Compound Wall Fall Protection, Rome, Italy
STATE, DEPARTMENT OF
Notice type
Solicitation
Solicitation #
191T7026Q0020
NAICS
238190
PSC
Y1DA
Posted
June 9, 2026
Response due
June 19, 2026
Place of performance
Rome, IT-RM
What this opportunity is
The U.S. Department of State is seeking a contractor for the installation of fall protection for the compound wall at the U.S. Embassy in Rome, Italy, under NAICS code 238190. This solicitation is suitable for small businesses with experience in construction and safety compliance. Interested contractors should note that the work may require after-hours operations at no additional cost, and they will need to manage logistics, materials, and safety measures carefully.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
- 1 -
EMBASSY OF THE UNITED STATES OF AMERICA
Via Veneto 119/A
00187 Rome, Italy
U.S. EMBASSY ROME
COMPOUND WALL FALL PROTECTION
FAC Engineering
05/14/2026
-- 1 of 15 --
- 2 -
FOREWORD
The Embassy of the United States in Rome needs to award a contract for the Compound Wall Fall
Protection.
GENERAL
• The contractor shall supply all the installation materials and equipment, skilled and
unskilled labor, technical supervision, as well as logistic and administrative support. The
contractor shall also supply all accessory services such as: transportation, leasing,
equipment and tools, disposal of debris, cleaning the work area and anything else necessary
to complete the project in compliance with the present specifications
• The COR may schedule some of the operations to be performed after-hours or during the
weekend. These activities shall be performed at no extra cost for the Embassy.
• Maximum attention is required for the safety of personnel at work on the site. The workers
shall operate in compliance with standard codes. In view of the fact that the work site consists
of crucial technical installations, temporary safety protection measures towards third parties
and workers shall be installed with care and attention, especially for the hours when site is
closed.
• The Contractor shall be responsible for submitting, for approval by the COR, samples of
materials and supplies to be used.
• It shall be Contractor's responsibility to verify all the quantities and dimensions.
DEFINITIONS
A glossary of terms and relative equivalents used in the drawing up of the tender documents are
indicated hereunder:
Client, Administration, Project Supervisor, COR, CO: all these denominations identify the
technical administrative staff, predisposed to handle the contract on behalf of the embassy of the
United States of America.
Contracting Company, Contractor: all these denominations identify the subject that undertakes
to carry out the work described in the contract.
Contract, Purchase Order (P.O.), Work Order: these terms identify the contract document with
which the project is awarded. The Client at his indisputable judgment shall make the formal
selection of the different types of documents.
-- 2 of 15 --
- 3 -
PARKING
No parking is allowed inside Embassy grounds. The Contractor's vehicles shall be allowed to enter
only for loading and unloading materials.
Loading and unloading operations shall be carried out using only one vehicle at a time.
Consequently, during the accomplishment of the project the Contractor shall ensure that its
vehicles are parked at its own expense outside the Government property.
SAFETY STANDARDS
The Contractor shall comply with all the applicable health and safety obligations provided by
Legislative Decree No. 81/2008 (Consolidated Law on Occupational Health and Safety). The main
objective is to eliminate or, where not possible, to reduce to the minimum any exposure of workers
to risks arising from work-related activities. To this end, the Contractor is required, when
applicable, to submit the Risk Assessment Document (Documento di Valutazione dei Rischi –
DVR) or the Operational Safety Plan (Piano Operativo di Sicurezza – POS), to provide adequate
and documented training to workers, to supply appropriate individual and collective protective
equipment (PPE and CPE), and to fully comply with all the other obligations set forth under
Legislative Decree 81/2008.
Submission of the Operational Safety Plan (POS)
Within 10 calendar days after receiving the Notice to Proceed, the awarded Contractor must submit
a detailed Operational Safety Plan (POS). The POS must clearly identify the following key
professional figures:
Site Technical Director (Direttore Tecnico di Cantiere):
The individual responsible for managing the construction site on behalf of the Contractor. This
role may be fulfilled by either an internal employee or an external professional formally appointed
by the company. This figure is not to be confused with the Construction Supervisor (Direttore dei
Lavori), who is appointed by the Client and is responsible for verifying that the works are carried
out in compliance with thedesign and technical specifications.
Supervisor (Preposto):
An individual who, by the nature of their duties, supervises the work of others (e.g., site manager,
workshop head, department chief). The Supervisor must be adequately trained to fulfill the
responsibilities assigned under Art. 19, paragraph 1, letter g) and in accordance with the objectives
of Art. 37 of Legislative Decree 81/2008. The Supervisor shall ensure, continuously and
effectively, that:
1. Workers comply with safety instructions and the provisions of the safety plan;
2. Personal protective equipment (PPE) is used as required;
-- 3 of 15 --
- 4 -
3. Any deficiencies in procedures, tools, PPE, or persistent non-compliance are promptly
reported to the employer or manager.
The contractor has to send the list of personnel who will work on site. The workers have to be
regularly registered and if there is a subcontractor this has to present the documents requested too.
All workers have to understand and speak Italian.
-- 4 of 15 --
- 5 -
DESCRIPTION OF WORK
AERIAL VIEWS
1. Scope of work
The Contractor shall provide all labor, materials, equipment, and services necessary for the
removal of existing vegetation, installation of a new French drain system, construction of
independent foundation blocks, fabrication and installation of a new iron safety railing, and the
laying of new porphyry stone paving above the Elephant stairs. All works shall be executed in
accordance with the highest standards of workmanship and in full compliance with applicable
national and international codes and regulations.
2. Site Preparation and Demolition
• Secure the work area with temporary safety barriers for the entire duration of the project.
• Remove all existing vegetation, including shrubs and root systems, from the designated
area. Ensure compl…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238190)
Grand Coulee Washington Power Plant Turbine Repair
INTERIOR, DEPARTMENT OF THE · Solicitation · due July 20, 2026
Restroom Demolition and Installation of New Concrete Restroom Facility, Lake Siog, East Brimfield Lake, Holland, MA
DEPT OF DEFENSE · Solicitation · due June 26, 2026
Replacement of Cooling Tower Base
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due June 26, 2026
ASHE 22-1058 REPAIR DOORS AT ZULU LOOP 1ST GEN PASs, AVIANO AB, ITALY
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 2, 2026
STGE - GTT Retaining Wall Rehab
INTERIOR, DEPARTMENT OF THE · Solicitation · due July 13, 2026
ASHE 22-1058 REPAIR DOORS AT ZULU LOOP 1ST GEN PASs, AVIANO AB, ITALY
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 2, 2026