Ft Gordon Trailer Lease
DEPT OF DEFENSE
Notice type
Solicitation
Solicitation #
W50S6Z26QA003
NAICS
532120
PSC
X1AA
Set-aside
Small Business Set Aside - Total
Posted
August 12, 2026
Response due
August 24, 2026
Place of performance
Fort Gordon, GA
Description
31 July 2026
PERFORMANCE WORK STATEMENT (PWS)
Leasing of Turnkey Relocatable Modular Buildings and Workspace
Fort Gordon, Georgia
1.0 General:
1.1 Scope:
The Contractor shall provide all personnel, equipment, tools, materials, supervision, and
quality control necessary to perform leasing, delivery, setup, maintenance, and eventual
removal of a turnkey relocatable modular office facility at Fort Gordon, Georgia, as
defined in this PWS.
1.2 Objectives:
To provide temporary administrative and workspace facilities to establish Initial
Operating Capability (IOC) for 142 personnel of the 117th & 155th COS being stationed
at Fort Gordon, Georgia, pending construction of their permanent MILCON facility.
1.3 Place and Performance of Services shall be at the designated relocatable facilities
site located at the corner of 31st Street and Lane Avenue, Fort Gordon, GA 30905 (651
31st Street).
1.4 Quality Assurance (QA):
The Government will evaluate the Contractor's performance under this contract in
accordance with a Quality Assurance Surveillance Plan (QASP). The COR will perform
periodic inspections to ensure compliance with setup timelines, HVAC performance,
and structural maintenance.
1.5 Access and General Protection/Security Policy and Procedures:
The Contractor shall comply with all Fort Gordon access control and security policies.
Contractor personnel must obtain temporary base identification and vehicle passes via
the Visitor Control Center.
• Antiterrorism (AT) Level I Training: All Contractor and subcontractor employees
requiring unescorted access to Army installations, facilities and controlled
access areas must complete:
• AT Level I Awareness Training within fifteen (15) calendar days after
contract start date or effective date of incorporation of this requirement
into the contract, whichever is applicable.
-- 1 of 12 --
31 July 2026
• The contractor shall submit certificates of completion for each affected
contractor employee and subcontractor employee, to the COR or to the
contracting officer, if a COR is not assigned, within 15 calendar days after
completion of training by all employees and subcontractor personnel. AT
level I Awareness training is available at the following website:
http://jko.jten.mil.
• Access and general protection/security policy and procedures: Contractor and
all associated subcontractor employees shall provide all information required for
background checks to meet installation access requirements to be accomplished
by installation Provost Marshal Office, Director of Emergency Services or Security
Office. Contractor workforce must comply with all personal identity verification
requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor
Personnel) as directed by DOD,HQDA and/or local policy. In addition to the changes
otherwise authorized by the changes clause of this contract, should the Force
Protection Condition (FPCON) at any individual facility or installation change, the
Government may require changes in contractor security matters or processes.
• For contractors that do not require CAC, but require access to a DoD
facility or installation: Contractor and all associated sub-contractors
employees shall comply with adjudication standards and procedures using
the National Crime Information Center Interstate Identification Index (NCIC-
III) and Terrorist Screening Database (Army Directive 2014-05/AR 190-13),
applicable installation, facility and area commander installation/facility
access and local security policies and procedures (provided by government
representative); or, at OCONUS locations, in accordance with status of
forces agreements and other theater regulations.
• iWATCH Training: The contractor and all associated sub-contractors shall
brief all employees on the local iWATCH Army program (training standards
provided by the requiring activity ATO). This local developed training will be
used to inform employees of the types of behavior to watch for and instruct
employees to report suspicious activity to the COR. This training shall be
completed within 15 calendar days of contract award and within 15calendar
days of new employees commencing performance with the results reported
to the COR NLT 15 calendar days after contract award.
• Physical Security & Key Control: The Contractor shall safeguard all Government
property. No keys or key cards issued by the Government shall be duplicated.
Lost keys must be reported immediately to the COR.
-- 2 of 12 --
31 July 2026
2.0 Definitions and Acronyms:
2.1 Definitions:
• Allied Support: Supporting construction (concrete pads, trenching, utility lines)
paid for by Civil Engineering/MILCON funds, distinct from RLF lease costs.
• Contractor: The modular leasing vendor awarded this contract.
• Leasing Services: The provision of relocatable structures, setup, wear-and-tear
maintenance, and eventual removal at the end of the lease.
• Requirement Owner: The 116th Wing/GA Air National Guard, responsible for
funding the RLF lease, installation, maintenance, and removal.
2.2 Acronyms:
• BMP: Best Management Practice
• COA: Course of Action
• COS: Cyber Operations Squadron
• EISA: Energy Independence and Security Act
• FOC: Full Operating Capability
• GPC: Georgia Power Company
• IOC: Initial Operating Capability
• MCCA: Military Construction Cooperative Agreement
• MS4: Municipal Separate Storm Sewer System
• PEA: Programmatic Environmental Assessment
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S):
3.1 Site Preparation:
The Government will provide a pre-developed, unpaved, compacted earth and grass lot
at the corner of 31st Street and Lane Avenue. The site has been historically utilized for
relocatable buildings and was previously brought into compliance with EISA Section
-- 3 of 12 --
31 July 2026
438 stormwater requirements. No additional grading, leveling of the general terrain, or
concrete pad pouring should be required.
Trailer Layout Reconf…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 532120)
Ft Gordon Trailer Lease
DEPT OF DEFENSE · Solicitation · due August 31, 2026
W065--Mobile MRI Trailer and Technologist Services
VETERANS AFFAIRS, DEPARTMENT OF · Sources Sought · due September 4, 2026
NNMC: Lease of Mobile Sterile Processing Unit
HEALTH AND HUMAN SERVICES, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 25, 2026
NOTICE OF PROCUREMENT VIA GSA eBUY (INFORMATIONAL PURPOSES ONLY) Mobile SPU/SPD Trailer (WBAMC)
DEPT OF DEFENSE · Special Notice · due August 31, 2026
Ft Gordon Trailer Lease
DEPT OF DEFENSE · Presolicitation · due September 1, 2026
RENTAL OF TWO (2) MOBILE SHOWER FACILITY TRAILERS
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 3, 2026