EOU Sunshades Creech AFB
DEPT OF DEFENSE
Notice type
Combined Synopsis/Solicitation
Solicitation #
F4FANG6133A001
NAICS
332312
PSC
5450
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
July 24, 2026
Response due
August 7, 2026
Place of performance
Indian Springs, NV
Description
CUI
Page 1 of 20
CUI
GOVERNMENT
STATEMENT OF WORK FOR
CCA SUNSHADE STRUCTURES ON SOUTH RAMP
27 April 2026
-- 1 of 21 --
CUI
Page 3 of 20
CUI
SECTION A: DESCRIPTION OF SERVICES
1. SCOPE:
1.1 Background. Creech Air Force Base (AFB) requires the purchase and
installation of four (4) shade structures for the CCA aircraft based at the airfield.
Also, the relocation of the four (4) existing structures and demolition of
the 5th sunshade. The current Sunshades will be turned perpindicluar and
align with the new sunshades. See Attachment 1. The Contractor shall design,
provide for and construct the following shade structures on the airfield’s aircraft
parking apron:
1.1.1 Four (4) CCA shade structures that include four (4) aircraft parking bays
each. The new shade structures shall be located on south ramp
west of current shade structures.
1.1.2 Column concrete footings, per footing, as needed.
1.1.3 The new shade structure shall follow the requirements below.
The shade structure will require LED lights and their conduit, CU
wiring, service power outlets, a service panel and its Una-strut support
assembly, and a solar battery powered obstruction light.
1.1.4 PVA (Photovoltaic Array) or Solar Paneling with 12-hour battery pack for
the LED Lighting for shade structure.
2. CONTRACTOR DESIGN REQUIREMENTS:
2.1 The Government will provide the Contractor electronic or hard copies of its CCA
Shade Structure as-built drawings for reference purposes only.
2.2 For shade structure, the Contractor shall design a CCA four (4) bay shade
structure.
2.3 For west side, the Contractor’s CCA shade structure design shall provide for a
vertical wall panel at its west end to help shade the occupants from the late
afternoon sun and heat. The wall panel’s specifications for the panel width, gage,
standing seams, and length shall match the shade structure’s SSMR roof panel
specifications.
2.4 The Contractor shall prepare and submit a proposed Progress Schedule at the 35%
design level for Contracting Officer review and approval.
2.5 The Contractor shall prepare and submit a Schedule of Materials and Values at the
35% design level that provides the Government a line item breakout of the shade
structure’s material for Contracting Officer review and approval.
-- 2 of 21 --
CUI
Page 4 of 20
CUI
2.6 The Contractor will be given site access to the current shade structures to help
evaluate their dimensions and existing components.
2.7 The Contractor shall field verify the shade structure dimensions after contract award
and bring any dimension discrepancies noted to the Contracting Officer’s attention
before starting any design work.
2.8 The Government will organize a site survey with the Contractor in order to take
official measurements and fulfill any other design requirements.
2.9 The Contractor shall provide field surveying services to ensure each shade
structure’s columns are installed in the correct locations and the distance between the
shade structures complies with aircraft taxi and clearance requirements. The
Contractor’s surveyor shall field verify that each column’s proposed anchor bolt
location maintains a minimum separation edge distance of 16 inches from existing
concrete apron construction joints or expansion joints.
2.10 The Contractor shall coordinate with the 432nd Wing Project Coordinator and
Airfield Base Operations Manager to obtain the correct shade structure separation
distance and arrange for site access to conduct the field survey. The Contractor shall
capture and include the latitude / longitude (lat/long) locations for all shade
structures’ individual columns and include that information on the Contractor’s
construction plans and As-built drawings.
2.11 The Contractor shall field core the existing concrete apron slab at each shade
structure’s proposed location to determine if the existing slab has adequate thickness
to support the columns or if new concrete footing(s) shall be required. The
Contractor shall submit the core sample(s) to the Contracting Officer for review and
approval purposes. In the event a column requires a new footing, the Contractor shall
supply an updated proposal to be evaluated.
2.12 The Contractor shall submit a 35%, 65%, 95% and 100% set of construction
drawings and specifications for each shade structure for Government review and
approval purposes. Once approved by the Government, both the 100% drawings and
specifications shall be stamped “Approved for Construction”, be sealed and signed by
the Contractor’s Civil or Structural Engineer of Record and a copy submitted for
Contracting Officer review and approval.
2.13 All shop drawings shall be reviewed and approved in writing by the Engineer of
Record before the Contractor submits the drawings to the Contracting Officer for
review and approval.
2.14 The Contractor shall prepare and submit structural calculations at the 65% design
level for the CCA shade structures for Government review and approval purposes.
The structural calculations shall account for a potential future photovoltaic array
panel, battery bank and light system. The calculations shall be sealed and signed
by the Contractor’s Civil or Structural Engineer. Refer to Paragraphs 7.1 Seismic Design,
7.3 Wind Load, 7.7 Dead Loads and 7.8 Roof for details.
-- 3 of 21 --
CUI
Page 5 of 20
CUI
2.15 The Contractor’s 100% design shall conform to the following specifications and
requirements:
2.15.1 The shade structures design shall conform to the latest version of the
International Building Codes (IBC), the American Institute of Steel
Construction (AISC) Steel Construction Manual (15th Edition), the
American Concrete Institute’s Building Code Requirements for Structural
Concrete (ACI 318-14 or newer), the National Electric Code (NEC), the
AF Instructions (AFI), the Unified Facilities Criteria (UFCs), and the
Creech Installation Facility Standards (IFS).
2.15.2 Provide a gabled Standing Seam Metal Roof (SSMR) system with a roof
slope for rain run off. The (SSMR) system sha…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 332312)
Outdoor Recreation - Mobile Bleachers
DEPT OF DEFENSE · Solicitation · due July 29, 2026
Outdoor Recreation - Mobile Bleachers
DEPT OF DEFENSE · Solicitation · due July 29, 2026
MEX-NEC SCAFFOLDING FOR COOLING TOWERS PREVENTIVE MAINTENANCE
STATE, DEPARTMENT OF · Presolicitation · due August 7, 2026
Outdoor Recreation - Mobile Bleachers
DEPT OF DEFENSE · Solicitation · due July 28, 2026
TSC IIJA 8530 UNIVERSAL TEST FIXTURE
INTERIOR, DEPARTMENT OF THE · Combined Synopsis/Solicitation · due July 31, 2026
Full and Open Competition: Custom Machined Parts - CMMC Level 1- Request Access to Drawings through SAM. Provide CAGE Code when requesting access in SAM.
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 28, 2026