CONTRACT DOCUMENTS AND SPECIFICATIONS
PROJECT CA22-D46/EDO-295-D46
PUBLIC LAW 86-121
SCATTERED SITE WELL DRILLING
May 2026
PREPARED BY
INDIAN HEALTH SERVICE
EDO DISTRICT OFFICE
CDR JOSH SIMS, PE
700 LA TERRAZA BLVD., STE.100
ESCONDIDO, CA 92025
PH: 760-735-6885
JOSHUA.SIMS@IHS.GOV
-- 1 of 41 --
California Area Indian Health Service Revised 6/29/2022
Advertisement for Bids
C-111 - 1
C-111
ADVERTISEMENT FOR BIDS
INDIAN HEALTH SERVICE
358940 MAGEE ROAD, PALA, CA 92059
SAN DIEGO COUNTY, CALIFORNIA
SCATTERED SITES WELL DRILLING
PROJECT CA22-D46
SOLICITATION NUMBER: EDO-295-D46
Engineer: IHS is the contracting authority and owner’s representative.
Indian Health Service
CDR Josh Sims, PE
700 La Terraza Blvd., Suite 100
Escondido, CA 92025
Phone: 760-735-6885
E-mail: joshua.sims@ihs.gov
Owner: Donna and James Rico
35940 Magee Road
Pala, CA 92059
General Notice
TheGovernment is requesting Bids for the construction of the following Project:
SCATTERED SITES WELL DRILLING
PROJECT CA22-D46/EDO-295-D46
Bids for the construction of the Project will be received in accordance with these solicitation documents.
The Project includes the following Work:
The drilling of a 5.5” min. inner diameter individual water well approximately 400 ft. deep, pump
testing, water quality analysis, and pump installation in Pala, CA. Approximate coordinates are
33.364331°N 117.05664°W.
Bids will be received for a single prime Contract. Bids shall be on a lump sum and/or unit price basis,
with additive alternate bid items as indicated in the accompanying Bid Form. The Project has an
expected duration of 70 days.
+ + END OF ADVERTISEMENT FOR BIDS + +
-- 2 of 41 --
-- 3 of 41 --
Bid Form
C-410 - 1
Item
No. Description Unit Estimated
Quantity
Bid Unit
Price Bid Price
1 Mobilization and
Demobilization LS 1
2
Well Drilling: for 5.5” min.
inner diameter casing with
annulus for filter pack
VF 400
3 Casing: 5.5” min. inner
diameter PVC VF 300
4 Slotted Casing: 5.5” min. inner
diameter PVC VF 100
5 Grouting VF 20
6 Filter Pack/Formation
Stabilizer VF 380
7 Well Development HR 4
8 Test Pumping, including
recovery HR 12
9 Well Disinfection and Water
Analysis LS 1
10 Submersible Pump: 1HP EA 1
11 Drop Pipe and Submersible
Cable: 1 inch Schedule 80 PVC VF 300
Total
-- 4 of 41 --
California Area Indian Health Service Revised 5/18/2018
Measurement and Payment
01 27 00 - 1
SECTION 01 27 00
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 SECTION INCLUDES
A. Summary.
B. Estimated quantities.
C. Survey and measurements.
D. Payment for increased or decreased quantities.
E. Omitted items.
F. Partial payments.
G. Payment for material delivered.
H. Final payment.
I. Incidental work.
J. Description of pay items
1.2 SUMMARY
A. Work covered by this section includes method of measurement and basis of payment for all
divisions included.
B. Payment for the various items of the Bid Schedules, as further specified herein, shall include
all compensation to be received by the Contractor for furnishing all tools, equipment,
materials, labor, supplies, manufactured articles, transportation, and temporary facilities
required to complete the work in accordance with contract documents including incidentals.
C. Respective prices and payment shall constitute full compensation for all work completed
including incidentals.
D. All items not expressly listed as being provided by others that are necessary for the completion
of work shall be furnished and installed by the Contractor.
E. No payment shall be made for mobilization and demobilization of equipment, unless it is
explicitly included as a bid item.
-- 5 of 41 --
California Area Indian Health Service Revised 5/18/2018
Measurement and Payment
01 27 00 - 2
F. The Contractor, in case of unit-price items measured for payment, shall be paid for the actual
amount of Work accepted and for the actual amount of materials in place, as shown by final
measurement. Plan quantity items shall be paid for at the unit price for the quantities shown
on the plans and tabulated in the bid form.
G. The Contractor, in case of lump sum amounts, or by plan quantities, shall be paid for the
percentage of the work item completed as determined by the Engineer.
H. All units of measurement shall be standard United States convention as applied to the specific
items of Work by tradition and as interpreted by the Engineer.
1.3 ESTIMATED QUANTITIES
A. All quantities stipulated in the bid schedule or other contract documents are approximate and
are to be used: (1) as a basis for estimating the probable cost of the work and (2) for the
purpose of comparing the bids submitted.
B. The Contractor shall be paid for actual quantities installed based on the quantities measured in
the field. The actual amounts of work completed and materials furnished may differ from
estimated quantities. The Contractor shall make no claim for damages, anticipated profits, or
otherwise, on account of differences between the estimated amounts and the actual amount of
work performed and materials furnished.
C. The payment of any partial estimate or of any retained percentage in no way shall affect the
obligation of the Contractor to repair or renew any defective parts of the construction or to be
responsible for all damage due to such defects.
1.4 SURVEY AND MEASUREMENTS
A. All quantity measurements shall be the responsibility of the Contractor and will be verified by
the project Engineer.
B. All measurements and subsequent payments will be based on completed and accepted work
performed in strict accordance with the drawings, specifications, and other contract
documents.
1.5 PAYMENT FOR INCREASED OR DECREASED QUANTITIES
A. When alterations in the quantities of work are ordered and performed, the Contractor shall
accept payment in full at the Contract price for the actual quantities of Work done. No
allowance will be made for anticipated profits.
1.6 OMITTED ITEMS
A. Should any items contained in the Bid Form be fo…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 237110)
Rosebud Lift Station Construction
HEALTH AND HUMAN SERVICES, DEPARTMENT OF · Solicitation · due July 20, 2026
Residential Water Pump Replacement at U.S. Consulate in Fukuoka
STATE, DEPARTMENT OF · Presolicitation
Temporary Sewer Line at Coast Guard Academy
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 3, 2026
99 CES - FLOW METER FOR FACILITY 1711
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 1, 2026
Replacement of Irrigation System, Clayton, NC
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 8, 2026