through ProjNet and bids on the PIEE web site.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
US Army Corps November 2025
Of Engineers
100% Specifications
VEHICLE RECOVERY RANGE
FOR THE
VEHICLE TRAINING DIVISION
Ft Gregg-Adams, Virginia NAO File Number: 1188
Norfolk District U.S. Army Corps of Engineers
Engineering Division
Design Branch
803 Front Street
Norfolk, VA 23510
-- 1 of 233 --
Blank Page
-- 2 of 233 --
1188 VEHICLE RECOVERY COURSE 1188VEHREC
RTA Submittal
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 08/15, CHG 2: 08/21 SUMMARY OF WORK
01 14 00 11/22, CHG 1: 02/23 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 08/23 PROJECT SCHEDULE
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 35 26 11/20, CHG 4: 08/23 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19, CHG 1: 08/23 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23 QUALITY CONTROL
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
DIVISION 31 - EARTHWORK
31 00 00 08/23 EARTHWORK
31 05 19.13 02/21 WOVEN GEOTEXTILES FOR EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 11 20 05/22 BASE COURSE FOR RIGID PAVING
32 12 13 05/17 BITUMINOUS TACK AND PRIME COATS
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 92 19 08/17, CHG 1: 08/21 SEEDING
DIVISION 33 - UTILITIES
33 40 00 11/21 STORMWATER UTILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
-- 3 of 233 --
1188 VEHICLE RECOVERY COURSE 1188VEHREC
RTA Submittal
SECTION 01 11 00
SUMMARY OF WORK
08/15, CHG 2: 08/21
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only. When
used, a code following the "G" classification identifies the office that
will review the submittal for the Government. Submit the following in
accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes construction of concrete turning pads, stone accsss to
training areas, add new storm culverts and end treatments, redress
designated roads per the design plans, regrade one designated road
segment, replacing damaged or destroyed end treatmants, maintenance
activities to include minor repairs and unclogging to existing culverts,
and incidental related work.
1.2.2 Location
The work is located at Fort Gregg-Adams. The exact location will be shown
by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Before work is started, arrange with the Contracting Officer a sequence of
procedure, means of access, space for storage of materials and equipment,
and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures,
Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or
damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered
during construction operations to match existing or adjoining work, as
approved by the Contracting Officer. At the completion of operations,
existing work must be in a condition equal to or better than that
which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with
Installation requirements for locating and marking underground utilities.
SECTION 01 11 00 Page 1
-- 4 of 233 --
1188 VEHICLE RECOVERY COURSE 1188VEHREC
RTA Submittal
Contact local utility locating service a minimum of 48 hours prior to
excavating, to mark utilities, and within sufficient time required if work
occurs on a Monday or after a Holiday. Verify existing utility locations
indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local
utility companies. Scan the construction site with Ground Penetrating
Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of
the ground or paved surface where existing underground utilities are
discovered. Verify the elevations of existing piping, utilities,and any
type of underground or encased obstruction not indicated, or specified to
be removed, that is indicated or discovered during scanning, in locations
to be traversed by piping, ducts, and other work to be conducted or
installed. Verify elevations before installing new work closer than
nearest manhole or other structure at which an adjustment in grade can be
made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting
excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
-- 5 of 233 --
1188 VEHICLE RECOVERY COURSE 1188VEHREC
RTA Submittal
SECTION 01 14 00
WORK RESTRICTIONS
11/22, CHG 1: 02/23
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G"
classification. Submittals not having a "G" " classification are for
information only. When used, a code following the "G" classification
identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar
with and obey Activity regulations including safety, fire, traffic and
security regulations. Keep within the limits of the work and avenues of
ingress a…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 236220)
BLDG 31B New Roofing Below Grade Structure
HEALTH AND HUMAN SERVICES, DEPARTMENT OF · Solicitation · due June 26, 2026
Progressive Design-Build Services under Other Transaction Authority Project: Multi-Domain Cyber and Intel Operations Center, Joint Base San Antonio, Lackland AFB Texas
DEPT OF DEFENSE · Special Notice
Repair BEQ HP135
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 16, 2026
NOS NCCOS COOP OXFORD LAB BSL 2 PROJECT (FEO PROJE
COMMERCE, DEPARTMENT OF · Solicitation · due July 20, 2026
P-1458 2nd Radio Battalion Complex, Phase 2, Parachute and Supply Facilities
DEPT OF DEFENSE · Solicitation · due May 28, 2025
Z1DA--Correct Martinez and Mare Island Generator Fuel Lines
VETERANS AFFAIRS, DEPARTMENT OF · Solicitation · due June 24, 2026