Description
STATEMENT OF WORK
Low Pressure Air Compressor [LPAC]
Spec #:
Rev: Page 1 of 12
1. SCOPE.
1.1. Portsmouth Naval Shipyard (PNSY) is seeking to lease electric powered Low Pressure Air Compressor
(LPAC) systems with support services (Start-up/commissioning, training, preventative maintenance and
weekly equipment inspections) for use at Naval Base Point Loma (NBPL) in San Diego, CA. Quantities are
listed in paragraph 3.1 component list. PNSY will use the LPAC Systems to establish a Breathing Air System,
Tooling Air System and Blast Air System. The minimum allowable requirements for the systems are detailed
in this Statement of Work. Unless otherwise stated, the contractor shall furnish the Low Pressure Air
Compressor systems, including all labor, supervision, tools, materials, equipment and other items and
services that are necessary to perform as described within this Statement of Work.
2. APLLICABLE DOCUMENTS.
2.1. Issues of Publications. The following documents in effect on the date of this requested proposal is a part
of this specification to the extent applicable, or as specified herein. Within the specification, they shall be
referred to by their basic designation only.
2.1.1. Government Furnished
2.1.1.1. Corporate Lifting and Handling Manual
2.1.2. Nongovernment Furnished
2.1.2.1. CGA G-7.1-2018: Commodity Specification for Air, Seventh Edition
2.1.2.2. OSHA 29 CFR 1910.134 – Respiratory Protection
2.1.2.3. ISO 8573-1:2001
2.1.2.4. OSHA 29 CFR 1910.169, Compressed Gas and Compressed Air Equipment, Air Receivers
2.2. Order of precedence. In the event of conflict between the Statement of Work (SOW) and the references
cited above, the text of this SOW shall take precedence. Nothing in this SOW, however, shall supersede
applicable laws or regulations unless a specific exemption has been obtained.
3. REQUIREMENTS.
3.1. Component List.
3.1.1. 100 HP LPAC Required components (Redundant Breathing Air System).
PIECE
NO.
QTY. NAME OF PART PARA NO.
PC-01 thru
PC-02
2 100 HP LPAC (400 CFM) 3.2 thru 3.7
PC-03 1 1000 Gal. Air Receiving Tank 3.6
PC-04 thru
05
2 400 CFM Desiccant Air Dryer 3.7
PC-06 250 FT 3 IN Air Hose 3.21
PC-07 thru
08
2 E-stop and cabling 3.2.11
3.1.2. 200 HP LPAC Required components (Tooling Air System).
PIECE
NO.
QTY. NAME OF PART PARA NO.
PC-09 1 200 HP LPAC (800 CFM) 3.8 thru 3.13
PC-10 1 1000 Gal. Air Receiving Tank 3.12
PC-11 1 800 CFM Desiccant Air Dryer 3.13
-- 1 of 12 --
STATEMENT OF WORK
Low Pressure Air Compressor [LPAC]
Spec #:
Rev: Page 2 of 12
PC-12 250 FT 3 IN Air Hose 3.21
PC-13 1 E-Stop and cabling 3.8.11
3.1.3. 400 HP LPAC Required Components (Blasting Air System).
PIECE
NO.
QTY. NAME OF PART PARA NO.
PC-14 thru
PC-16 3 400 HP LPAC (1600 CFM) 3.14
PC-17 thru
PC-19 3 1000 Gal. Air Receiving Tank 3.18
PC-20 thru
PC-22 3 1600 CFM Desiccant Air Dryer 3.19
PC-23 500 FT 3 IN Air Hose 3.21
PC-24 500 FT 3 IN Air Hose 3.21
PC-25 400 FT 2 IN Air Hose 3.21
PC-26 500 FT 3 IN Air Hose 3.21
PC-27 300 FT 3 IN Air Hose (25ft lengths) 3.21.3
PC-28 thru
PC-30 3 E-Stop and cabling 3.14.11
PC-31 thru
PC-37 7 Compressed Air Manifold 3.20
3.2. 100 HP Electric LPAC Requirements-[Redundant Breathing Air System].
3.2.1. The vendor shall provide, install, and configure a complete rental breathing air package designed
for continuous, uninterrupted operation. The system shall consist of two (2) air compressors in an
automated lead-lag configuration, two (2) air dryers in a primary/standby manual switchover
configuration, and a 1000-gallon receiver tank. The piping and valving must be sufficient to allow
any single major component (compressor or dryer) to be completely isolated and removed for
maintenance or in case of failure while the redundant unit continues to operate, ensuring no loss of
air supply to the facility.
3.2.1.1. Compressor Configuration: The two compressors shall be piped in parallel to a common
manifold. An isolation valve must be installed immediately downstream of each compressor,
allowing either unit to be individually taken offline without interrupting flow from the other.
3.2.1.2. Dyer Configuration: The two air dryers shall be installed in a primary/standby configuration.
• Under normal operating conditions, only the primary dryer will be online, receiving and
treating the compressed air.
• The secondary dryer shall remain completely isolated from the system via dedicated inlet
and outlet valves. It will be depressurized and non-operational (cold spare).
3.2.1.3. Isolation for Maintenance: The piping and valving must allow for the complete isolation of
any single component. The system must enable an operator to manually:
• Isolate and remove either compressor by closing its dedicated downstream valve.
• Isolate the primary dryer and bring the standby dryer online by manipulating their respective
inlet/outlet valves. This switchover must be achievable without interrupting the operation
of the running compressor.
3.2.1.4. Compressor Automatic Failover(Lead-Lag): The compressors shall be controlled by an
automatic lead-lag sequence controller. This controller will designate one unit as “lead” and
the other as “Lag.”
• Primary Set Point: The Lead compressor will operate to maintain system pressure within the
primary operating band.
-- 2 of 12 --
STATEMENT OF WORK
Low Pressure Air Compressor [LPAC]
Spec #:
Rev: Page 3 of 12
• Backup Set Point: The Lag compressor will remain in powered standby. It shall automatically
activate if the system pressure drops to a lower set point (100 PSI), indicating a failure of the
Lead unit.
3.2.1.5. Dryer Manual Failover: The switchover between the primary and standby air dryers is a
manual operation performed by an operator. The compressor control system is to be
independent of the dryer selection.
Operational Scenarios
Scenario Compressor 1 Compressor 2 Dryer 1 Dryer 2
Normal
Operation
Lead (Auto) Lag (Auto Standby) Online/Pressurized Offline/Isolated
Compr…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 532490)
Rental of Dust Collector for 87' Ridley
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 6, 2026
750 kW Rental Emergency Diesel Generator (EDG)
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 30, 2026
FY27 - AIR SHOW METAL DETECTORS
DEPT OF DEFENSE · Solicitation · due August 6, 2026
W065--Mobile MRI Trailer Lease
VETERANS AFFAIRS, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 30, 2026
EQUIPMENT RENTAL- AIR COMPRESSOR and BLAST POT
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 5, 2026
EQUIPMENT RENTAL- ARTICULATING BOOM LIFTS
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 5, 2026