Firemain Discharge Piping
DEPT OF DEFENSE
Notice type
Solicitation
Solicitation #
N6264926Q0471
NAICS
336611
PSC
J999
Set-aside
No Set aside used
Posted
July 15, 2026
Response due
August 10, 2026
Place of performance
Sasebo City, JP-42
What this opportunity is
The Department of Defense is buying firemain discharge piping for the USS TRIPOLI. This opportunity is suitable for businesses with a NAICS code of 336611, as there is no set-aside used. Since this is a solicitation notice, businesses should track the opportunity rather than bidding immediately.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Ship/HULL NO. Ship/HULL NAME ICN: Rev: Key Op:
LHA-7 USS TRIPOLI JON. 38DJA52104 AOl
TITLE:
Firemain Discharge Piping for No.16 Fire Pump; replace
JOB SPECIFICATION
Anticipated Award Date: Production Completion Date: PREPARING ACTIVITY:
SASEBO POP Start Date: POP End Date:
PREPARED BY:
T.YOSHINAGA
CODE
P_YO
DATE
1127/2026
APPROVEDBY:
S.MURAKAMI
CODE
S225
CONCURRED BY:
T.TAKAMASU '"f '"
0L CODE
S234
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
_
ASSIST PLANNER'S NAME: CODE _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
ASSIST PLANNER'S NAME: CODE
ASSIST PLANNER'S NAME: CODE
DVNG OPS
DESCRIPTION:
JSN(S): ERO4-1593 CASREP #25124 DTG: 110514ZAUG25, C-2
S/F CONTACT: TILLMAN DCCS / FINLEY, RYAN CWP # CCNS #
Approved by S3001S90
D. PERK
g Date: . AvI: 6A1
LWC:
Work Completed
S/Force:
SHIPSUPT:
Rate: Date:
Date: SRF CONTROL NO.: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
WORK CERTIFICATION SIGNATURES
COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE DATE:
>13
-- 1 of 13 --
Ship/HULL NO. Ship/HULL NAME ICN: Rev: Key Op:
LHA-7 USS TRIPOLI JON. 38DJA52104 AOl
TITLE:
Firemain Discharge Piping for Noi6 Fire Pump; replace
1. SCOPE:
1.1 Title: Firemain Discharge Piping for No.16 Fire Pump; replace
1.2 Location of Work:
1.2.1 Fire Pump Room (5 1/2-97-01-E)
1.2.2 No. 10 Cargo Ammunition Magazine (5-97-0-M)
1.3 Identification:
1.3.1 Quantity (One BA), Bolted Plate, Closure No. 5-99-2 of 2.3,
Clear Opening Size: 36 Inch Length by 48 Inch Width, Located in 1.2.1
and 1.2.2
1.3.2 Quantity (One EA), One Inch IPS through 3 Inch IPS Firemain
Discharge Piping for No.16 Fire Pump Including Firemain Piping
Discharge Piping Main Line for No.13 through No.16 Fire Pump Located
in 1.2.1, between One Inch IPS Boss Outlet Piping on 5 Inch IFS
Discharge Piping for No.16 Fire Pump, Check Valve Outlet Side Unions
(FM-V-2161, 2162 and 2163), 2-1/2 Inch IFS Gate Valve Outlet Side
Flange (6G -ASW-V-0007) and 3 Inch IFS Gate Valve Inlet Side Flange
(FM-V-2166), Not Including Boss, Approximately 35 Feet Length, CuNi
Piping, CuNi and Bronze Fittings, CuNi LOKRING, See ENCLOSURE (A)
1.3.2.1 Quantity (One EA), 2-1/2 Inch IPS Flange assembly on
Firemain Discharge Piping Main Line for No.13 through No.16
Fire Pump Located in 1.2.1, CuNi Flanges
2. REFERENCES:
2.1 Standard Items (FY26)
2.2 ELM-265076, USS TRIPOLI / LHA-7 Firemain OVBD Discharge Piping for
Fire Pumps #13, #14, #15 and #16 in AFT Fire Pump Room (5.5-97-01-E),
(enclosed)
2.3 167-7563713 Rev B, STRUCT Closures 0/F List, ASSY 402
2.4 167-7563782 Rev B, Tank Vent Hose Covers and Bolted Plates
Fabrication List
2.5 141-7563533 Rev C, STRL ASSY 402 lB to 1st PLATF 12"FWD FR 96 to 18"
FWD FR 105 MDL 4
2.6 635-7566067 Rev C, Hull Insulation Details
2.7 635-7569955 Rev B, Insulation Matrix
2.8 521-7566289 Rev B, Firemain Piping System Diagram
-- 2 of 13 --
Ship!HULL NO. Ship/HULL NAME ICN: Rev: Key Op:
LHA-7 USS TRIPOLI JON. 38DJA521 04 AOl
TITLE:
Firemain Discharge Piping for No.16 Fire Pump; replace
2.9 521-7565100 Rev A, Piping Firemain SYS AFT Fire Pump Room
2.10 256-7566624 Rev A, Seawater Service Piping ASSY 402
2.11 MIL -STD -1627 Rev C, Bending of Pipe or Tube for Ship Piping Systems
3. REQUIREMENTS:
CV) (C) "PRE -BRIEF"
3.1 Prior to the start of work, attend Pre -Brief to confirm that the
Contractor, the Government, and the Ship's Force understand the tasks the
contractor is required to accomplish as part of this job specification and
that each of the parties understand the precautionary measures to be taken to
prevent flooding while the repairs/alterations are in progress and who has
responsibility for such measures. -SHIPSUPT
NOTE: Opening Item 78 and 79 of LHA-7 Docking Drawing (DWC.801 -8502725) for
piping listed in 1.3.2
3.2 Remove each existing bolted plate listed in 1.3.1 for the replacement
of each firemain discharge piping, using 2.3 through 2.7 for guidance.
3.2.1 Clean each exposed part and fastener free of foreign matter,
leaving no residue or injurious effects.
3.2.1.1 Chase and tap each exposed threaded area.
3.3 Remove existing and install new firemain discharge piping to replace
the firemain discharge piping listed in 1.3.2, using 2.8 through 2.10 for
guidance.
3.3.1 Do not remove gate valve (FM -V-2166)
reuse.
3.3.2 Do not do onboard hot work located in 1.2.2. (See 4.3)
3.3.3 Clean each existing orifice, fastener and pipe hanger for
3.3.4 Accomplish the requirements of Paragraphs 4 and 5 of 2.11 for
pipe bending section.
3.3.5 Accomplish the requirements of 009-12 of 2.1, including Table
One Columns A and B, Lines One through 10 for shop welding.
3.3.6 Accomplish the requirements of 2.2 including each note for
installation of new flange assembly listed in 1.3.2.1 to facilitate
installation work of new firemain discharge piping without onboard hot work.
343
-- 3 of 13 --
Ship/HULL NO. Ship/HULL NAME ICN: Rev: Key Op:
LHA-7 USS TRIPOLI -
JON. 38DJA521 04 AOl
TITLE:
Firemain Discharge Piping for No.16 Fire Pump; replace
3.3.7 Accomplish the requirements of 009-71 of 2.1 for hydrostatic
test, using clean, fresh water at 296 (+6/-O) PSIG, for each welded joint and
each brazed joint of new and disturbed piping.
3.3.8 Accomplish the requirements of 009-95 of 2.1 for
LOKRING fitting to facilitate installation work of new firemain discharge
piping without onboard hot work. (See 4.4)
…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 336611)
52000QR260026942 USCGC RESOLUTE STBD PROP BLADE LEAK
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 28, 2026
CGC ABBIE BURGESS CO2 INSPECTION / HOSE REPLACEMENT
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 31, 2026
USS RUSHMORE (LSD-47) 7C1 SRA 52pkg
DEPT OF DEFENSE · Solicitation · due July 29, 2026
52000QR260026976- CGC Earl Cunningham and CGC Frederick Mann Underwater Hull Inspect, Clean & Zinc Renewal
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 3, 2026
Standby Emergency Diesel Generator (SEDG); provide
DEPT OF DEFENSE · Solicitation · due August 24, 2026
Annual Shipyard Services for R/V MINKE
COMMERCE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 7, 2026