What this opportunity is
The Department of the Interior is seeking a contractor for the UFO Pump Relocation Project, which involves moving a Fairbanks Morse pump and motor approximately 10 feet and ensuring it is operational. This opportunity is set aside for total small businesses under NAICS 811310, focusing on machinery repair. As this is a presolicitation notice, interested small businesses should prepare to submit quotations rather than bids, as the formal solicitation has not yet been released.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Presolicitation Notice
Purchase Request Number: 44049589, UFO Pump Relocation Project
This Presolicitation Notice is drafted in accordance with FAR 5.101(c).
1. Point of Contact
a. Name: Brendan Koop, Contract Specialist.
b. Email: brendan_koop@ios.doi.gov.
c. Address: 1150 N Curtis Road, Boise, Idaho, 83706.
d. Contracting Officer: Jeri L. Wahl (Lynn); jeri_wahl@ios.doi.gov.
2. Set-Aside
a. This requirement will be set aside for a total small business.
3. Codes for Services
a. PSC: N043; Installation of Equipment – Pumps and Compressors
b. NAICS: 811310; Commercial and Industrial Machinery and Equipment (except
Automotive and Electronic) Repair.
4. See attached Draft Performance Work Statement (PWS) for the scope of this
requirement.
5. Place of Performance
a. Hermiston, Oregon.
6. Period of Performance
a. Two weeks from contract award.
All responsible sources may submit a quotation which will be considered for award.
-- 1 of 4 --
PERFORMANCE WORK STATEMENT (PWS)
U.S. Bureau of Reclamation – Umatilla Field Office
UFO Pump Relocation Project
1. Background
The Bureau of Reclamation, Umatilla Field Office located in Hermiston Oregon, has a requirement to move
the #2 Fairbanks Morse 3 stage vertical pump which is currently in the Government’s possession and in
operation, located approximately 10 feet from the location it needs to be installed. The contractor will also
be responsible for having it brought to operational capacity.
Description of the Government furnished components
• Pump: Fairbanks Morse, Model# 36XHC6927UW250, and is Approximately 31 feet long. Weight:
30,000 lbs.
• Motor: U.S. Motor, Inverter Duty Weight: 20,600 lbs.
2. Scope
The contractor shall provide all equipment, labor, and materials necessary to complete the scope of this
requirement. This requirement is to disconnect Pump #2 (Fairbanks Morse Model 36XHC6927UW250) from
its current operation and reinstall the pump in a new position approximately 10 feet away, disconnect the
currently operational synchronous motor and relocate it to a position where it will not be operational, install a
2,500‑HP inverter‑duty VFD motor, align and couple it, and conduct motor trim balancing.
3. Period of Performance
Two weeks from contract award.
4. Place of Performance
The pump is located at the Columbia River Pumping Plant near Hermiston Oregon off HWY 730 (next to Sand
Station Park). The coordinates are latitude: 45.922865, longitude: -119.122338.
5. Tasks
a) Pump and Motor Relocation.
Contractor will be responsible for:
• Unbolting and removing the current motor from the pump, a spare motor pedestal will be provided,
the spare motor pedestal is 60 feet from current pump location. The pump motor will have
electrical, RTD’s and vibration probes disconnected by Reclamation personnel.
• Unbolting and removing the pump from the manifold and pump base.
• Supplying a new flange gasket for the pump to manifold flange.
• Relocate pump and motors in accordance with Section 2 of this document.
b) Installation
After relocating the pump and motor the contractor will:
• Secure the pump to the manifold and pump base with the new flange gasket.
• Re-install the VFD motor ensuring proper alignment and coupler adjustments.
Draft
-- 2 of 4 --
• Trim balance the motor. Reclamation personnel will complete electrical hook up, reconnect the
RTD, and vibration probes.
6. Deliverables
Deliverable Description / Required Content Due Date Acceptance Criteria
Lift & Rigging
Plan
Contractor’s plan detailing crane
configuration, rigging method,
equipment load ratings, safety
controls, and sequencing for
pump/motor removal and installation.
Minimum 5
business days
prior to lifting
operations
Meets OSHA/ASME
standards; includes all
required load calculations
and safety controls.
Alignment Report Documentation of final
motor-to-pump alignment, including
pre-alignment readings, final readings,
tolerances, and verification that OEM
specifications were met.
Within 3
business days
after alignment
completion
Alignment readings fall
within OEM tolerances;
complete dataset provided.
Trim Balance
Report
Vibration/trim balancing data
including baseline vibration values,
corrective actions/weights added, final
vibration levels, and confirmation of
OEM compliance.
Within 3
business days of
trim balancing
completion
Final vibration readings
meet OEM specifications;
report includes all required
measurements.
Installation
Verification Report
Confirmation that pump and motor
were installed correctly, including
torque verification, gasket installation,
coupler fit, and visual inspection of
mechanical connections.
Within 5
business days of
installation
completion
All required checkpoints
completed and
documented; no
deficiencies noted.
Draft
-- 3 of 4 --
7. Performance Requirement Summary
Performance Requirement Summary
Performance
Requirement
Method of
Surveillance
Acceptable
Quality
Level
(AQL)
Performance Standards (PRS) Performance
Measurement
Services
necessary to
install pump
and motor
COR
Inspection
After Task
Completion
Successful testing and
operation of pump and motor;
contractor also submits all
deliverables within the
timeframes stated in section 6
of this PWS.
Fully operational prior to two (2) weeks after
award
COR inspection that
100% of the task has been
achieved
Draft
-- 4 of 4 --