What this opportunity is
The Department of Defense is seeking a contractor to perform cleaning services for the Track Dipper System at DLA Distribution Red River, Texas. This total small business set-aside opportunity involves the removal of contaminants and sludge from various components of the system, including the dip vat, drying oven, and associated conveyor systems. Interested small businesses should note that this is a combined synopsis/solicitation, indicating that they will need to track the opportunity closely and prepare to submit bids in response to the solicitation.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
DDRT Track Dipper System Cleanout Statement of Work
Page 1 of 9
1.0 Scope
a. This Statement of Work (SOW) covers the work, material, equipment, and
controls that shall be required to remove the solvent/ dried on preservative/
contaminants and sludge from the track dipper system in its entirety as
described below:
i. The track shoe preservation vat includes vat, lid, and all associated items
attached to the vat.
ii. Drip tray from vat to oven including support columns.
iii. Heated wind tunnel drying oven including all items inside and outside the
confines of the oven.
iv. All overhead conveyor systems associated with the Track Dipper System,
including support beams and columns.
v. Input/ output overhead catwalks including ladders, support beams, and
columns.
vi. Ground level conveyor systems from the East/ West main line conveyor to
the endpoint of the three-dipper input/ output sections, top to bottom of
conveyor system.
vii. Flooring under all the above components.
viii. South interior wall behind system from input catwalk to east end of oven.
b. Upon removal of liquid mixture from the vat and remaining thickened sludge, all
track dipper system components, surfaces described above will be mechanically
cleaned to maximize removal of solvent/ preservative/ contaminants to all
components listed above.
c. All wastes will be containerized and staged by the Contractor for disposal as
coordinated by DLA Distribution Red River, Texas (DDRT) through the Host
installation Hazardous Waste Disposal Contract. Safety Data Sheet for track dip
preservative, solvent and biocide chemicals are included as a part of this SOW.
d. Entry into the vat and heated wind tunnel drying oven will be required to
accomplish cleanout and replace aeration heads. Dip vat and heated wind
tunnel drying oven have been identified and labeled as Permit-Required
Confined Spaces.
2.0 Site
a. The site of work is located at DLA Distribution Red River Texas. Located on Red
River Army Depot approximately 18 miles West of Texarkana, Texas on Interstate
30.
-- 1 of 9 --
DDRT Track Dipper System Cleanout Statement of Work
Page 2 of 9
3.0 System Layout and Function
a. The function of the track shoe preservation system is to transport track shoe
bundles by inbound accumulating conveyor lines to a dip vat, apply Government-
furnished solvent and preservative mixture to the material, dwell, dry material in a
heated wind tunnel drying oven, and transport material to outbound conveyor
lines to be stored or shipped.
b. The preservation dip vat is constructed of heavy-duty steel and is resting on the
concrete floor, located along the southern-most wall of Zone 6. The vat was
constructed in accordance with approved Underwriter’s Laboratories, Inc.
Standards. Dimensions of the vat are 20ftL x 6ftW x 5.5ftH with a fill capacity of
approximately 4,000 gallons. The vat is equipped with a retractable cover. Vat
appurtenances also include but may not be limited to pneumatic agitator pumps,
drain lines, air compressor, dip pan, heated wind tunnel drying oven. The vat is
surrounded by nearby associated conveyor lines, conveyor controls, pallet turn
tables, overhead monorails, tractor trolleys, air compressors, support structures,
propane lines, drip pan, forklift barriers, etc.
c. Warehouse roll up doors are located immediately to the west and east of the vat.
Nearest dock ramps are located at the southwest and southeast corners of Zone 6.
d. Access to 110v electrical outlets is available within approximately 15ft of the vat.
4.0 Applicable Specifications, Standards and Codes
a. Applicable Federal or MIL-SPEC requirements
b. Occupational Safety and Health Administration (OSHA Standards)
i. 29 CFR 1910 Occupational Safety and Health Standards
ii. 29 CFR 1960 Basic Program Elements for Federal Employee
Occupational Safety and Health Programs and Related Matters
c. Environmental Compliance Standards
i. 40 CFR 104-135 Water Programs
ii. 40 CFR 239-282 Solid Wastes
-- 2 of 9 --
DDRT Track Dipper System Cleanout Statement of Work
Page 3 of 9
5.0 Requirements
a. Task
i. The Contractor shall provide all equipment, materials, control
components, supervision and labor necessary to accomplish the work
described in Section 1.0 Scope with the exception of waste collection
containers which will be provided by the Government (poly totes for
liquid waste [275-300 gallons each] and 55 gallon drums for solid wastes
such as contaminated gloves, coveralls, rags, etc.).
ii. The Contractor shall transfer all liquid preservative and solvent mixture
from the vat, including sludge along the bottom of the vat, into poly totes
that will be provided by the Government. Note: Aeration system piping
and heads located at the bottom of the vat are surrounded by thickened
sludge. All sludges must be removed from the vat and from around all
appurtenances.
iii. Following bulk removal of liquid mixture and sludge, any residual
preservative mixture and sludge will be removed from all vat surfaces
and appurtenances as described in Section 1.0 Scope to provide a clean,
dry surface, free of significant residuals, debris, or other inhibiting
materials. If any cleaning chemicals are used, the chemicals must be
compatible with the construction materials of the vat and appurtenances
and be approved in advance by RRAD for use on the Depot. All residual
preservative mixture and debris removed from the vat surfaces and
appurtenances will be properly containerized for hazardous waste
disposal in accordance with host installation waste disposal procedures.
iv. The Contractor shall remove all oven liners contaminated with
preservative mixture and mechanically remove any accumulated or
residual mixture or sludge from inside the oven.
-- 3 of 9 --
DDRT Track Dipper System Cleanout Statement of Work
Page 4 of 9
v. The Contractor shall mechanically remove any accumulated or residual
mixture, sludge, and dirt from ground conveyors endpoint to 15’ north of
the track dippe…