Sustain Hangar Doors, Multi QJKL260019
SECTION 01 11 00
SUMMARY OF WORK
02/24
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" or "S"
classification. Submittals not having a "G" or "S" classification are for
Contractor Quality Control approval. Submit the following in accordance
with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes furnishing of all labor, materials, and equipment and
performance of all work to sustain hangar door paint and incidental
related work on buildings 821 and 870, in accordance with the contract
drawings and specifications.
1.2.2 Location
The work is located at the 934th Airlift Wing, approximately as
indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this
Contract.
Before work is started, arrange with the Contracting Officer a sequence of
procedure, means of access, space for storage of materials and equipment,
and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
Remove or alter existing work in such a manner as to prevent injury or
damage to any portions of the existing work which remain.
Repair or replace portions of existing work which have been altered during
construction operations to match existing or adjoining work, as approved
by the Contracting Officer. At the completion of operations, existing
work must be in a condition equal to or better than that which existed
before new work started.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 11 00 Page 1
Revision 1 07-13-2026
-- 1 of 64 --
Sustain Hangar Doors, Multi QJKL260019
-- End of Section --
SECTION 01 11 00 Page 2
Revision 1 07-13-2026
-- 2 of 64 --
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES
Sustain Hangar Doors, Multi
01 33 00 SD-01 Preconstruction Submittals
1.7 G Submittal Register
01 74 19 SD-01 Preconstruction Submittals
1.5 G Construction Waste Management
Plan
SD-11 Closeout Submittals
1.7 G Final Construction Waste
Diversion Report
02 83 00 SD-01 Preconstruction Submittals
1.5.1.1 G Competent Person
1.5.1.2 G Training Certification
1.5.2.6 G Lead Waste Management Plan
1.5.2.2 G Lead Compliance Plan
3.4.2.1 G Written Evidence of TSD
Approval
SD-11 Closeout Submittals
3.4.2.1 G Hazardous Waste Manifest
3.4.2.1 G Turn-In Documents or Weight
Tickets
09 90 00 SD-03 Product Data
2.1 Product Data Sheets
SD-04 Samples
2.2 G Color
SD-08 Manufacturer’s Instructions
3.2.1 Application Instructions
2.1 Mixing
SUBMITTAL REGISTER CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A
C
T
I
V
I
T
Y
N
O
T
R
A
N
S
M
I
T
T
A
L
N
O
S
P
E
C
S
E
C
T
DESCRIPTION
ITEM SUBMITTED
P
A
R
A
G
R
A
P
H
#
C
L
A
S
S
I
F
I
C
A
T
I
O
N
G
O
V
T
O
R
A
/
E
R
E
V
W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A
C
T
I
O
N
C
O
D
E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A
C
T
I
O
N
C
O
D
E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Revision 1 07-13-2026
-- 3 of 64 --
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES
Sustain Hangar Doors, Multi
09 90 00 1.7.1 Manufacturer's Safety Data
Sheets
SUBMITTAL REGISTER CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A
C
T
I
V
I
T
Y
N
O
T
R
A
N
S
M
I
T
T
A
L
N
O
S
P
E
C
S
E
C
T
DESCRIPTION
ITEM SUBMITTED
P
A
R
A
G
R
A
P
H
#
C
L
A
S
S
I
F
I
C
A
T
I
O
N
G
O
V
T
O
R
A
/
E
R
E
V
W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A
C
T
I
O
N
C
O
D
E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A
C
T
I
O
N
C
O
D
E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
Revision 1 07-13-2026
-- 4 of 64 --
Sustain Hangar Doors, Multi QJKL260019
SECTION 01 33 00
SUBMITTAL PROCEDURES
08/18, CHG 4: 02/21
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples
and descriptions of submittals identified by the Submittal Description
(SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Government approved Division 01 preconstruction submittals that are
required prior to or commencing with the start of work must be submitted
within 30 calendar days of contract award unless specified elsewhere in
the specifications. Contractor approved Division 01 submittals that are
required prior to or commencing with the start of work must be submitted
within 45 calendar days of contract award unless specified elsewhere in
the specifications.
Preconstruction Submittals include schedules and a tabular list of
locations, features, and other pertinent information regarding
products, materials, equipment, or components to be used in the work.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Construction Schedule
Submittal Register
Schedule Of Prices Or Earned Value Report
Work Plan
SD-03 Product Data
Catalog cuts, illustrations, schedules, diagrams, performance charts,
instructions and brochures illustrating size, physical appearance and
other characteristics of materials, systems or equipment for some
portion of the work.
Samples of warranty language when the contract requires extended
product warranties.
SD-04 Samples
SECTION 01 33 00 Page 1
Revision 1 07-13-2026
-- 5 of 64 --
Sustain Hangar Doors, Multi QJKL260019
Fabricated or unfabricated physical examples of materials, equipment
or workmanship that illustrate functional and aesthetic
characteristics o…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238320)
Utility Building Exterior & Interior Wall Repairs
STATE, DEPARTMENT OF · Solicitation · due July 27, 2026
Z1DZ--531-26-3-5043-0091 Exterior Painting Boise VAMC BLDGS 4, 124, 120
VETERANS AFFAIRS, DEPARTMENT OF · Solicitation · due July 21, 2026
KES Enclosure Painting services
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 31, 2026
Carson National Fish Hatchery Quarters 4 Interior
INTERIOR, DEPARTMENT OF THE · Combined Synopsis/Solicitation · due August 22, 2026
Z1DZ--531-26-3-5043-0091 Exterior Painting Boise VAMC BLDGS 4, 124, 120
VETERANS AFFAIRS, DEPARTMENT OF · Presolicitation
Refurbish/Repaint Antenna Towers
TRANSPORTATION, DEPARTMENT OF · Solicitation · due July 20, 2026