Z--Road Repairs NEXRAD Battle Mountain/Reno, NV - NWS
COMMERCE, DEPARTMENT OF
Notice type
Combined Synopsis/Solicitation
Solicitation #
1305M326Q0357
NAICS
238990
PSC
Z2LB
Set-aside
Small Business Set Aside - Total
Posted
August 25, 2026
Response due
August 31, 2026
Place of performance
NV
Description
PERFORMANCE WORK STATEMENT
Road Repair at KLRX & KRGX Next Generation Radar (NEXRAD) Sites Near Battle Ground & Reno
Nevada
1. GENERAL INTENTION:
It is the intention of this requirement to improve drainage, removal of excess vegetation for vehicular travel
on the access roads to the National Weather Service (NWS) Next Generation Radar (NEXRAD) sites
located near Battle Mountain, NV (herein KLRX Battle Mountain NEXRAD) and near Reno, NV (herein
KRGX Reno NEXRAD). The roads are in need of rehabilitation to a state that allows for proper water
runoff and safe vehicular travel.
The KLRX Battle Mountain NEXRAD road is approximately 11.7 miles with an estimated maximum slope
of 25%. The access road work will start at 40° 41 '26"N 116° 52' 09"W and end at 40° 44 '22"N 116° 48'
10"W. The road has not been serviced in the past few years and is in need of repair services.
The KRGX Reno NEXRAD road is approximately 6.06 miles with an estimated average slope of 9% with a
max of 22%. The access road work will start at 39°43'19"N 119°31'17"W and end at 39°45'15"N
119°27'43"W. The road was serviced in the past two years and is in need of maintenance services.
2. GENERAL REQUIREMENTS:
The contractor shall provide all supervision, labor, tools, materials and equipment necessary to perform
work as stated. All work and materials supplied shall be in accordance with these instructions,
manufacturer’s specification, all applicable federal, state, local, OSHA, EPA, NEC, NFPA, building and
facilities codes and criteria and accepted trade and industry standards. A bid guarantee (due upon Quote
submission), Payment and Performance bonds will be required (RFO 52.228-15), and the Davis-Bacon Act
will be applicable to this work.
The Contractor Shall:
2.1. Provide a Finalized schedule of work with start and completion dates that have an integrated
payment milestone schedule at least ten (10) days in advance of starting work & in compliance
with the solicitation instructions.
2.2. Accomplish all work according to these instructions and specifications
2.3. Verify all measurements and obtain all permits required for work.
2.4. All work must not impede local traffic and comply with Nevada DOT specifications.
2.5. Ensure all vegetation is cleared alongside the roadway to allow safe traffic flow and fire
protection as per DOT standards.
2.6. Imported aggregate base material must meet Nevada DOT specifications for a Type 1, class A
material.
2.7. Provide all equipment and machinery necessary to complete the project as set forth in these
specifications.
2.8. For KLRX Battle Mountain NEXRAD, provide details in submittal for additional culvert
proposals.
2.9 For the KRGX Reno NEXRAD coordinate all onsite work with local Homeowners Association
(HOA) the Contractor must:
2.9.1. Have dust control measures in place.
PWS | KLRX & KRGX NEXRAD Road Repair
1
-- 1 of 6 --
2.9.2. Adhere to all posted speed limits.
2.9.4. Have work warning signs posted
SURFACE BLADING SPECIFICATIONS:
Description:
Surface blading is keeping the native or aggregate surfaced road in a condition to facilitate traffic,
minimize additional future maintenance, reduce erosion, and provide proper drainage. It includes
maintaining the crown, in-slope or out-slope of the traveled roadway and shoulders, water bars, drainage
dips, leadoff ditches, berms, turnouts, removal of minor slides and slumps, and other irregularities that
prevent normal runoff from the road surface. This routine maintenance extends the road's lifespan and
provides a safer, smoother ride for vehicles. Adding imported material to achieve these desired
conditions is expected.
Requirements:
Blading operations shall be conducted when the aggregate contains sufficient moisture to allow for
optimum compaction and to prevent segregation of fines. The Contractor shall ensure that existing
shoulder aggregates are pulled back into the roadway to maintain the specified width and cross-section
without cutting into the ditch backslopes or contaminating the road surfacing with non-aggregate debris.
Surface blading shall be performed to reshape a gravel road's surface, restoring the correct crown and
potholes or ruts to ensure effective water drainage.
The blading shall be performed in such a manner as to preserve the existing cross section and to
conserve surface materials. On gravel-surfaced roads, the base must not be disturbed and no surface
material may be bladed into the ditch or over the road shoulders. Blading of native surface roads shall be
performed so no base material less than 4 inches in the greatest dimension is lost. All ruts, holes, etc.,
shall be removed by scarifying and/or cutting to the bottom of any surface irregularities. Oversize
material brought to the surface in the scarification process shall be removed from the roadway. Surface
material which has been displaced to the shoulders, turnouts, outside of curves, etc., shall be brought
back so as to leave a uniform depth on the traveled way at completion of blading. Water shall be applied
during blading if sufficient moisture is not present to prevent segregation of fines.
Roadside cut-slopes or berms shall not be undercut.
At intersections, the roadbeds of side-roads shall be graded for a reasonable distance to assure proper
blending of the two riding surfaces.
Drainage dips and leadoff ditches shall be cleaned and continually maintained to conform reasonably to
their original constructed lines, grade, and cross section.
Berms shall be repaired promptly by placing selected material as needed to restore the berm to its
original condition.
All blading operations shall be properly “Signed” in accordance with all applicable State Laws.
Surface blading of native surface roads also includes ditch cleaning, which shall be done in accordance
with the following ditch cleaning specifications.
DITCH CLEANING SPECIFICATIONS:
PWS | KLRX & KRGX NEXRAD Road Repair
2
-- 2 of 6 --
Description:
Ditch cleaning is removing and disposing of all slough …
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238990)
Repair Fence and Expand MEP Lot, PFC Roy M. Reynolds USARC, Parkersburg, WV
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due September 3, 2026
Sliding Gate Safety Deficiencies Remediation
STATE, DEPARTMENT OF · Solicitation · due August 27, 2026
432 SFS Crash Beam Barriers
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due September 17, 2026
B200 Fence and Surveillance Upgrades/Elkhorn Communications Site
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 28, 2026
Furnish and Install Storm Shelters on Capehart Housing, Vance AFB, OK
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due September 2, 2026
Y--BDO BLM ESR RANGE FENCE CONSTRUCTION
INTERIOR, DEPARTMENT OF THE · Solicitation · due September 9, 2026