What this opportunity is
The U.S. Department of State is soliciting bids for chilled and hot water piping interconnection works at the American Embassy in New Delhi, India. This project requires contractors to provide labor, materials, and equipment for a turnkey installation, with a focus on ensuring system efficiency and environmental resilience. As there is no set-aside for small businesses, this opportunity is open to all qualified contractors. Interested parties should note the strict timeline and potential penalties for delays, indicating a need for careful project management.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
SCOPE OF WORK & TECHNICAL SPECIFICATIONS: Chilled & Hot Water
Piping Interconnection Works (Existing Plantroom to New SPX Building)
Location: US Embassy, Enclave Compound New Delhi, India
Project Duration, Target Deadlines: Tentative Start Date is November 16, 2026
and completion date December 21 2026. (40 working days total)
Penalty and Liquidated Damages (LD): Time is the strict essence of this contract
to ensure winter heating is activated by late December 2026."Since heating must be
activated before late December, any delay in handing over the charged pipelines
beyond 20th December the liquidated damages (LD) clause may apply in
accordance with contract clauses FAR 52.211-12 at the rate 1% per calendar day,
the quantum of LD shall be 10% of the contract value".
1. Project Background & Objective
The objective of this project is to hydraulically decouple the existing "CHILLER"
from serving the residential blocks designated as "B Block" and "C Block", and to
seamlessly interconnect these existing distribution loops to the high-capacity central
plant located in the "NEW SPX BUILDING".
The modification will utilize the existing infrastructure routed through a newly
excavated tie-in zone. The final network configuration must guarantee strict
isolation capabilities, dynamic flow balancing, and system parameters monitoring
via accessible underground civil valve chambers (manholes). The design must
withstand the harsh environmental parameters of New Delhi, preventing ground
moisture ingress and condensation thermal losses.
2. Detailed Scope of Work (SOW)
The Contractor shall provide all labor, premium materials, construction equipment,
specialized tools, shoring, excavation machinery, dewatering systems, and
professional supervision required to complete the following works on a turnkey
basis:
-- 1 of 10 --
2.1. Pre-Construction, Mapping & Approvals
• As-Built Verification: Physically survey, map, and verify the exact alignment
depths, material conditions, and coordinates of the existing 250 mm
(CHW)and 200 mm (HW) headers as referenced in the system line schematic.
• Utility Clearance: Conduct rigorous Ground Penetrating Radar (GPR) scans
to mark out buried electrical grids, telecom lines, and water infrastructure.
Obtain utility clearances and permits
• Method Statement: Submit a comprehensive Method Statement, Project
Schedule (Gantt Chart), and localized Risk Assessment (RAMS) detailing
execution steps, focusing on the critical plant shutdown window.
2.2. Civil Excavation & Structural Masonry
• Excavation Operations: Excavate the earth at two distinct tie-in locations
down to the necessary depth of 8 to 10 feet (approx. 2.4 m to 3.0 m) to
establish clear access to the headers. Clear internal structural plan dimensions
must be around 6 feet × 6 feet (1.8 m × 1.8 m).
• Shoring & Trench Safety: Install robust structural timbering or steel sheets
to secure loose soil walls in strict accordance with IS:3764 standards. Keep
the workspace fully dry using continuous automatic dewatering pumps to
handle subsurface water weeping or sudden precipitation.
• Manhole Structural Foundation: Lay a 100 mm thick Plain Cement
Concrete (PCC 1:4:8) mud-mat foundation, followed by a monolithic,
minimum 150 mm thick Reinforced Cement Concrete (RCC) bottom slab of
M25 Grade reinforced with 10 mm TMT bars at 150 mm center-to-center (c/c)
both ways.
• Wall Infrastructure: Construct load-bearing chamber walls using first-class
burnt clay engineering bricks in a unified 1:4 Cement Mortar mix using
Ordinary Portland Cement and graded Stone Dust.
• Surface Finishing: Apply a smooth 10 mm thick cement plaster coat in a 1:4
ratio (cement to clean washed sand) on all internal and external masonry faces,
complete with integrated liquid waterproofing additives.
-- 2 of 10 --
• Structural Top Slab & Access Cover: Cast a heavy-duty, minimum 100 mm
thick structural M25 concrete slab reinforced with 10 mm TMT steel bars at
150 mm c/c both ways. Integrate a 3 feet (900 mm) clear diameter circular
Grade 316 Stainless Steel heavy-duty air-tight frame and cover matching
Class D400 loading characteristics as per IS:1726.
2.3. Mechanical, Valving & Piping Modifications
• Pipe Adaptation: Cut into the existing pipelines and install high-strength
concentric/eccentric carbon steel reducers (300 mm → 250 mm and 300 mm
→ 200 mm) to seamlessly step down the primary distributions arriving from
the New Building into the regional residential circuits.
• Valving Matrix: Mount industrial-grade Butterfly Valves (BFV) for complete
positive isolation lines and Static/Dynamic Manual Balancing Valves (BLV)
positioned on the Chilled Water Return (CHWR) and Heating Water Return
(HWR) lines for precise hydraulic regulation.
• Structural Pipe Supports: Erect structural steel support frames (ISMC
sections conforming to IS:2062) inside the chambers. All piping components
must securely rest on adjustable saddle assemblies with 10 mm thick heavy-
duty neoprene anti-vibration pads to isolate structural loads and prevent
thermal bridging.
• Welding & NDT Inspections: Execute multi-pass butt welding using
certified IBR (Indian Boiler Regulations) or ASME Section IX qualified
welders. Perform 100% Visual Inspection and a minimum of 25%
Radiographic / Magnetic Particle Testing (MPT) on all newly formed field
welds.
• Hydrostatic Testing: Pressurize the newly completed interconnection loop
assembly at 1.5× the maximum working pressure (minimum 10.5 kg/cm² /
150 PSI) and maintain it for an uninterrupted duration of 4 hours. Document
pressure charts prior to wrapping and insulating.
2.4. Thermal Insulation & Anti-Corrosive Protection
• Underground Pipe Protection (External Sections): Clean bare carbon steel
surfaces to SA 2.5 standards, apply two initial coats of anti-corrosive
-- 3 of 10 --
bitumastic primer, and wrap with a 4 mm thick polymer-modified asphaltic
anti-corrosive tape (e.g., Pypk…
Source: SAM.gov, as posted. Verify the current solicitation before responding.