Dry Dock Elevator Dismantle
DEPT OF DEFENSE
Notice type
Sources Sought
Solicitation #
N32253-26-900-0009
NAICS
238910
PSC
P500
Posted
July 24, 2026
Response due
July 28, 2026
Place of performance
JBPHH, HI
Description
PERFORMANCE WORK STATEMENT (PWS)
Dry Dock Elevator Dismantle and Package for Disposal
for Pearl Harbor Naval Shipyard
& Intermediate Maintenance Facility (PHNSY & IMF)
1.0 BACKGROUND
1.1 The primary mission of Pearl Harbor Naval Shipyard & Intermediate Maintenance Facility (PHNSY
& IMF) is to deliver regional maintenance, at the depot and intermediate levels, to keep the surface
ships and submarines of our nation's navy "Fit to Fight." As Hawaii’s regional maintenance center,
capabilities include excellence in overhauling, repairing, converting, alteration, refurbishing, and
decommissioning of Navy vessels.
2.0 OBJECTIVE & SCOPE
2.1 As part of planned infrastructure modernization, PHNSY & IMF seeks a contractor that is qualified to
perform the dismantling and packaging for disposal of three (3) legacy dry dock elevators. Two (2)
Champion Elevators, model US-10000-FP, which are inclusive of the tower, car, counterweight(s),
base and upper platforms, base and upper landings and all peripherals and electrical components. One
(1) Industrial Rack and Pinion Elevator, which is inclusive of the tower, car, counterweight(s), base
and upper platforms, base and upper landings and all peripherals and electrical components. The
schedule of the dismantling and disposal of the elevators shall be determined by a government
representative and coordinated with the contractor. The desired result of these services is to clear the
dry dock basins to allow PHNSY & IMF to use the spaces more effectively. This equipment removal
effort is above and beyond the current resource capacity of PHNYS & IMF’s production shops.
3.0 PERFORMANCE REQUIREMENTS
3.1 The Contractor shall provide all labor, supervision, tools, design, transportation and machinery to
remove, dismantle and palletize the dry dock elevators and all associated parts.
3.2 The contractor shall provide one (1) individual as a Project Manager who is responsible for planning,
scheduling and managing the execution of all aspects of the work required.
3.3 The contractor shall submit a preliminary Dismantle Plan as part of the Contractor’s proposal and bid
submittal. The preliminary plan should include at a minimum: scope of work to be performed, lifting
and handling material and equipment to be used, rigging plan showing lift points, rigging equipment
used, rigging procedure, lift configuration, center of gravity of load and timeline of work to be
performed.
3.4 The contractor shall provide an Environmental Protection Plan (EPP) as part of the Contractor’s
proposal and bid submittal. Appendices I and II, in paragraph 12.0, outline the various elements that
shall be addressed, including testing the Champion Elevator for the presence of hazardous material,
including lead and asbestos, and environmental mitigation efforts, including nuisance dust control and
other steps to be taken to minimize or prevent damage to adjoining structures, on-going PHNSY &
IMF operations and injury to personnel working in the vicinity. Once accepted by the Government,
the EPP shall become an integral part of the requirements of this PWS.
3.5 A preliminary Plan of Action (POA) plan must be submitted prior to commencing. This plan will
highlight disassembly plans for the equipment items to be disassembled, relocated, staged and
packaged for disposal under this specification during the contract period of performance. The POA
shall be submitted in a PDF format within ten (10) business days after the contract is awarded. The
POA will be reviewed and approved by the Government.
3.6 When the contract is awarded, the contractor will complete the NAVFAC HI QA/Safety Contractor &
DRAFT
-- 1 of 7 --
Rigging Crane Entry Package in Appendix IV of paragraph 12.0 and submit to the TPOC and COR
within the designated time frame stated. The lifting and handling plan shall include, but is not limited
to, the following minimum requirements: a rigging plan, showing the lift points; rigging equipment
to be used (including Safe Working Load [SWL]); and rigging procedure; the center of gravity of the
lifted load; laydown area; overhead interference(s) and mobile crane hook height requirements. The
Contractor must provide any additional technical data, hazard analysis, or site specific details
necessary to ensure safe operation beyond the baseline. Lifting and handling operations shall only
commence once the Crane Entry Package is reviewed by the Government.
NOTE: Rigging items by choking or sweeping using synthetic products is not allowed unless
approved by the Government. Tilting of lifted or suspended loads during installation, when it is
necessary, shall only be performed using a chain-fall, ratchet hoist or similar equipment, and only
done in a controlled manner following government approval.
3.7 Prior to commencing work, the contractor shall meet in conference with the government Technical
Point of Contact (TPOC), Contracting Officers Representative (COR) and necessary support
personnel to discuss and develop mutual understandings relative to environmental, safety, schedule,
security, and waste management.
3.8 The contractor shall provide a Safety Plan and Fall Protection Plan (if applicable) covering all aspects
of safety for this project. The safety plan shall be approved by the Government prior to
commencement of work. All work performed shall be in accordance with applicable Federal, State of
Hawaii and OSHA requirements. Refer to Appendix I for guidance regarding safety.
3.9 The contractor shall provide all lifting and handling equipment (such as cranes, multi-purpose
machines, MHE, and construction equipment that may be used as a crane or in a crane like
application to lift-suspended loads), rigging equipment, rigging support services, and other support
equipment necessary for continuous support and shall provide qualified personnel for safe operation.
3.9.1 Contractors shall have a spill kit at the work area to clean any fluid spills from the Material
Handling Equipment (MHE)…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238910)
W569QE26QA007 Combined Synopsis Solicitation - T4 Demolition / Ft Bliss,TX
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 29, 2026
Former General Leonard Wood Army Community Hospital Demolition, Optical Fabrication Laboratory, with Site Improvements
DEPT OF DEFENSE · Sources Sought · due July 30, 2026
Range Echo Berm Upgrade - Fort Devens, MA
DEPT OF DEFENSE · Solicitation · due July 27, 2026
P--WV CANAAN VLY NWR BONNER HS DEMO
INTERIOR, DEPARTMENT OF THE · Solicitation · due July 23, 2026
B2A Demolition, NIST, Boulder, CO
COMMERCE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 12, 2026
Demolition IDIQ
DEPT OF DEFENSE · Presolicitation · due July 31, 2026