NASA is seeking engineering services for the Aeolus Wide Field Context Camera (WFCC) lens development project, focusing on design evaluation and development options for a flight-qualified lens. This opportunity is set aside for total small businesses under NAICS 541715. Interested firms should have a minimum of 10 years of experience in designing space-qualified optics and relevant academic qualifications. As this is a combined synopsis/solicitation notice, businesses should track the opportunity closely for submission details rather than prepare a formal bid at this stage.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
STATEMENT OF WORK
Aeolus Wide Field Context Camera (WFCC)
Lens Design Option Evaluation
Prime Contract No. Page 1 of 2 RFP No.
BACKGROUND
NASA is developing the Aeolus instrument suite to investigate the processes driving seasonal cycles of
dust and water ice on Mars by systematic observation of its atmosphere from orbit. Within this suite, the
Aeolus Wide Field Context Camera (WFCC) provides aerosol abundance context for the energy balance
observations made by the other Aeolus instruments.
This task will evaluate design and development options for the Aeolus WFCC lens. Engineering tasks may
include simulation, modeling, and analysis. Additionally, tasks may involve estimation of costs and schedule
for different options, as well as identification of suitable previously flight qualified lenses options, or suitable
COTS or modified COTS lens options.
OBJECTIVE
The objective of this task is to evaluate options for the development of a flight qualified lens for the Aeolus
WFCC. The options of interest are:
• Development of a “clean sheet” design.
• Reuse of a flight qualified lens design, or minor modification thereof.
• Use of a COTS lens with minor or significant modifications.
REQUIRED QUALIFICATIONS
• A demonstrated history of successfully designing, developing, and delivering flight lenses for
deep space orbiter imaging systems meeting schedule, performance, and environmental
requirements.
• A minimum of 10 years designing space qualified optics.
• MS in optical sciences, physics, or related fields.
SCOPE OF WORK
The Subcontractor will be responsible for performing the following tasks:
1. Perform preliminary lens design work for a “clean sheet” design meeting field of view (FOV), sharpness,
chromatic aberration, and image circle size requirements. A final optimized design is not desired, but
evaluation should be sufficient to:
a. Establish the likelihood of meeting provided performance requirements
b. Provide rough estimates of the size and mass of the lens
c. Provide rough order of magnitude (ROM) cost and schedule estimates.
2. Evaluate the option of using an existing flight qualified lens design or minor modification thereof,
meeting FOV, sharpness, chromatic aberration, and image circle size requirements. Of particular
interest are modifications of the VIPER mission NavCam lens design, including replacement of the
bandpass filter in the current design with a clear window in a dual camera approach, or using existing
lens elements in a fisheye lens design. The evaluation should be sufficient to:
a. Establish the likelihood of meeting provided performance requirements.
b. Provide rough order of magnitude (ROM) cost and schedule estimates.
3. Evaluate the option of using a modified COTS lens for the WFCC, meeting FOV, sharpness, chromatic
aberration, and image circle size requirements. This task may involve contacting COTS vendors for
lens design details to identify promising candidates. Of particular interest are vendors with radiation
tolerant designs. The evaluation should be sufficient to:
a. Establish the likelihood of meeting provided performance and environmental requirements.
b. Provide rough order of magnitude (ROM) cost and schedule estimates.
-- 1 of 2 --
STATEMENT OF WORK
Aeolus Wide Field Context Camera (WFCC)
Lens Design Option Evaluation
Prime Contract No. Page 2 of 2 RFP No.
PERIOD OF PERFORMANCE
120 hours. Upon Award Date thru [TBD]
TRAVEL REQUIREMENTS
No travel is required.
MILESTONES/DELIVERABLES
No Milestone Due Date
Reporting
2 Weekly status meetings Recurring
Evaluate Design Options
3 Deliver assessment of the “clean sheet” design option [TBD]
4 Deliver assessment of the option to reuse a flight qualified lens
design, or minor modification thereof
[TBD]
5 Deliver assessment of the option to use a modified COTS lens [TBD]
ACCEPTANCE CRITERIA
Subcontractor work will be deemed accepted when the following performance criteria have been met:
Progress reporting
• Weekly meetings: current disposition of work
Delivered Documentation
• Written evaluations of the options investigated.
• Any Zemax models or simulations developed.
-- 2 of 2 --