What this opportunity is
The Department of Defense is seeking to procure three specialized trailer systems for the 9th Civil Engineer Squadron at Beale AFB, CA, under a Total Small Business Set-Aside. The requirement includes a Two-Stall Mounted Restroom Trailer, a Gravity Tilt Trailer, and a Bottle Fill Trailer, all essential for field maintenance and sanitation support. This opportunity is a Combined Synopsis/Solicitation, indicating that interested small businesses should track the notice for potential bidding once funding becomes available, as the contract award is contingent on appropriated funds.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
CUI
CUI
STATEMENT OF NEED
Project Title: Procurement of Trailer Systems for Water Fuels and Systems MTX
Requesting Organization: 9th Civil Engineer Squadron (9 CES)
Delivery Location: Beale AFB, CA
Funding Status: This requirement is currently unfunded. The Government's obligation under
this solicitation is contingent upon the availability of appropriated funds. No contract will be
awarded until funds are made available.
A. Purpose and Background
The 9th Civil Engineer Squadron (9 CES) requires the procurement of three specialized trailer
systems to support the Water Fuels and Systems Maintenance (MTX) shop. These assets are
critical for sustaining operational readiness, field maintenance, and secure water/sanitation
capabilities. The procurement includes a Two-Stall Mounted Restroom Trailer, a Gravity Tilt
Trailer, and a Bottle Fill Trailer.
B. Scope and Salient Characteristics
The contractor shall provide all equipment meeting or exceeding the following salient
characteristics. Exact specifications may vary slightly based on the manufacturer, provided they
meet the minimum operational intent.
1. Two-Stall Trailer Mounted Restroom
Purpose: Field sanitation support for the 9 CES Water Fuels and Systems MTX shop.
Component Minimum Specification / Requirement
• Overall Size - Approximately 9.3 ft (L) × 6.7 ft (W) × 8.6 ft (H)
• Towbar & Coupling - 4 ft (1,200 mm) towbar equipped with a secure safety
coupling for tractor towing
• Axle & Brake System - Single axle with two tires, equipped with a mechanical
braking system and hand brake
• Suspension & Frame - Heavy-duty frame with rust-resistant treatment
• Stabilizing Jacks - 4 jacks (one on each corner, with extendable legs)
• Water System - High-flow heavy-duty water pump, sink, and integrated tanks
• Electrical System - LED lighting, cables, power outlets, switches, and circuit
breaker panel
• Maximum Load Capacity - 2,000 kg (4,500 lbs)
-- 1 of 3 --
CUI
CUI
2. Gravity Tilt Trailer
Purpose: Heavy equipment and materials transport for the 9 CES Water Fuels and
Systems MTX shop.
Component Minimum Specification / Requirement
• Configuration - 7x25 (17 ft tilt deck + 8 ft stationary front platform), Gravity Tilt
Trailer
• Towing Capacity - 20k GVWR Bumper Pull
• Axle & Brakes - Tandem 9k lbs Direct Lube 8-lug with electric brakes on both
axles
• Flooring & Fenders - 1/8" Diamond Plate flooring; 102" wide with drive-over
fenders
• Tires & Spares - 17.5" ST235/75R17.5 18-ply radial LRJ Tires; includes 1 spare
tire
• Finish - Fully primed and painted with high-grade acrylic enamel
• Lighting - All flush-mount or recessed lifetime LED stop/turn/clearance lighting
3. Bottle Fill Trailer
Purpose: Potable water distribution and chilling for field personnel.
Component Minimum Specification / Requirement
• Trailer Type - Galvanized DOT approved trailer
• Primary Tanks - 500-gallon NSF / FDA Compliant tank
• Secondary Tank - 100-gallon rinsing/flushing tank
• Dispensing System - Stainless Steel dispensing faucets for water bottles
• Water Pressurization - 110V Water pump to pressurize delivery lines
• Sanitation - UV Disinfection system with reverse cleaning pump
• Cooling System - Chiller system with an onboard generator to power the cooling
water chiller
• Storage - Storage bin mounted at the tongue of the trailer
• Compliance - The tank, piping, and pump must be NSF / FDA Compliant
-- 2 of 3 --
CUI
CUI
C. Delivery and Logistics
POC: TSgt Brian Berquist
Shipping Destination - Bldg. 2536 B. Street, Beale AFB, CA
Delivery Lead Time - 60 days after receipt of order (ARO) / payment
Condition - All equipment must be delivered fully assembled, new, and ready for immediate
deployment.
D. Base Access Procedure.
The contractor shall adhere to the following procedures for all deliveries to Beale AFB:
• Submit Entry Authorization List (EAL): A completed EAL must be submitted to the
Government POC at least 14 days prior to delivery for all personnel.
• Provide Valid Identification: All personnel must present either a REAL ID or two (2)
other forms of valid identification upon arrival.
• Use Designated Entry Point: All vehicles must enter through the Wheatland Gate.
• Consent to Inspection: All vehicles and personnel are subject to inspection by base
security forces.
E. Traffic Laws
The contractor and their employees shall comply with all installation traffic
regulations.
F. Cellular Phone Policy
The contractor shall comply with local base policies regarding cellular phone operation.
-- 3 of 3 --