Description
YTPM 24-0012
Page 1 of 19
CONSTRUCTION
STATEMENT OF WORK:
Repair HVAC, Building 7087
Contract Number:
Base Project Number: YTPM 24-0012
21 May 2026
-- 1 of 28 --
YTPM 24-0012
Page 2 of 18
1.0 INTRODUCTION
The Government is issuing this Statement of Work (SOW) to transition from concept definition
to construction services. The Contractor shall be capable of addressing and interpreting all
aspects of most current Unified Facility Guide Specifications (UFGS) regarding this SOW.
2.0 PURPOSE
2.0.1 Under this contract, construct project YTPM 24-0012, Repair HVAC, Building 7087 at Westover Air
Reserve Base. The Contractor is responsible for the construction work described in this Statement of
Work.
2.0.2 The objective of this project is to replace one (1) of the three (3) existing Trane Model CGAFC40 air
cooled chillers that provide cooling for the C5 Flight Simulator.
2.0.3 The laterals for all 3 chillers will be modified such that future replacement of the other 2 chillers can
be conducted while the system is operational. This feature of work involves scheduling restrictions
and must be pre-coordinated. See Paragraph 4.2.1.1 below.
2.0.4 In order to install these six (6) isolation valves, the Contractor will need to drain the system,
temporarily store the fluid, reinstall the fluid, and return the system to operational status. The
Government believes that the best place to drain the system will be at the dry cooler connection point
at the far end of the chilled water loop. See attached photos and Record Drawings.
2.0.5 The chiller will need to be connected to the existing MNL controller and coordinated with the other 2
units. The existing controls are serviced by SNE Building Systems.
2.0.6 Additionally, the Niagara JACE will need to be updated within the Base-wide EMCS system. The
existing EMCS system is serviced by Kleeberg Mechanical Services, LLC., out of Ludlow MA.
2.1 Project Information
2.1.1 Project Number: YTPM 24-0012, Repair HVAC, Building 7087
2.1.2 Project Location: Westover Air Reserve Base, MA 01022.
2.1.3 Work to be performed: The project is a construction contract. The Contractor shall
provide all labor, materials, and equipment to install, construct, and complete the work planned
in accordance with this Statement of Work (SOW).
2.1.4 Construction Deliverables. As specified in Section 8.0, Meetings & Deliverables
Schedules. The period of performance for all work shall be as established in Section
12.0, Performance.
3.0 SCOPE
-- 2 of 28 --
YTPM 24-0012
Page 3 of 18
3.1 The work of this Project YTPM 24-0012 Repair HVAC, building 7087 consists of furnishing
all labor, equipment, materials, and all miscellaneous services required to accomplish the
following work in the facilities on the Base:
• Demo existing chiller (#5), piping, pumps, and all other existing
appurtenances back to the lateral where new valves are to be installed. This
includes disposal of refrigerant in accordance with all rules and regulations.
• Install one (1) new Carrier chiller model 30RAP 030 that meets all
performance criteria outlined herein.
• Provide submittals for all equipment and materials to be installed under this
project.
• R-410A Refrigerant digital scroll compressors for capacity control to provide
multiple incremental steps for tighter temperature control.
• Provide an ultra-low sound package consisting of low sound AeroAccoustic
fans and sound blankets as well as low sound compressor blankets
• Chiller will have the factory supplied Hydronic Package with primary pump.
• Utilize Victaulic fittings with grooved carbon steel pipe as much as possible.
Use flexible Victaulic couplings at the chillers for vibration and isolation.
• Reconfigure the piping feeds to all three (3) chillers and install new shut-off
valves as close as possible to the main supply and return headers, which run
along the building wall, for all three (3) chillers. Use ball valves for all
shutoff duty valves.
• Install new fiberglass insulation with aluminum jacketing for outside exposed
piping. The insulation system shall be designed to prevent condensation on
the outer jacket under all anticipated ambient conditions, and shall, at
minimum, meet or exceed the thickness requirements of the latest
International Energy Conservation code (IECC).
• New chiller shall have Motormaster V Low ambient controls for year-round
cooling of the flight simulator systems.
• New chiller shall have Security Grilles/Hail guards.
• Extend existing concrete pad (if required) to create a single, level, and
continuous concrete surface that will fully accommodate the footprint of the
new chiller, including required service clearances per the manufacturer’s
installation manual.
• Install vibration isolation pads at unit mounting points to help reduce
vibration transmission.
• Electrical Information - The three (3) existing Chillers are 40 ton /each, 480
volts 3 phase, 60 hz fed from panel H1C and 125 main breaker, each Chiller
has a secondary exterior disconnect rating 200-amp, 600 volt 3 phases.
• The two (2) existing Trane chillers to remain utilize LON protocol for
communication. The new chiller shall be provided with a native BACnet
communication interface. The chillers are currently controlled by an MNL
Controller. The final installed system must provide, at a minimum, the
following capabilities from a single, unified DDC interface:
a) View the operational status (On/Off/Alarm) of the chiller.
b) View the entering and exiting chilled water temperatures for the chiller.
c) Individually enable/disable the chiller.
d) Receive and display critical alarms from the chiller.
-- 3 of 28 --
YTPM 24-0012
Page 4 of 18
3.1.1 Site Survey. The Contractor shall perform a site survey to confirm information
pertaining to the project under this SOW and shall provide all plans, labor, equipment, and
materials necessary to support all work under this SOW.
3.1.2 Base Regulations. The Contractor shall conform to all Base regulations and directives
pertaining to …
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238220)
HVAC Replacement and Modernization of Controls - Owings Mills, MD
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 30, 2026
57 MXG Paint Booth Upgrade
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 21, 2026
J--GATE-REPLACE HVAC SYS AT BLDG 47&58-SAHO
INTERIOR, DEPARTMENT OF THE · Combined Synopsis/Solicitation · due July 30, 2026
J--Heat Pump Replacement @ BRVB
INTERIOR, DEPARTMENT OF THE · Combined Synopsis/Solicitation · due August 6, 2026
Replace Seals, Building 4305 FRCE
DEPT OF DEFENSE · Solicitation · due September 3, 2026
127EAW26Q0053 - Kern River Ranger District HVAC
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 27, 2026