Replace Magnolia DFAC AHUs
DEPT OF DEFENSE
Notice type
Solicitation
Solicitation #
FA301026R0008
NAICS
238220
PSC
N041
Set-aside
Service-Disabled Veteran-Owned Small Business Set Aside
Posted
May 26, 2026
Response due
June 5, 2026
Place of performance
Biloxi, MS
What this opportunity is
The Department of Defense is seeking a contractor to replace three air-handling units and an overhead door air curtain at the Magnolia Dining Facility in Mississippi. This solicitation is set aside for Service-Disabled Veteran-Owned Small Businesses, making it suitable for eligible small firms. Proposals are due on June 5, 2026, and interested bidders should note that funds are not currently available, meaning no awards will be made until funding is secured.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
MAHG241006
Mar 2026
Page 1 of 18
V16-CONS-03/12/26
STATEMENT OF WORK
Replace AHU’s Magnolia Dining Hall B7409
MAHG241006
1.0 INTRODUCTION:
The contractor shall furnish all equipment, labor, supervision and materials necessary to
replace three air-handling units (AHU) located within the mechanical rooms of Magnolia
Dining Facility, B7409. Additionally, the contractor is to replace the kitchen overhead door
air curtain. This project includes the replacement of motors and bearings of eight kitchen
supply fans, eight kitchen exhaust fans, and six additional exhaust fans located on the rooftop
of B7409. All work is to be performed in accordance with this statement of work and is
subject to the terms and conditions of the contract.
2.0 ACRONYMS/DEFINITIONS:
ACM - Asbestos Containing Material
AF - Air Force
AFB - Air Force Base
AFI - Air Force Instruction
AHU - Air Handling Unit
APR - Air Purifying Respirator
BMP - Best Management Practice
BOS - Base Operating Support
C&D - Construction and Demolition
CE - Civil Engineering
CES - Civil Engineer Squadron
CEV - Civil Engineering Environmental
CFR - Code of Federal Regulations
CM - Contract Monitor/Construction
Manager
CO - Contracting Officer
CUI - Controlled Unclassified
Information
DOD - Department of Defense
EISA - Energy Independence and
Security Act
EPA - Environmental Protection Agency
FPCON - Force Protection Condition
FOIA - Freedom of Information Act
FT - Foot
GFCI - Ground Fault Circuit Interrupter
HEPA - High Efficiency Particulate Air
(filter)
IAW - In Accordance With
IBC - International Building Code
IN – Inch
KEF-Kitchen Exhaust Fan
KSF-Kitchen Supply Fan (Make-Up Air
Unit)
LBP - Lead Based Paint
LF - Linear Feet
MDEQ - MS Department of
Environmental Quality
MDOT - Mississippi Department of
Transportation
MSS - Material Submittal Schedule
MAU - Make-up Air Unit
NEC - National Electric Code
NFPA - National Fire Protection
Association
OSHA - Occupational Safety and Health
Act
PM - Project Manager
POC - Point of Contact
PPE - Personal Protection Equipment
RAMS - Random Antiterrorism
Measures
RCRA - Resource Conservation and
Recovery Act
RFI - Request for Information
SDS - Safety Data Sheets
SF - Square Foot
SOW - Statement of Work
SWPPP - Storm Water Pollution
Prevention Plan
SY - Square Yard
UFC - United Facilities Criteria
WT - Work Task
TAB - Test, Adjust and Balance
Attachment 1
FA301026R0008
-- 1 of 18 --
MAHG241006
Mar 2026
Page 2 of 18
V16-CONS-03/12/26
3.0 PROJECT DESCRIPTION
3.1 LOCATION: This project is to be performed at Magnolia Dining Hall, B7409 at Keesler
Air Force Base, Biloxi MS
3.2 DESCRIPTION OF WORK:
3.2.1 The Contractor is urged and expected to examine the site and make note of all
requirements of the work before submitting any proposals. The Contracting
Officer (CO) will provide drawings, specifications, and documents relevant to this
requirement. The Contractor shall check all drawings furnished immediately upon
receipt and notify the CO of any discrepancies. The Contractor shall be
responsible for any errors that might have been avoided by complying with these
procedures set forth. Any accessories or incidental items not specifically shown
on the Drawings and detailed in the SOW herein, which are necessary and/or
required to complete the work within the intent of these documents, shall be
included by the Contractor without additional cost to the Government. All work
shall be performed in strict accordance with the SOW/Specifications/Drawings,
and subject to the terms and conditions of this contract.
3.2.2 Utilities from the work will be provided by the Government unless otherwise
noted.
3.2.3 It is not anticipated that hazardous material will be encountered during work.
However, should such material be encountered, the Contractor is to immediately
stop work and contact the CO.
3.2.4 SCOPE:
3.2.4.1 GENERAL NOTES:
3.2.4.1.1 Replace AHUs in kind, as per the Mechanical Schedule
provided within the drawings.
3.2.4.1.2 Replace supply and exhaust fans. The contractor shall conduct
a survey of the exhaust and supply fans being replaced within
the scope of the contract to determine the types to replace in
kind. Refer to the Mechanical Schedule provided within the
drawings.
3.2.4.1.3 Any anticipated work tasks that could negatively impact food
service operations shall be coordinated with the CM prior to
beginning that work task.
3.2.4.1.4 Air-handlers will be replaced, in sequence, one after the other,
during the evening hours to limit negative effects on the dining
hall operations. Normal operations of this facility will continue
during the performance of this work task.
3.2.4.1.5 All fans are to be replaced within (14) calendar days to limit
the complete shutdown of the dining hall. Additional work
tasks can be performed concurrently.
3.2.4.1.5.1 **Schedule this (14) day work task with CM
and facility manager 14 days prior to start of
work. This facility is not intended to be
operational during this 14-day period only.**
3.2.4.2 PHASING:
-- 2 of 18 --
MAHG241006
Mar 2026
Page 3 of 18
V16-CONS-03/12/26
3.2.4.2.1 Phase I: Survey of materials to be replaced, 5 calendar days
3.2.4.2.2 Phase II: Submittals and Material Procurement, 90 calendar
days
3.2.4.2.3 Phase III: Installation of new materials, 45 calendar days
3.2.4.2.4 Phase IV: Testing and balancing and Project Closeout, 5
calendar days
3.2.4.3 DEMOLITION:
3.2.4.3.1 Demolish three existing air-handlers and replace them in kind.
Demolish AHU includes removing old breakers, disconnect
switches and wiring. Only one AHU can be demolished at a
time.
3.2.4.3.2 Demolish and replace all exhaust fans and supply (make-up
air) fans.
3.2.4.3.3 All materials to be demolished shall be removed from the site
and disposed of off-site in a legal landfill. The contractor is not
allowed to stockpile demolition materials on site; all materials
to be removed in a timely fashion.
3.2.4.4 NEW CONSTRUCTION:
3.2.4.4.1 Mechanical:
3.2.4.4.1.1 Install three new AHUs.
3.2.4.…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238220)
N--George Washington Birthplace National Monument- RE
INTERIOR, DEPARTMENT OF THE · Solicitation · due June 26, 2026
RFQ - RFQ - 19ZA6026Q0004 - FAC NEC CHILLER MAINTENANCE- FAC NEC CHILLER MAINTENANCE
STATE, DEPARTMENT OF · Solicitation · due July 20, 2026
Installation of an Engineered Fire Suppression System
DEPT OF DEFENSE · Solicitation · due June 25, 2026
J045--High Pressure Steam Piping Replacement
VETERANS AFFAIRS, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 6, 2026
1698- CE Chiller Maintenance/Service Recompete
DEPT OF DEFENSE · Solicitation · due June 22, 2026
VGLZ 252018 - Repair HVAC Building 303
DEPT OF DEFENSE · Presolicitation