Description
DEPARTMENT OF THE AIR FORCE 04/06/2026
14 CONTRACTING SQUADRON
BASE PAVING AND CIVIL WORKS INDEFINITE DELIVERY INDEFINITE QUANTITY CONTRACT
COLUMBUS AIR FORCE BASE, MISSISSIPPI
Table of Contents
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01011 – GENERAL DESCRIPTION
SECTION 01620 - ENVIRONMENTAL CONSIDERATIONS
DIVISION 2 - SITEWORK
SECTION 02222 - EXCAVATION, TRENCHING, AND BACKFILLING FOR UTILITIES SYSTEMS
SECTION 02225 - EARTHWORK FOR ROADWAYS AND AIRFIELDS
SECTION 02226 - RECONSTRUCT BASE COURSE
SECTION 02232 - SELECT-MATERIAL SUBBASE COURSE
SECTION 02233 - GRADED-CRUSHED-AGGREGATE BASE COURSE
SECTION 02235 - LIMEROCK BASE COURSE
SECTION 02239 - PORTLAND CEMENT-STABILIZED BASE OR SUBBASE COURSE
SECTION 02241 - STABILIZED-AGGREGATE BASE COURSE
SECTION 02511 - CONCRETE SIDEWALKS AND CURBS AND GUTTERS
SECTION 02515 - CONCRETE PAVEMENT FOR ROADS AND AIRFIELDS
SECTION 02551 - BITUMINOUS INTERMEDIATE AND WEARING COURSES FOR ROADS AND
STREETS (CENTRAL-PLANT HOT-MIX)
SECTION 02555 - DOUBLE BITUMINOUS SURFACE TREATMENT (DBST)
AGGREGATE GRADATION
SECTION 02556 - BITUMINOUS INTERMEDIATE AND WEARING COURSES FOR AIRFIELDS,
HELIPORTS, AND HEAVY-DUTY PAVEMENTS (CENTRAL-PLANT HOT-MIX)
SECTION 02558 - BITUMINOUS TACK COAT
SECTION 02559 - BITUMINOUS PRIME COAT
SECTION 02562 - RUBBERIZED COAL-TAR EMULSION SAND SLURRY SEALCOAT FOR
BITUMINOUS PAVEMENT
SECTION 02574 - PATCHING OF RIGID PAVEMENTS
SECTION 02576 - RUBBER AND PAINT REMOVAL FROM AIRFIELD PAVEMENTS
SECTION 02577 - PAVEMENT MARKINGS
SECTION 02580 - RANDOM CRACKS SEALING IN BITUMINOUS PAVEMENTS
SECTION 02581 - SEALING AND RESEALING JOINTS AND RANDOM CRACKS IN CONCRETE
PAVEMENTS
SECTION 02598 - COLD MILLING OF BITUMINOUS PAVEMENTS
SECTION 02722 - SITE STORM SEWERAGE SYSTEMS
SECTION 02935 - TURF
-- 1 of 195 --
DEPARTMENT OF THE AIR FORCE 04/06/2026
14 CONTRACTING SQUADRON
BASE PAVING AND CIVIL WORKS INDEFINITE DELIVERY INDEFINITE QUANTITY CONTRACT
COLUMBUS AIR FORCE BASE, MISSISSIPPI
01011- 1
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01011 – GENERAL DESCRIPTION
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
The work will include providing all labor, equipment, plant, tools, transportation, and materials to perform
various types of site work. The site work will include, but is not limited to, repair and construction of
asphalt and concrete pavements including subbase and base course, installation of associated utilities,
drainage structures, sidewalks, curb and gutters, rubber removal and painting of runways, taxiways, and
aprons, and turf. All work indicated in the specifications, drawings, and bid schedule shall be accomplished
for the original bid price. The work will be issued in incremental task orders throughout each year as money
becomes available. Each task order will be separately negotiated to determine quantities, not price
determined by Gordian estimating methods. The Contractor will only apply the applicable requirements of
the specifications to each separate task order. Unique items of work not priced in the (catalog) will be
determined through Gordian procedures. This general outline of work does not, in any way, limit the
responsibility of the Contractor to perform all work as specified herein.
1.2 LOCATION
The work will be located at Columbus Air Force Base, Columbus, Mississippi, SEA-RAY Remote Airfield,
Macon, Mississippi and the Auxiliary Airfield, Shuqualak, Mississippi. The exact location of each task
order will be indicated by the Contracting Officer.
1.3 SITE CONDITIONS
The Contractor acknowledges satisfaction as to the nature and location of the work, the general and local
conditions, access to job site; disposal, handling, and storage of materials; availability of labor, water,
electric power or similar physical conditions at CAFB and the auxiliary airfield; the character of equipment
and facilities needed preliminary to and during the performance of the work; and all other matters that can in
any way affect the work or the cost thereof under this contract. The Contractor shall protect existing
underground and above ground structures from damage. The Contractor will provide temporary support for
all structures in the areas of excavation. Where existing utilities or any other structures are damaged during
construction, and which are not included for removal in the design and specifications, the Contractor shall
restore them to their original condition at the Contractor's own expense. The Contractor shall notify the
Contracting Officer of any damaged underground structure and make repairs or replacements before
backfilling.
1.4 NOTIFICATION:
The Contractor will be notified of a site work requirement by the Contracting Officer. Each notification will
contain a project description for the task order. Upon receipt of notification, contact the Contracting Officer
-- 2 of 195 --
DEPARTMENT OF THE AIR FORCE 04/06/2026
14 CONTRACTING SQUADRON
BASE PAVING AND CIVIL WORKS INDEFINITE DELIVERY INDEFINITE QUANTITY CONTRACT
COLUMBUS AIR FORCE BASE, MISSISSIPPI
01011- 2
to arrange an appointment for a joint site visit with Civil Engineering. The initial site visit will be held
within five (5) working days from receipt of notification and at a time convenient to both parties.
1.5 SITE VISIT
The Contractor will be escorted to the work site by a Government representative to view the scope of work
for all work to be accomplished in the task order. Any clarification of the scope can be discussed at that
time. If applicable, a task order detailing the scope of work will be issued following completion of
negotiations.
1.6 PERFORMANCE PERIOD
Contractor shall perform the work within the time as specified in each task order. Work days for this
contract will be Monday through Friday between the hours of 7:30AM and 4:30PM. Flight line work may
be done on weekends, after duty hours, or during other times approved by the Government. The
Government will issue a Notice to Proceed (NTP) to the Contractor for initiation of work. The Contractor
will give…