The U.S. Department of the Interior is seeking an Architect-Engineer (A-E) firm to provide Construction Administration Services for the renovation of the Great Plains Nature Center in Wichita, KS. This opportunity falls under NAICS 541330 and is suitable for small businesses, particularly those with expertise in architectural and engineering services. Interested firms should note that this is a solicitation notice, indicating a requirement to track the opportunity closely and prepare to submit proposals rather than simply express interest.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Construction Administration Services
Great Plains Nature Center Page 1 of 7
Title III Statement of Work
Project GPNC-101
Construction Administration Services
Great Plains Nature Center Renovation
United States Fish and Wildlife Service
Great Plains Nature Center, Wichita, KS
June 2026
1.0 General Information
1.1 This project is for an Architect-Engineer (A-E) to provide Construction Administration
Services (Title III Services) for the Great Plains Nature Center Renovation project.
1.2 The A-E shall provide a list of key personnel for approval to the Contracting Officer
(CO) in conjunction with the price proposal for this contract. Key personnel shall not
change during the performance of this contract unless written approval is obtained from
the Contracting Officer.
1.3 Period of performance for Title III Services will be from the date of contract issuance
until 300 days, unless modified by the Contracting Officer. The work of this contract shall
be provided from approximately October 2026 – August 2027. The intent is to provide
support to the Great Plains Nature Center Renovation project, from solicitation through
completion of construction.
1.4 All architectural and engineering design work produced under this contract shall be
performed in accordance with applicable codes and accepted industry. All work shall be
under the direct supervision of a professional architect/engineer licensed in the State of
Kansas. All design work performed under this contract shall be stamped.
2.0 Acronyms
A-E Architect-Engineer Firm
CO Contracting Officer
COR Contracting Officer’s Representative
MEP Mechanical/Electrical/Plumbing
-- 1 of 7 --
Construction Administration Services
Great Plains Nature Center Page 2 of 7
QA Quality Assurance
QCP Quality Control Plan
RFI Request for Information
USFWS United States Fish and Wildlife Service
3.0 Scope of Work
3.1 Task 1 – Attend Teleconference Construction Support Kick-Off Meeting
a. Participate in teleconference on construction support pre-work meeting. The participating
personnel shall be the Lead Engineer, at the minimum.
b. Provide detailed meeting notes for the contract kick-off meeting.
3.2 Task 2 – Perform Construction Support Services
a. Review and respond to construction originated RFIs, estimated at 25. RFIs arising from
insufficient clarity of construction documents shall be responded to by the A/E at no
additional cost to the Government.
b. Review and approve submittals as identified in A-E prepared “Submittal List” /
Construction Documents. Estimated at 200 submittals.
1. The A/E shall review and recommend to the government that it approve, approve with
notations, or disapprove submittals after thorough review of the construction
documents and applicable standards and codes.
2. Each submittal shall be checked to verify conformance to the Construction
Documents. Corrections to the submittal shall be noted in red.
c. Participate in teleconference construction meetings. For purposes of estimating level of
effort for this contract, the A-E shall assume 44 conference calls which will occur during
the course of construction, lasting approximately 60 minutes, with the initial pre-
construction kick-off meeting expected to last an hour. The construction contractor will
provide the minutes for each meeting; however, the A-E may be required to provide notes
-- 2 of 7 --
Construction Administration Services
Great Plains Nature Center Page 3 of 7
on issues from time to time.
3.3 Task 3 – Provide On-Site Inspections and Reports
a. A-E shall provide competent engineering inspections during the milestone construction
events, and competent construction project field inspections onsite approximately once a
week during active construction, to verify work is completed in compliance with the
construction documents. For purposes of estimating level of effort for this contract, the
A-E shall assume that 14 engineering inspections, and 25 construction field inspections will
occur during the course of construction. The milestone construction events include but not
limits to the following:
Work item Discipline Comment
Helical Piles / Piers Inspection Structural
Finish Site grading Civil
Concrete Lifting and Leveling
Brick Tucking Structural/Architectural
Roof Flashing and Roof Repair Architectural
Exterior Window and Door
Installation (Flashing Inspection)
Architectural
Interior framing Structural/Architectural
Architectural Progress/initial finishes Architectural
HVAC Balancing & Testing MEP Basic Commissioning
Substantial Completion All Architectural/Civil/MEP/Structural
Final Completion Structural/Architectural,
Civil
1. A-E shall verify that the construction contractor is adhering to the requirements
identified in the construction drawings and specifications. If at any time the A-E
discovers that the construction contractor is not performing the work in accordance
with the contract documents, the A-E shall immediately notify the COR and CO in
writing. A-E shall be specific in stating the contractor’s noncompliance and provide
recommended corrective actions.
2. A-E shall verify design assumptions align with actual field conditions. A-E will
propose design modifications with the CO and COR when the field conditions differ.
3. During site visits, A-E shall maintain accurate and complete inspection reports of the
prime contractor and their subcontractors working onsite. At a minimum, the
following information shall be provided for each report:
-- 3 of 7 --
Construction Administration Services
Great Plains Nature Center Page 4 of 7
(a) Weather and general condition of the work site.
(b) Company names, total number of workers onsite.
(c) Number and type of equipment onsite if they are being utilized.
(d) Description of work activities. This shall include the type of activities, location
of activities, and any issues that have developed.
(d) Photographs to document construction progress and/or support any noted
deficiencie…