The Department of Homeland Security is seeking quotations for the overhaul of solenoid valves, classified under NAICS 336413. This is an unrestricted requirement, meaning it is open to all businesses regardless of size. The contract will be an Indefinite Delivery Requirements type with Firm Fixed Pricing, lasting up to five years. Interested vendors should note that only offers meeting the specified traceability and certification requirements will be considered for award, and this solicitation is a combined synopsis/solicitation, indicating a need for close monitoring rather than formal bidding.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Attachment 2 – Statement of Work (SOW)
Overhaul Solenoid Valve
70Z03826QJ0000112
Page 1 of 7
1.0 Scope
1.1 The United States Coast Guard (USCG) Aviation Logistics Center (ALC), Medium Range
Recovery (MRR) Product Line Division located in Elizabeth City, NC has a requirement for the
overhaul of the following components specified in the following table:
Description: National Stock Number (NSN): Part Number (P/N): Alt. P/N:
Valve, Solenoid 4810-01-102-2473 3213850-3-1 70306-02107-104
1.2 The components are utilized on the MH-60T aircraft. Upon receipt of the components, the
Contractor shall perform Test, Teardown and Evaluation (TT&E) to determine the condition of the
component. Any components where no faults are found (NFF) or the components are determined to be
Beyond Economical Repair (BER) in accordance with (IAW) Section 2.5; the Contractor will be
allowed one of the following firm-fixed prices (FFP) only:
Service: Total:
Firm Fixed Price (FFP)
TT&E/NFF/BER/Scrap Fee TBD at time of award
1.2.1 When a component is found BER, the Contractor shall prepare a failure data report in accordance
with (IAW) Section 2.6. This report shall be included with the returned component. The Contracting
Officer will provide disposition instructions IAW Section 2.5 via a modification for all components
found to be BER.
2.0 Overhaul
2.1 Non-Ready for Issue (Non-RFI) components shall be overhauled and returned to Ready for Issue
(RFI) condition IAW the Original Equipment Manufacturer (OEM) functional performance
specifications. Components shall be overhauled for the specific fault noted on the DD Form 1577-2,
Unserviceable (Repairable) Tag-Material, or CG-1577-A (11-90), Unsatisfactory Report Tag, which will
be attached to each Non-RFI component. The Contractor shall perform an inspection and correct all
deficiencies found. This shall include, but is not limited to, replacement of missing or broken
components and the removal of any foreign matter or corrosion.
2.2 Upon receipt, the Contractor shall update Government Property Records based on the DD Form
1577-2, Unserviceable (Repairable) Tag-Material, CG-1577-A (11-90), Unsatisfactory Report Tag or
Form 1348 information provided and any discrepancies. The Contractor shall account for all end-
components received from, and shipped to, the Government. The Contractor shall provide a copy of its
Government Property Records to the Contracting Officer no later than the 15th of each month.
Government Property Records will include the following minimum information:
• Kit/Equipment/Component Description, P/N, Serial Number (S/N)
• USCG consignee
• Date received
• Status of contract service
-- 1 of 7 --
Attachment 2 – Statement of Work (SOW)
Overhaul Solenoid Valve
70Z03826QJ0000112
Page 2 of 7
• Expected contract service completion date
2.3 Procedures
Overhaul services must be performed IAW the procedures established in this SOW. The documents are
listed in order of precedence. Latest revisions of any instruction or manual shall apply. The information
contained within is not intended to be all inclusive nor to detract from or modify procedures outlined in
the manuals. If the applicable technical manual does not cover a procedure, the Contractor shall utilize
the OEM overhaul manual. If the OEM manual does not cover a procedure, the Contractor shall utilize
the best commercial business practice. Where an application of “best commercial practice” conflicts
with these manuals, the Contracting Officer may approve deviation from requirements. When
applicable, each manual will specify if the Export Control Act applies. The following documents are
required to complete the services required by this acquisition. The USCG does not own, nor can it
provide the technical documents specified herein.
• Depot Maintenance Work Requirement (DMWR), 1-4810-216.
• All OEM shop, inspection, overhaul, repair, or other OEM Component Maintenance Manuals
(CMM).
• All OEM service bulletins, amendments, modifications, and specifications as applicable.
2.3.1 The Contractor shall have access to required overhaul specifications and test/acceptance criteria
and data to ensure all components are tested and overhauled IAW the current specifications and
procedures. The USCG may review overhaul manuals and performance/test acceptance criteria as
required. The Contractor is solely responsible for obtaining all specifications required for this effort.
Original design or functional capabilities of the end component and components thereof shall not be
changed unless authorized or directed by the requirements of this SOW.
2.4 Test, Teardown and Evaluation (TT&E)
If, after visual and functional inspections, a component is found to be in RFI condition and NFF or is
considered to be BER IAW Section 2.5, the contractor will be allowed the FFP TT&E/NFF/BER/Scrap
Fee only. If found BER, the Contractor shall prepare a failure data report IAW Section 2.6. This report
shall be included with the returned component. The parts shall be marked "RFI” or “BER” and returned
IAW Section 2.5. A copy of the failure data report shall be attached to the invoice.
2.5 Beyond Economic Repair (BER)
In the event a component cannot be overhauled to like new condition and is found to be BER, the
Contractor shall immediately stop working on the component and notify the Contracting Officer in
writing. The Contractor’s written notification shall include the following information at a minimum:
contract number, delivery order number, contract line-item number (CLIN), nomenclature, NSN, P/N,
S/N, and a brief description supporting the determination. The Contracting Officer will provide
disposition instructions via modification within thirty (30) calendar days after receipt of notification.
The Contractor will be authorized the FFP TT&E/NFF/BER/Scrap Fee only.
(Remainder of Page Intentionally Left Blank)
-- 2 of 7 --
Attachment 2 – Statement of Work (SOW)
Overhaul Solenoid Valve
70Z03826QJ0000112
Page 3 of 7
2.6 Failure Data Report
The …