Attachment 1- Scope of works — Kitchen Renovation
RFQ 19FR6326Q0097
1 | P a g e 1 4
STATEMENT OF WORK FOR
Consular Affairs, B-building
Location:
2 Avenue Gabriel, Paris 75008, France
Client:
Embassy of the United States of America in Paris
Date:
July 17 , 2026
-- 1 of 14 --
Attachment 1- Scope of works — Kitchen Renovation
RFQ 19FR6326Q0097
2 | P a g e 1 4
I. PROJECT OVERVIEW:
This project comprises the full renovation of the kitchen breakroom in Room B15, Building B, at
the U.S. Embassy Paris. Works shall be organized into two lots:
Lot 1 covers the complete fit-out of the kitchen space, including demolition of all existing
equipment and finishes; installation of new ceramic floor and wall tiling throughout the room;
supply and installation of a full kitchen cabinet suite (type IKEA or equivalent) with integrated
appliances (refrigerators, compact oven, and microwave); a custom quartz countertop; a new
stainless steel sink and mixer tap; reinstallation of the existing water fountain; new dedicated
plumbing, drainage, and electrical circuits; and concealed under-cabinet LED lighting with
occupancy sensor control. All works shall comply with applicable French standards (NF DTU
60.1, NF C 15-100, NF DTU 52.2) and a CONSUEL electrical compliance certificate shall be
issued upon completion.
Lot 2 covers the partial demolition of an existing non-load-bearing partition and installation of a
custom steel-framed workshop-style glazed screen (verrière atelier) above 2,000mm finished floor
level. The glazed screen is designed to preserve natural light transmission between the kitchen and
the adjacent open-plan office while providing a defined visual separation. A 200mm coffee bar
shelf shall be installed at the junction between the retained partition and the base of the glazed
screen. All structural calculations shall be certified by an engineer and submitted to the Contracting
Officer's Representative (COR) for approval prior to fabrication.
Both lots shall include site mobilization, protection, cleaning, and waste removal to a licensed
disposal facility upon completion.
All brand-name items are specified for design reference purposes only. The contractor may supply
equivalent products meeting the same dimensional, functional, and aesthetic criteria, subject to
prior written approval.
LOT 1 LOT 2
-- 2 of 14 --
Attachment 1- Scope of works — Kitchen Renovation
RFQ 19FR6326Q0097
3 | P a g e 1 4
II. HEALTH & SAFETY REQUIREMENTS
i) General Obligations
✓ The contractor shall comply with all applicable French health and safety legislation, including
but not limited to:
o Code du Travail (French Labor Code), in particular provisions relating to construction
site safety.
o Décret n° 2004-924 relating to working at height.
o Décret n° 94-1159 and associated regulations on coordination of health and safety on
construction sites (SPS — Sécurité et Protection de la Santé).
o NF C 15-100 for all electrical works.
o NF DTU 60.1 for all plumbing works.
✓ The contractor shall always appoint a competent site supervisor responsible for health and
safety on site during works.
✓ Prior to commencement, the contractor shall submit a site-specific Health & Safety Plan
(Plan Particulier de Sécurité et de Protection de la Santé — PPSPS) to the Contracting
Officer's Representative (COR) for review and approval.
✓ All subcontractors engaged by the contractor are subject to the same health and safety
obligations and must be briefed accordingly before commencing work.
ii) Works in an Occupied and Functioning Embassy Environment
✓ Works are being carried out within an active, occupied U.S. Embassy facility. Embassy staff,
Consular Affairs personnel, and members of the public may always be present in adjacent areas
during normal working hours.
✓ The contractor shall coordinate all works with the COR and the Embassy Facilities Manager
to:
o Agree on permitted working hours prior to commencement. Works generating
significant noise, dust, or disruption (demolition, drilling, grinding, tiling) shall be
scheduled to minimize impact on Embassy operations, and may be restricted to outside
normal Embassy working hours as directed by the COR.
o Provide a minimum of 48 hours' advance notice to the COR before commencing any
phase of work that may cause disruption, noise, or temporary loss of access.
o Obtain all necessary Embassy access authorizations for contractor personnel and
vehicles before work begins. All contractor personnel must carry valid identification
and always comply with Embassy security protocols.
-- 3 of 14 --
Attachment 1- Scope of works — Kitchen Renovation
RFQ 19FR6326Q0097
4 | P a g e 1 4
iii) Site Segregation and Pedestrian Protection
✓ The contractor shall fully segregate the works area from all occupied and circulation spaces
using rigid hoarding, temporary partitions, or equivalent barriers of sufficient height and
stability to prevent unauthorized access and contain dust, debris, and noise.
✓ All barriers shall be clearly marked with warning signage in both English and French
indicating an active construction zone and prohibiting unauthorized entry.
✓ Pedestrian routes adjacent to the works area shall remain clear, safe, and unobstructed at all
times. Where temporary narrowing of a corridor or passage is unavoidable, the contractor shall
provide adequate signage and, where required, a banksman or site marshal to manage
pedestrian flow safely.
✓ Floor protection shall be installed on all circulation routes used by contractor personnel for
access to and from the works area, to prevent damage to existing finishes and to reduce slip
hazards from dust and debris.
✓ No materials, tools, or equipment shall be stored in corridors, stairwells, emergency exits, or
any other shared circulation area.
iv) Dust and Debris Control
✓ The contractor shall implement effective dust suppression and containment
measures throughout all phases of works, including:
o Sealing of all openings, gaps, and ventilation grilles in the …
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 236118)
Kitchen Renovation
STATE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 20, 2026
Renovation and repairs at U.S. Government property- 43/2/20
STATE, DEPARTMENT OF · Solicitation · due August 5, 2026
Armed Forces Retirement Home Sheridan Bldg Construction Services
GENERAL SERVICES ADMINISTRATION · Solicitation · due August 6, 2026
AFHC Repair Quarters 82 and 86, Camp Zama, Japan
DEPT OF DEFENSE · Solicitation · due November 6, 2026
31100PR260000052 - USCG BASE LA LB Building #20 Galley Restrooms Renovations
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 24, 2026
Armed Forces Retirement Home Sheridan Bldg Construction Services
GENERAL SERVICES ADMINISTRATION · Solicitation · due August 6, 2026