The Department of Defense is soliciting a total small business set-aside for the INDIG Village Demolition project, which involves providing labor, materials, heavy equipment, and supervision for demolition, debris removal, and grading in Virginia. This opportunity suits small businesses in the construction sector, specifically those classified under NAICS 238910. Interested contractors should note that this is a solicitation notice, indicating that they should prepare to submit bids based on the detailed Performance Work Statement provided in the solicitation attachment.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Explosive Ordnance Disposal Training & Evaluation Unit TWO
Solicitation N0018926QL133 – INDIG Village Demolition
Questions and Responses
CUI
CUI
1. Question: The PWS states that foundations and below-grade structures are to be removed and excavations
restored; however, no specific backfill specification was identified.
Please confirm:
• Required backfill material type (common fill, structural fill, borrow fill, select fill, crushed
aggregate, etc.).
• Whether imported material is required or if suitable on-site material may be reused.
• Compaction requirements
• Testing requirements and responsibility for geotechnical verification
Response: Structural fill; onsite material may be reused as long as compaction requirements are met;
compaction requirements are 2,500 lbs. per sq. ft. of barring capacity; provide customer verification of
testing
2. Question: The PWS references grading and stabilization but does not provide detailed specifications.
Please confirm:
• Required final stabilization method:
o Seed and straw
o Hydroseed
o Temporary seed
o Permanent turf establishment
o Erosion control matting
o Other
• Required seed mix specifications.
• Topsoil requirements, if any.
• Required stabilization timeframe following demolition activities.
Response: Leave area bare, no stabilization preference.
3. Question: Please confirm that all existing building with concrete slabs and paved surfaces are to remain in
place unless specifically noted otherwise.
Response: Correct, please refer to site map attachment.
4. Question: The solicitation documents do not appear to include an asbestos survey, hazardous materials
assessment, or abatement report.
Please provide:
• Existing asbestos survey reports.
• Hazardous materials assessment reports.
• Lead-based paint survey reports (if applicable).
• Confirmation that all hazardous material identification and abatement has been completed prior
to contractor mobilization.
If no reports are available, please confirm that no asbestos-containing materials (ACM), lead-containing
materials, PCB-containing equipment, or other regulated hazardous materials are present within the
contractor’s scope of work.
Response: No reports available and no awareness of any asbestos, lead or PCB containing material
within the contractor’s scope of work.
5. Question: Please clarify the status of all above-ground and below-ground fuel storage systems.
-- 1 of 8 --
Explosive Ordnance Disposal Training & Evaluation Unit TWO
Solicitation N0018926QL133 – INDIG Village Demolition
Questions and Responses
CUI
CUI
Please confirm:
• All tanks will be emptied, cleaned, disconnected, and certified safe prior to demolition activities.
• The Government will remove all fuels, oils, and regulated contents before contractor .
• The existing fuel tank identified during the site visit is to remain in place and is excluded from
demolition.
• Any associated piping, dispensers, monitoring systems, or electrical equipment associated with
the fuel system that are to remain.
Response: No fuel tanks or lines being removed.
6. Question: Please confirm that all utilities serving the structures have been disconnected and rendered safe
prior to demolition, including:
• Electric
• Water
• Sewer
• Telecommunications
• Gas/Fuel
• Fire protection systems
Please identify any active services that must remain operational during construction.
Response: There are no utility services to the compound.
7. Question: Please verify that of the 23 Structures and 6 wall sections all consist of wood excluding
foundation and footings. Specifically, there are 6 large "Concrete" Structures in the rear that are not
included in the Solicitation, nor any other loose item other than the 23 and 6 Wood structures.
Response: The concrete structures remain, please refer to site map attachment.
8. Question: Please verify there are no underground utilities required demolition attached to foundations
designated Demo structures?
Response: No underground utilities.
9. Question: PWS number 7. States No debris is left on site which could impede grading, verify debris is
referencing only debris of the 23 and 6 structures not debris for the entire site?
Response: Debris refers to the 23 and 6 structures.
10. Question: Material left inside structures such as dummy ammo must be turned in through proper DOD
procedures verify Customer will clear any simulated ammo on site prior to work beginning?
Response: Buildings will be cleared by EOD prior to demolition.
11. Question: PWS Number 8. States COMPREHENSIVE grading of the ENTIRE site (a.) Please verify
Entire site i.e. Fence to fence or only demo area of structures? (b.) Please verify Comprehensive grading
without set of engineered plans with established elevations and bench. Simply rough grading to allow for
good drainage of rain fall is not comprehensive. Please verify if the Customer will provide their desired
elevations and gradients to meet the task stated?
Response: a) only demo area of structures b) grading needs to be level to current grade and compaction
requirements at 2,500 lbs. per sq. ft. of barring capacity.
-- 2 of 8 --
Explosive Ordnance Disposal Training & Evaluation Unit TWO
Solicitation N0018926QL133 – INDIG Village Demolition
Questions and Responses
CUI
CUI
12. Question: PWS Number 10. Is very vague in that preparing of sub grade prior to a future "Phase two"
without knowing if there will be required material needed such as fill; specifically, without known
elevations or known SPECIFICATION. Will the Customer provide the required specification?
Response: Grading needs to be level to current grade and compaction requirements at 2,500 lbs. per sq.
ft. of barring capacity.
13. Question: In the original solicitation packet Period of Performance on page 6 states over 90 days, please
verify Contract is for 60 days?
Response: The period of performance is from date of award through 60 days after award. Once awarded,
these dates will reflect the exact 60 days.