What this opportunity is
The Department of Defense is soliciting bids for the construction of a microgrid at the 178th Wing Base in Ohio. This opportunity is set-aside for total small businesses, as defined by the Federal Acquisition Regulation (FAR) 19.5. Small businesses with experience in heavy construction, specifically building construction contractors (NAICS 237130), should track this solicitation for potential participation.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Page | 1
DEPARTMENT OF THE AIR FORCE
178th WING
CIVIL ENGINEER SQUADRON
SPRINGFIELD, OH
STATEMENT OF WORK
Install Basewide Microgrid
PROJECT NO.
WAAR209001
DEPARTMENT OF THE AIR FORCE
178th CIVIL ENGINEER SQUADRON
SPRINGFILED-BECKLEY AIR NATIONAL GUARD BASE
SPRINGFIELD, OH
REV: 20260422
-- 1 of 16 --
Page | 2
1. GENERAL INFORMATION
1.1. DEFINITION OF TERMS
1.1.1. GOVERNMENT refers to the United States GOVERNMENT and the
United States Air Force as represented by the United States
CONTRACTING OFFICER or their designated representative, the
CONTRACTING OFFICER’s REPRESENTATIVE (COR) from the 178th
Civil Engineer Squadron.
1.1.2. CONTRACTOR refers to the CONTRACTOR, the SUBCONTRACTOR
for the CONTRACTOR, any and all CONTRACTOR and
SUBCONTRACTOR employees or personnel, the CONTRACTOR’s tools,
and the CONTRACTOR’s vehicles and equipment.
1.1.3. NOTICE TO PROCEED (NTP) provides written notification that the
CONTRACTOR has provided adequate design submittals and approved by
the CONTRACTING OFFICER. This shall allow the CONTRACTOR to
begin ordering construction materials.
1.1.4. PERIOD OF PERFORMANCE (PoP) begins with the NOTICE TO
PROCEED and ends after the final acceptance of the construction.
1.2. ABBREVIATIONS / ACRONYMS
KO: CONTRACTING OFFICER
COR: CONTRACTING OFFICER’s REPRESENTATIVE
PoP: Period of Performance
OTHERS: Workmen under the employ of Other CONTRACTORS or the GOVERNMENT.
NTP: Notice To Proceed provided by the CONTRACTING OFFICER
ASTM: American Society for Testing and Materials
DDC: Direct Digital Controls
ECPs Entry Control Points
EM: Environmental Manager
GFE: GOVERNMENT Furnished Equipment
IT: Information Technology
MSDS: Material Safety Data Sheet
OPSEC: Operations Security
OSHA: Occupational Safety and Health Administration
QA/QC: Quality Assurance / Quality Control
SOW: Statement of Work
UFC: Unified Facilities Criteria (Design Manual)
UFGS: Unified Facilities Guide Specifications
VECP: Value Engineering Contract Proposal
-- 2 of 16 --
Page | 3
1.3. INSTALLATION STANDARDS
1.3.1. CONTACTOR shall provide all labor, material, tools, equipment,
supervision, and all items to complete the work in accordance with all
portions of the SOS, Drawings, Specifications, all applicable building codes,
UFCs, ETLs, etc. unless otherwise noted under the Government Furnished
Equipment/Property section (Para. 2.2).
1.3.2. Repairs, replacements, new installations and re-installations shall conform
to the current version of all applicable Federal, State, and Local building
codes, laws, and regulations for building constructions, renovations, and
maintenance activities as specified by the installation’s Base Facility
Standards referenced below. The workmanship shall meet the requirements
of these standards. The CONTRACTING OFFICER or COR must approve
the workmanship upon completion and prior to closeout of the contract.
1.3.3. Adhere to all Unified Facilities Criteria (UFC) and Unified Facilities Guide
Specifications (UFGS). The US National Electric Code (NEC), Plumbing
Codes, International Building Code (IBC), and the Ohio Building Code
(OBC) shall be the minimum construction standard allowed, however the
UFC shall take precedence should conflict arise.
1.3.4. Follow standards for worker safety found in Occupational Safety and Health
Administration (OSHA) requirements, EM385-1-1, National Electric Safety
Code, and other similar Standards.
1.3.5. For any electrical work, provide a licensed electrician knowledgeable of and
conforming to the requirements of the National Electrical Code (NEC). The
licensed electrician must hold and be able to provide a current and valid
certification prior to the start of any electrical work. Certification shall be
submitted to base engineering for review. Follow all standards for
electrical installations pertaining to fire protection and personnel safety
found in the most current US National Electric Code (NEC).
1.3.6 Any work completed to add new, repair or modify existing fire alarm,
suppression, and/or detection systems must be installed in accordance with
current NFPA requirements. The components or system installed shall
operate with existing building components and be compatible with existing
fire alarm panel, able to communicate with headend units at the primary and
alternate BDOC locations. The Springfield Ohio Air National Guard Base
Fire Department requires a Monaco Fire Alarm panel system.
1.3.7 Any work completed to add new, repair, modify, or otherwise interface with
the Springfield Ohio Air National Guard Base DDC system shall operate and
be compatible with existing DDC IT infrastructure with no system
degradation of existing capabilities. The Springfield Ohio Air National Guard
-- 3 of 16 --
Page | 4
Base uses a system based on Honeywell Niagara 4 software. Potential
connections may be necessary depending on how controls can be integrated.
1.3.8 Exterior walls, interior bearing walls (and/or columns) and roof assembly
shall meet minimum blast and ballistic mitigation criteria as set forth by UFC
4-010-01, Change 3.
1.3.9 All concrete design shall be in accordance with ACI 318 Code Requirements
for Structural Concrete.
1.3.10 Dispose of all solid waste to include non-hazardous and hazardous waste in
compliance with all Federal, State, and Local environmental laws and
regulations in coordination with the Base Environmental Management
Office (EMO). Track and report the volume of solid waste (Construction &
Demolition) disposal and recycling costs incurred, or funds received,
disposal sites, and weight tickets to the COR using Post-Project Waste
Diversion Report (attached) within 30 days from project completion using
the submittal process.
1.3.11 Perform site preparation in accordance with drawings and specifications
included within or attached to this Statement of Work (SOW). Questions
pertaining to the depth and extent of the site preparation shall be directed to
…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 237130)
178th Wing Base Microgrid Construction
DEPT OF DEFENSE · Solicitation · due August 14, 2026
XUMU 20260001 OSP Oak Mountain Fiber Relocation
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 21, 2026
Nez Perce-Clearwater NF - Seed Orchard Disconnect and Electrical Life Safety Rehab
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 27, 2026
Nez Perce-Clearwater NF - Seed Orchard Disconnect and Electrical Life Safety Rehab
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 27, 2026
U.S. ARMY 63RD READINESS DIVISION MILCON ERCIP MICROGRID
DEPT OF DEFENSE · Solicitation · due July 31, 2026
Eareckson Air Station Container Tower
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 25, 2026