What this opportunity is
The Department of Commerce is soliciting bids for the upgrade of the Cold Neutron Imaging Instrument, specifically for a Phase Grating Roll Alignment System. This opportunity is suited for small businesses in the manufacturing sector, particularly those with capabilities in precision engineering and control systems, as the procurement involves high precision rotation stages with specific technical requirements. Interested vendors should note that this is a solicitation notice, indicating that they can submit proposals to fulfill the outlined specifications, with a delivery date set for December 1, 2026.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
1 | P a g e
STATEMENT OF WORK/SPECIFICATIONS
Title: Upgrade of the Cold Neutron Imaging Instrument, Phase Grating Roll Alignment
System
Date: 9 JUN 2026
I. BACKGROUND INFORMATION
The NIST neutron imaging team, in the Radiation Physics Division of the Physical Measurement
Laboratory, is developing a far-field grating neutron interferometer to measure the projection of
the pair correlation function, G(Z), of a sample of interest. This interferometer geometry
requires precision alignment of 3 gratings about the roll direction of the neutron beam. Since
G(Z) is a vector quantity, aligned perpendicular to the grating direction, the grating alignment
stages need to be able to rotate a full 360°, with high resolution. The gratings are lines etched
into silicon wafers, where the period of the lines is of order 1 micrometer and the wafers are 100
mm in diameter. The mass of a grating, including a holder is of order 100 g. The interferometer
pattern is measured by translating one of the gratings, so that that mass of the alignment
system must be kept to as low as achievable. For control hardware, the separation of two of the
gratings along the beam ranges from 1 mm to 300 mm. The third grating is separated by up to
5 m. The overall grating alignment system requires translating the gratings in the vertical
direction, requiring that the grating roll stages (which much also translate) be less than 1 kg in
mass.
II. PURPOSE
This procurement is to obtain quantity three high precision rotation stages (resolution better than
0.00005 degrees) with a clear aperture to allow the beam to pass unattenuated and required
cabling, control hardware, and control software.
Delivery Date
01 DEC 2026.
III. SPECIFIC REQUIREMENTS
SPECIFICATIONS
The rotation stage shall have an angular position resolution at least or better than 0.00001
degrees (lower is better).
1. The rotation stage shall have a central clear aperture at least 80 mm in diameter
(larger is better).
2. The rotation stage shall have a mass less than 1 kg (less is better).
3. The rotation stage shall be able to rotate a full 360 degrees (continuous rotation is
better).
4. The rotation stage shall have a minimum rotation speed of greater than 3 degrees
per second
5. The rotation stage shall maintain resolution when mounted and operated such that
the rotation axis is perpendicular to the vertical direction (perpendicular to gravity)
and supporting a mass of 150 g (supporting a larger mass is better).
6. The rotation stage movement mechanism shall have 0 backlash and maintain
position in the event of unplanned loss of electrical power. Mandatory powered-off
position holding.
7. Vendor to provide all required sensors and control hardware and software to achieve
the specified minimum resolution such that two rotation will separated at a maximum
of 0.3 m and the third rotation stage will be 5 m from the other 2 stages.
-- 1 of 3 --
2 | P a g e
8. Vendor to provide cables with lengths of 10 meters to allow the control box to be
located outside a radiation area.
9. Optional: Hand control unit with cable to permit manual operation of the rotation
stages during initial alignment performed with visible light.
IV. GENERAL REQUIREMENTS
Inspection & Acceptance
In addition to the inspection and acceptance terms articulated in the specific FAR clause that
allows the Government reserves the right to perform such performance tests and evaluations as
defined below to verify specified system performance. Such tests and evaluations, if performed,
shall be conducted within the environment that the system is to be operated. The Contractor has
the right to be present during the tests and evaluations, if performed, at the Contractor’s
expense.
NIST may choose at its discretion to forego this part of acceptance testing.
A visual inspection of the equipment will be performed by the NIST POC to identify surface
defects or any form of indication that any equipment was damaged during transport to
NIST. The Government shall have sole discretion to require repair or replacement of damaged
and/or nonconforming supplies at no cost to the Government. The Government at any time
prior to acceptance shall reject the equipment due to defects and/or nonconformance. The
vendor is responsible for latent defects discovered any time after final inspection. However, the
extent of its liability shall be prorated over the useful life of the equipment.
Ownership of the equipment shall transfer to NIST upon acceptance by the Government.
The Government will test, inspect, and accept or reject the equipment within 15 days of receipt
of the equipment unless otherwise indicated above. The Government reserves the right to
conduct quality assurance testing to confirm that a given instrument(s) meets the
manufacturer’s and/or the Government’s performance specifications. It is anticipated that the
equipment will meet all manufacturer’s specifications and/or the Government’s performance
specifications identified in the most recent operations and maintenance manual for each piece
of equipment and/or in this document.
V. SCHEDULE OF DELIVERABLES
Deliverable
Number Description Format Due Date Quantity
1 Phase grating roll
alignment stages
Provide the
required format
for the
deliverable.
For example,
word, AutoCAD,
Excel, PPT
31 DEC 2026 3
-- 2 of 3 --
3 | P a g e
2 Motion sensors,
motion control
hardware, to
control alignment
stages
Sensors and
controller to
permit better than
0.00001 angular
position resolution
31 DEC 2026 2
3 Sets of cables
between stages,
sensor, controllers
Cables are 10 m 31 DEC 2026 3
4 Motion control
software
SDK based in
C/C++/C# or
.NET
31 DEC 2026 1
5 (Optional) Hand control unit
with cable to
permit manual
operation of the
rotation stages
during initial
alignment
performed with
visible light.
31 DEC 2026 1
Standards of Acceptance: The NIST POC or COR shall review all the above deliverables
and respond with an acceptance or request for revision email to the Co…
Source: SAM.gov, as posted. Verify the current solicitation before responding.