What this opportunity is
The Department of the Interior is seeking a contractor to repair and maintain stormwater structures in Washington, D.C. This opportunity is set aside for women-owned small businesses, which may be particularly well-suited to bid given their unique eligibility. As a Combined Synopsis/Solicitation, bidders will need to track the solicitation and respond when the notice is posted, rather than waiting for a separate notice to be issued.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
PMIS 320885 ROCR
July 6, 2026
PERFORMANCE WORK STATEMENT (PWS)
for
Repair and Maintenance of Stormwater Structures and Pervious Pavement
1.0 Background
1.1 The Contractor shall furnish all equipment, materials, tools, and labor necessary to
perform the maintenance tasks for approximately 4.5 miles of pervious trails and
parking lot pavement in Rock Creek Park and Fort Reno Park. The pervious surface
area of the pavement is approximately 228,300 square feet. The contractor will be
responsible under this contract for work to provide maintenance services as described
in this document.
1.2 All work shall conform to Section 3.5.7 of the District Department of Energy &
Environment (DOEE) “Stormwater Guidebook Permeable Pavement Systems.”
1.3 A Schedule of Tasks will be included in the appendix to indicate the frequency of
each task/activity.
1.4 The performance requirement for the work as outlined above is to maintain 100%
functionality of the Permeable Pavement System.
2.0 Scope
2.1 The Contractor will provide periodic maintenance services for pervious paving to
keep the systems and assemblies operating to original performance specifications.
The work may involve the use of specialized cleaning and debris collection
equipment, as well as any other necessary materials needed to perform work under
the terms of this PWS.
2.2 This contract will be between the National Park Service and the Contractor. The
contractor shall be responsible for assuring that any subcontractor(s) perform the
work as stated in this PWS as outlined.
2.3 Contractor shall submit work plan to include means and methods of performing tasks
to the Contracting Officer’s Representative (COR) for approval prior to the
commencement of any work.
3.0 Work to be Performed – The following are the tasks that will be performed by the contractor
on a monthly, seasonal, and annual basis to fulfill this contract, as outlined in the Quality
Assurance and Surveillance Plan and Schedule of Tasks in the appendix.
3.1 Permeable Pavement Maintenance
3.1.1 Routine maintenance
3.1.1.1 Inspection: Conduct visual inspection of pavement to
determine that it is clean of debris and sediment and that it is
dewatered quarterly, or as needed at least four times annually.
-- 1 of 51 --
PMIS 320885 ROCR
July 6, 2026
Inspect pavement after any major weather events such as rain
or snowstorms of more than 1 inch of precipitation.; these
inspections are in addition to the four annual inspections.
3.1.1.2 Maintenance:
3.1.1.2.1 Monthly: Remove leaves and sediment so that it does
not become ground down into the surface. Any
materials blown off pavement need to be collected by
the Contractor, weighed, and taken off site.
3.1.1.2.2 As needed: Dry out any ponding or moist areas of
pavement if moss is observed and use a lime mortar
mix to kill the moss and vacuum clean the surface.
3.1.2 The performance requirement for the work as outlined above is to
maintain 100% functionality of the Permeable Pavement System.
3.1.3 Locations: See 4.0 as well as Schedule of Locations which is in the
appendix for details on the locations of work.
3.1.4 Contractor must maintain a maintenance log that records the following:
• Date of service.
• Name of individual/company performing service.
• Type of maintenance performed.
• Amount (lbs.) and type(s) of sediment/debris/other material removed
as result of cleaning.
• General observations and record of pavement condition.
• Name/signature of individual completing the inspection.
• Additionally, if ASTM C1701 is performed (see Section 7.0 of this
Scope of Work), the test results and locations should be included in the
report.
• The log must be submitted to the COR each month for approval.
3.2 Permeable Pavement Repairs
3.2.1 If inspections reveal repairs are needed to the pervious pavement, notify
the COR within 24 hours of discovery. This contract does not involve
repair to the pervious pavement infrastructure; reporting only.
3.3 Inspect, Repair and Maintain Stormwater Structures at all locations shown in
Paragraph 4
3.3.1 Debris Accumulation
3.3.1.1 Inspect for fallen leaves, debris, and litter accumulation.
3.3.1.2 Maintain: Remove these foreign materials. Especially before
winter and in early spring, remove sediment especially when
-- 2 of 51 --
PMIS 320885 ROCR
July 6, 2026
more than two inches deep of if shown to impact the growth of
required vegetation.
3.3.1.3 Scheduled Service: Spring and Fall, Monthly, and after major
storm events.
3.3.2 Entry points and Pretreatment Areas
3.3.2.1 Inspect: Area such as filter strips, and Bioswale floor for
excessive deposition of sediment, rocks, etc. Inspect monthly
for erosion at inflows or ponding areas.
3.3.2.2 Maintain: Remove sediment and stabilize any eroded areas
quarterly using methods approved by the and the NPS COR.
Reestablish vegetations that conforms with original plant
materials if needed, reseed and restore all filter strips.
3.3.2.3 Scheduled Service: Inspect monthly and after major storm
events, and in the spring and fall. Maintain spring and fall,
monthly during the growing season, and after major storm
events.
3.3.3 Culverts
3.3.3.1 Inspect: All locations where culverts are part of the Bioswale
system annually to ensure that erosion has not occurred at the
outfall of said culverts.
3.3.3.2 Maintain: Repair eroded areas, replace or move to original
locations all stone, grave, and revetment materials. Remove
any debris that was not part of the original construction.
3.3.3.3 Scheduled Service: Inspect annually, Maintain When repair is
needed as documented by inspections.
3.3.4 Check Dams
3.3.4.1 Inspect: Annual inspection to check dams for excessive
deposition of sediment, rocks. Inspect condition of any choker
layer materials on the front side of rock checks.
3.3.4.2 Maintain: Clear all debris and bring Check Dams back to
original operational specification.
3.3.4.3 Scheduled Service: Inspect Annually, Maintain when
inspection shows repa…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 561730)
Boundary Line Maintenance Services, Greers Ferry Project Office
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 30, 2026
Landscaping at NOAA Weather Forecast Office in Topeka, KS
COMMERCE, DEPARTMENT OF · Solicitation · due July 28, 2026
Landscaping at NOAA Weather Forecast Office in Rapid City, SD (UNR)
COMMERCE, DEPARTMENT OF · Solicitation · due July 28, 2026
Landscaping at NOAA Weather Forecast Office in La Crosse, WI
COMMERCE, DEPARTMENT OF · Solicitation · due July 28, 2026
Landscaping at NOAA Weather Forecase Office in White Lake (Detroit), MI (DTX)
COMMERCE, DEPARTMENT OF · Solicitation · due July 28, 2026
Columbia Landscape & Snow Services
FEDERAL COMMUNICATIONS COMMISSION · Combined Synopsis/Solicitation · due August 6, 2026