TINKER AFB MAC BOA WWYK230053 - Replace Vault and Fuel Tank, B3202
DEPT OF DEFENSE
Notice type
Presolicitation
Solicitation #
FA813726R0023
NAICS
236220
PSC
Z2GC
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
June 12, 2026
Response due
June 19, 2026
Place of performance
OK
What this opportunity is
The Department of Defense is seeking a contractor to replace a vault and fuel tank at Tinker Air Force Base, Oklahoma, under a total small business set-aside. This opportunity is classified under NAICS 236220 and PSC Z2GC, making it suitable for small construction firms. As this is a presolicitation notice, interested businesses should monitor the opportunity closely for the upcoming solicitation details rather than submitting bids at this stage.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line
Acti
vity
#
Transm
ittal #
Specification
Section
SD
# Submittal Description Item Submitted Paragraph #
Classification:
GOVT or A/E
Reviewer Submit
Approval
Needed
By
Material
Needed
By
Action
Code
Date Of
Action
Date FWD to
APPR / Auth
Date RCD From
CONTR
Date FWD To
Other Revwr
Date RCD
From Other
Reviewer
Action
Code
Date Of
Action
Mailed To
CONTR/ Date
RCD From
APPR
Authority Remarks
1 00 70 00 01 Preconstruction Submittals Entry Access List 1.6 G
2 00 70 00 01 Preconstruction Submittals Key Issue Receipt 1.3.12.1
3 00 70 00 06 Test Reports Pre-Construction Testing Record 1.3.11 G
4 00 70 00 07 Certificates Welding, Cutting and Brazing Permit 1.4 G
5 00 70 00 07 Certificates Framed Instructions 1.8
6 00 70 00 11 Closeout Submittals Key Return Receipt 1.3.12.1
7 00 71 00 01 Preconstruction Submittals Health and Safety Plan 1.3 G
8 00 71 00 01 Preconstruction Submittals Internal Combustion Engines Plan 1.3.5 G
9 00 71 00 01 Preconstruction Submittals Entry Authority List 1.5.2
10 00 71 00 01 Preconstruction Submittals Vehicle Entry Authority List 1.5.2 G
11 00 71 00 01 Preconstruction Submittals Equipment and Material Storage 1.5 G
12 00 71 00 01 Preconstruction Submittals Contractor Offices and Plants 1.5 G
13 00 71 00 01 Preconstruction Submittals Designated Waste and Disposal Areas 1.5 G
14 00 71 00 01 Preconstruction Submittals Construction Phasing Plan 1.5 G
16 00 71 00 01 Preconstruction Submittals FAA Form 7460-1 1.5.3 G
17 00 71 00 07 Certificates Safety Meetings 1.3
18 00 71 00 07 Certificates FOD Awareness and Prevention Training 1.4
19 00 72 00 01 Preconstruction Submittals Restoration Plan 1.3.2 G
20 00 72 00 01 Preconstruction Submittals Storm Water Pollution Prevention Plan 1.3.3.2 G
21 00 72 00 01 Preconstruction Submittals Water System Construction Permit 1.3.3.6 G
22 00 72 00 01 Preconstruction Submittals AF Form 3952 Chemical/Hazardous
Material Request/Authorization 1.4 G
23 00 72 00 01 Preconstruction Submittals Spray Painting Plan 1.9 G
24 00 72 00 01 Preconstruction Submittals Environmental Management System
Awareness Training 1.1
26 00 72 00 03 Product Data Affirmative Procurement Documentation
or Green Statement 1.3.10 G Provide only one. Reference specification for
additional information
27 00 72 00 06 Test Reports AF Form 487 Generator Operating Log
(Inspection and Testing) 1.3.8.1 G
28 00 72 00 07 Cerificates Fire Ant Federal Compliance Agreement
or state phyto-sanitary certificate 1.3.4.1
29 00 72 00 07 Cerificates Monthly Hazardous Material Usage
Report 1.4 G Provide 1st week of each month during
construction
32 00 72 00 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data
Sheets 1.4
33 00 72 00 11 Closeout Submittals Notice of Termination
(ODEQ Form 640-572) 1.3.3.2 G
34 00 72 00 - Attch 2 01 Preconstruction Submittals Documentation of Training/ Experience C.2
C.13
TITLE: Tinker AFB General Requirements Specification (Div 00-01)
SUBMITTAL REGISTER
JOB NAME: WWYK230053 - Repair Vault Tank B3202
LOCATION: B3202 Tinker AFB, OK
CONTRACT NO:
CONTRACTOR:
(d)
CONTRACTOR
ACTION
CONTRACTOR SCHEDULE
DATES APPROVING AUTHORITY
Submittal Register_v3_03/07/22
-- 1 of 4 --
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Line
Acti
vity
#
Transm
ittal #
Specification
Section
SD
# Submittal Description Item Submitted Paragraph #
Classification:
GOVT or A/E
Reviewer Submit
Approval
Needed
By
Material
Needed
By
Action
Code
Date Of
Action
Date FWD to
APPR / Auth
Date RCD From
CONTR
Date FWD To
Other Revwr
Date RCD
From Other
Reviewer
Action
Code
Date Of
Action
Mailed To
CONTR/ Date
RCD From
APPR
Authority Remarks
(d)
CONTRACTOR
ACTION
CONTRACTOR SCHEDULE
DATES APPROVING AUTHORITY
36 00 72 00 - Attch 2 01 Preconstruction Submittals Regulatory Agency Notification C.3
37 00 72 00 - Attch 2 01 Preconstruction Submittals Security Documentation C.4
38 00 72 00 - Attch 2 01 Preconstruction Submittals Communications C.5
39 00 72 00 - Attch 2 01 Preconstruction Submittals Step-by-Step Abatement Procedures C.6 G
40 00 72 00 - Attch 2 01 Preconstruction Submittals Glovebag Procedures C.7 G
42 00 72 00 - Attch 2 01 Preconstruction Submittals Respirator Protection Program C.9
43 00 72 00 - Attch 2 01 Preconstruction Submittals Encapsulation Procedures C.11 G
44 00 72 00 - Attch 2 01 Preconstruction Submittals Landfill Qualifications C.14
45 00 72 00 - Attch 2 01 Preconstruction Submittals Work Schedule C.16
46 00 72 00 - Attch 2 01 Preconstruction Submittals Emergency Plans and Fire Prevention
Plans C.17 G
47 00 72 00 - Attch 2 01 Preconstruction Submittals Written Hazardous Communication
Program C.18
48 00 72 00 - Attch 2 01 Preconstruction Submittals Rental Equipment C.19
49 00 72 00 - Attch 2 07 Cerificates Manufacturer’s Certifications C.10
50 00 72 00 - Attch 2 07 Cerificates Laboratory and Monitoring
Qualifications/Certifications C.12
51 00 72 00 - Attch 2 07 Cerificates Asbestos Waste Transporter
Certification of Insurance C.13
52 00 72 00 - Attch 2 08 Manufacturer's Instructions Safety Data Sheets/Material Safety Data
Sheets C.15
53 00 72 00 - Attch 2 11 Closeout Submittals Waste Disposal Receipt M.1(1) G
54 00 72 00 - Attch 2 11 Closeout Submittals Air Sampling Results M.1(2) G
55 00 72 00 - Attch 3 01 Preconstruction Submittals Documentation of Training/ Experience C.1
56 00 72 00 - Attch 3 01 Preconstruction Submittals Employee Physicals C.2
57 00 72 00 - Attch 3 01 Preconstruction Submittals Security Documentation C.3
58 00 72 00 - Attch 3 01 Preconstruction Submittals Step-by-Step Abatement Procedures
Plan C.4 G
59 00 72 00 - Attch 3 01 Preconstruction Submittals Full Containment Construction
Procedures/Drawings C.5 G
60 …
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 236220)
BLDG 31B New Roofing Below Grade Structure
HEALTH AND HUMAN SERVICES, DEPARTMENT OF · Solicitation · due June 26, 2026
Progressive Design-Build Services under Other Transaction Authority Project: Multi-Domain Cyber and Intel Operations Center, Joint Base San Antonio, Lackland AFB Texas
DEPT OF DEFENSE · Special Notice
Repair BEQ HP135
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 16, 2026
P-1458 2nd Radio Battalion Complex, Phase 2, Parachute and Supply Facilities
DEPT OF DEFENSE · Solicitation · due May 28, 2025
Orrin Hatch U.S. Courthouse LED Lighting Upgrade
GENERAL SERVICES ADMINISTRATION · Solicitation · due July 9, 2026
Z1DA--Correct Martinez and Mare Island Generator Fuel Lines
VETERANS AFFAIRS, DEPARTMENT OF · Solicitation · due June 24, 2026