$19M obligated·35 awards·1 agencies·4 NAICS

Federal Contracts

Showing contracts 150 of 79 total. Sorted by action date, most recent first. Excludes $0 modifications.

DateAgencyPIIDNAICSDescriptionAmount
Sep 17, 2025Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503424CWA000070237130EAGLE BUTTE SUBSTATION, STAGE 03, SOUTH DAKOTA$9K
Sep 16, 2025Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503225CWA000122237130NORTH CODY MOI 954 SWITCH REPLACEMENT - WESTERN AREA POWER ADMINISTRATION (WAPA) ROCKY MOUNTAIN REGION HAS A REQUIREMENT WITH THE PRINCIPLAL COMPONENTS OF WORK TO INCLUDE REPLACING ONE (1) 115-KV, 1200-AMP MOTOR-OPERATED INTERRUPTER (ALSO REFERRED TO$522K
Sep 10, 2025Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503425CWA000081237130GRAND ISLAND SUBSTATION, STAGE 08 AND SIOUX FALLS SUBSTATION, STAGE 15, STATION SERIVE UPGRADES, NEBRASKA AND SOUTH DAKOTA$2.3M
Aug 18, 2025Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503225CWA000119237130FLATIRON SUBSTATION 2025 BREAKER REPLACEMENT WITH PRINCIPAL COMPONENTS OF SUBSTATION WORK TO INCLUDE DEMOLITION AND SITE DEVELOPMENT, FOUNDATIONS AND PLATFORMS FOR SUBSTATION ELECTRICAL EQUIPMENT, FURNISH AND INSTALL GALVANIZED STEEL STRUCTURES, INST$184K
Jul 16, 2025Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503423CWA000068237130GROTON SUBSTATION, STAGE 15, SOUTH DAKOTA$4K
Jun 25, 2025Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503424CWA000070237130EAGLE BUTTE SUBSTATION, STAGE 03, SOUTH DAKOTA$38K
May 1, 2025Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503222CWA000072237130HOYT AND KIOWA CREEK 115-KV BREAKER REPLACEMENT$3K
Sep 5, 2024Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503222CWA000072237130HOYT AND KIOWA CREEK 115-KV BREAKER REPLACEMENT$485
Aug 22, 2024Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503224CWA000104237130AULT SUBSTATION STAGE 10 TO REPLACE 13.8KV OIL REACTORS WITH GOVERNMENT FURNISHED AIR CORE REACTORS, REPLACE SIX GOVERNMENT FURNISHED 230KV CCVTS ON EXISTING STRUCTURES, REPLACE FOUR 115KV LINE SWITCHES AT WINDSOR TAP AND HYGIENE TAP ON EXISTING STR$215K
Apr 12, 2024Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503424CWA000070237130EAGLE BUTTE SUBSTATION, STAGE 03, SOUTH DAKOTA$800K
Feb 22, 2024Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503424PWA001775335931SUBSTATION CONNECTORS.$10K
Feb 20, 2024Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503122CWA000074237130LIBERTY SUBSTATION - STATION SERVICE UPGRADES, CONTRACTOR TO AQUIRE AND INSTALL VARIOUS ELECTRICAL EQUIPMENT ITEMS. SEE SPEC FOR DETAILS$5K
Jan 9, 2024Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503222CWA000072237130HOYT AND KIOWA CREEK 115-KV BREAKER REPLACEMENT$11K
Oct 24, 2023Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503222CWA000074237130YELLOWTAIL BREAKER REPLACEMENT$2K
Sep 22, 2023Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503423CWA000068237130GROTON SUBSTATION, STAGE 15, SOUTH DAKOTA$1.6M
Sep 5, 2023Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503122CWA000074237130LIBERTY SUBSTATION - STATION SERVICE UPGRADES, CONTRACTOR TO AQUIRE AND INSTALL VARIOUS ELECTRICAL EQUIPMENT ITEMS. SEE SPEC FOR DETAILS$1K
Feb 7, 2023Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503420CWA000042237130CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA$22K
Sep 28, 2022Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503420CWA000042237130CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA$3K
Sep 20, 2022Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503122CWA000074237130LIBERTY SUBSTATION - STATION SERVICE UPGRADES, CONTRACTOR TO AQUIRE AND INSTALL VARIOUS ELECTRICAL EQUIPMENT ITEMS. SEE SPEC FOR DETAILS$1.3M
Sep 7, 2022Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503222CWA000074237130YELLOWTAIL BREAKER REPLACEMENT$178K
Sep 2, 2022Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000050237130KIMBALL SUBSTATION STAGE 04$4K
Aug 9, 2022Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503222CWA000072237130HOYT AND KIOWA CREEK 115-KV BREAKER REPLACEMENT$755K
Mar 18, 2022Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503420CWA000042237130CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA$30K
Sep 2, 2021Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503420CWA000042237130CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA$1K
Jul 22, 2021Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000050237130KIMBALL SUBSTATION STAGE 04$16K
Jun 19, 2021Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000037237130AULT-BADWATER-NORTH CODY EQUIPMENT INSTALL$23K
Apr 15, 2021Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000050237130KIMBALL SUBSTATION STAGE 04$32K
Mar 4, 2021Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000050237130KIMBALL SUBSTATION STAGE 04$7K
Sep 24, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000050237130KIMBALL SUBSTATION STAGE 04$194K
Sep 23, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000037237130AULT-BADWATER-NORTH CODY EQUIPMENT INSTALL$13K
Sep 14, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000037237130AULT-BADWATER-NORTH CODY EQUIPMENT INSTALL$193K
Sep 8, 2020Department of EnergyWESTERN-UPPER GREAT PLAINS REGION89503420CWA000042237130CONSTRUCTION OF WATERTOWN SUBSTATION, STAGE 22, STATION SERVICE REPLACEMENT IN SOUTH DAKOTA AND BISMARCK SUBSTATION, STATION SERVICE REPLACEMENT IN NORTH DAKOTA$930K
Jun 17, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503219CWA000017237130LINGLE - STAGE 02$60K
May 6, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503220CWA000037237130AULT-BADWATER-NORTH CODY EQUIPMENT INSTALL$259K
Apr 8, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503219CWA000017237130LINGLE - STAGE 02$4K
Jan 30, 2020Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503219CWA000017237130LINGLE - STAGE 02$994
Dec 2, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$15K
Sep 16, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$24K
Sep 13, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503219CWA000025237130GREENWOOD SUBSTATION SWITCH REPLACEMENT FOR ROCKY MOUNTAIN REGION LOCATED IN MORILL COUNTY NEBRASKA$128K
Sep 12, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$3K
Aug 30, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503219CWA000017237130LINGLE - STAGE 02$648K
Aug 26, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$17K
Aug 16, 2019Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503118CWA000021237130GILA SUBSTATION STAGE 07 CONSTRUCTION PROJECT, G5600, DSW, YUMA, AZ$15K
Aug 1, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$36K
Jul 16, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$91K
May 16, 2019Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503118CWA000023237130WESTERN AREA POWER ADMINISTRATION, DESERT SOUTHWEST REGION HAS A REQUIREMENT FOR THE LIBERTY SUBSTATION, STAGE 07 (RUDD BAY UPGRADE), CONSTRUCTION PROJECT$2K
Apr 24, 2019Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$1K
Apr 4, 2019Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503118CWA000023237130WESTERN AREA POWER ADMINISTRATION, DESERT SOUTHWEST REGION HAS A REQUIREMENT FOR THE LIBERTY SUBSTATION, STAGE 07 (RUDD BAY UPGRADE), CONSTRUCTION PROJECT$22K
Feb 15, 2019Department of EnergyWESTERN-DESERT SOUTHWEST REGION89503118CWA000023237130WESTERN AREA POWER ADMINISTRATION, DESERT SOUTHWEST REGION HAS A REQUIREMENT FOR THE LIBERTY SUBSTATION, STAGE 07 (RUDD BAY UPGRADE), CONSTRUCTION PROJECT$597
Sep 26, 2018Department of EnergyWESTERN-ROCKY MOUNTAIN REGION89503218CWA000008237130BIG GEORGE-NORTH CODY 115KV CONVERSION PROJECT FOR ROCKY MOUNTAIN REGION LOCATED NEAR PARK COUNTY WYOMING. IGF::OT::IGF$4.4M