What this opportunity is
This federal contracting opportunity is for a small business to repair the historic stone retaining wall at the Mesa Falls Grandview Overlook in the Caribou-Targhee National Forest, Idaho. The project is set aside for small businesses and has a NAICS code of 238140, which pertains to foundation, structure, and building exterior contractors. The notice type is a Combined Synopsis/Solicitation, indicating that interested parties should track the solicitation for updates rather than submitting a bid immediately.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-1
Section C - Description/Specifications/Statement of Work
GENERAL SPECIFICATIONS
Mesa Falls Grandview Overlook Retaining Wall Repair
1.1 SCOPE OF CONTRACT
A. This project includes repairing the historic stone retaining wall at the Mesa Falls
Grandview Overlook.
1.2 PROJECT LOCATION
A. The project is located on the Ashton-Island Park District of the Caribou-Targhee National
Forest, Fremont County, Idaho. It is located at LAT 44.174916°, LONG -111.314911°
1.3 SITE INFORMATION AND LIMITATIONS
A. The following site conditions are considered incidental to the contract and the contractor
will not be paid directly for any of the following items:
1. Construction site will be occupied by employees and the public. The Contractor
will be responsible for signing and limiting access.
2. Utilities are not available at the site for construction purposes.
3. Government toilet facilities are available at the site during all construction work.
1.4 TRAFFIC CONTROL AND CONSTRUCTION SIGNING
A. No work that endangers, interferes, or conflicts with traffic or access to work sites shall
be performed until a plan for satisfactory warning and handling of traffic has been
submitted by the contractor and approved by the COR and Idaho Department of
Transportation. Construction signing for traffic control shall conform to the Manual of
Uniform Traffic Control Devices (MUTCD). All traffic control signs will be placed in
areas adequate for a truck pulling a fifth wheel trailer to be turned around. Contractor
shall not be paid directly for this item, rather it will be considered incidental to other items
of work listed in the Schedule of Items.
1.5 WORK CAMPS, STAGING AND STORAGE AREAS
A. Areas for staging operations and storage of materials shall be approved by the CO. The
Contractor must request in writing for approval from the CO to stage work trailers on site.
B. No overnight camping will be allowed at the project site
1.6 INSPECTION OF WORKSITE
A. The contractor acknowledges they have taken the necessary steps to ascertain the nature
and location of work, and have investigated and satisfied themselves as to the general and
local conditions that can affect the work or its cost. Any failure of the contractor to take
the actions described and acknowledged in this paragraph will not relieve the Contractor
-- 1 of 28 --
SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK 000001-2
from the responsibility of estimating properly the difficulty and cost of successfully
performing the work, or for proceeding to successfully perform the work without
additional expenses to the government.
1.7 START DATE
A. To be determined.
1.8 CONTRACT TIME
A. Base Bid: 60 days.
1.9 SPECIFICATIONS
A. The following specifications are attached. Some sections in the schedule of items refer
to other sections not listed and are subsidiary to, or are included in payment for other pay
items in this contract. These items are considered incidental and no additional
compensation will be made.
Section 011250 - Measurement And Payment
Section 011900 - Mobilization
Section 013300 - Submittal Procedures
Section 013591 - Historic Treatment Procedures
Section 014100 - Quality Control
END OF SECTION C
May 2026
-- 2 of 28 --
MEASUREMENT AND PAYMENT 011250-1
USDA FOREST SERVICE, R4
Mesa Falls Grandview Overlook Retaining Wall Repair
SECTION 011250 - MEASUREMENT AND PAYMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Measurement and payment for contract work will be made only for and under those pay
items included in the Schedule of Items. All other work, labor, materials, equipment, and
incidentals necessary to successfully complete the project will be considered as included
in the payment for items shown. This section defines the method of measurements and
basis of payment for work items listed in the Schedule of Items.
B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items
for any pay item, suffixes will be added to the item number to differentiate between the
pay items.
1.2 DETERMINATION OF QUANTITIES
A. The following measurements and calculations shall be used to determine contract
quantities for payment.
1. For individual construction items, longitudinal and lateral measurements for area
computations shall be made horizontally or corrected to horizontal measurement
unless otherwise specified. Measurements for geotextiles, netting and erosion
control blankets shall be along slope lines.
2. For excavation or embankment volumes, the average end area method shall be used
to compute volumes. However, if in the judgment of the Contracting Officer (CO),
the average end area method is impractical, measurement shall be made by volume
in hauling vehicles or by other three-dimensional methods.
3. For Structures, they shall be measured according to neat lines shown on the
drawings or as altered by the CO, in writing, to fit field conditions.
4. For items that are measured by the linear foot, such as pipe culverts, fencing,
guardrail, piping, utilities, and underdrains, measurements shall be made parallel to
the base or foundation upon which the structures are placed.
5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture
content, unless otherwise provided for.
6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe
conduits) identified by gauge, weight, section dimensions, and so forth, such
identifications shall be considered the nominal weights or dimensions. Unless
controlled by tolerances in cited specifications, manufacturer's tolerances shall be
accepted.
B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the
tolerances specified in this contract, or shifts of balance points up to 100 feet shall be
-- 3 of 28 --
MEASUREMENT AND PAYMENT 011250-2
made by the contractor as necessary to produce the designed sections and to balance
ea…
Source: SAM.gov, as posted. Verify the current solicitation before responding.