What this opportunity is
The U.S. Department of Agriculture is seeking a contractor to install a 1,000-gallon septic tank and a gravity feed sewage line at the Agricultural Research Service facility in Starkville, MS. This opportunity is set aside for total small businesses under NAICS 238910, which covers plumbing, heating, and air-conditioning contractors. Interested businesses should note that this is a combined synopsis/solicitation, indicating they should track the opportunity closely and prepare to submit bids as required.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Agricultural Research Service
U.S. DEPARTMENT OF AGRICULTURE
Statement of Work
Sewage Line and Tank Install
Asset ID #606400B013
USDA-ARS
Mississippi State,
Mississippi
Prepared by:
Jason Johnson
February 9, 2026
-- 1 of 4 --
1. PROJECT INTRODUCTION
1.1. PROJECT TITLE
Install septic tank (1,000 gallon) and gravity feed sewage line to manhole.
1.2. PROJECT BACKGROUND AND PURPOSE
The USDA, Agricultural Research Service (ARS), Poultry Research Unit is housed in its own
fenced compound at 606 Spring Street, MS State, MS 39762. Some of the research
activities for this unit are housed in Building 13 which had a major renovation in the early
1990’s. When the building was renovated a sewage lift station was installed to remove bird
waste, two sinks, one toilet and floor drains. A lift station was installed, and waste was
pumped uphill approximately 350 feet uphill to a manhole using two-inch PVC pipe. A
modular building was placed on top of the two-inch PVC line in 2002. Research usage of
the building has changed over time. More solid waste is now being placed into this
system. The current pump is not built to handle the larger solid particles and the larger
volume. The purpose of this project is to place a two-chamber septic tank (at least 1,000
gallon) and gravity feed sewage with 4-inch PVC down hill to the nearest manhole (about
440 feet of line). All plumping work with be installed to current building codes.
1.3. PROJECT CONTACT PERSONS
CONTRACTING OFFICER’S REPRESENTATIVE (COR)
TBD
LOCATION POINT OF CONTACT (LPOC)
TBD
Research Leader (RL)
TBD
CONTRACTING OFFICER (CO)
Michael Sherlock
USDA, ARS
Michael.Sherlock@usda.gov
ADMINISTRATIVE OFFICER (AO)
TBD
ENGINEER PROJECT MANAGER (EPM)
TBD
-- 2 of 4 --
2. SCOPE AND OBJECTIVES
2.1. DESCRIPTION OF WORK
Provide all materials, labor, and equipment to install the new septic tank and PVC pipe to
downhill manhole. Contractor services must be performed by a licensed Contractor. The
Contractor must:
2.1.1. Install 1,000-gallon two chamber septic tank and run four-inch PVC downhill to
manhole.
2.1.2. Flush water to make sure all is correct..
2.1.3. Clean up all debris and dispose at a proper location off site.
2.2. The Contractor will verify all dimensions and site conditions prior to beginning work. No
Government equipment will be available for use by the Contractor. The Contractor must
provide their own restroom facility.
2.3. LOCATION OF WORK
The project is located at 606 Spring Street, MS State, Mississippi 39762.
-- 3 of 4 --
2.4. SITE VISIT
Site Visit Attendance is mandatory to submit a quote. Review the solicitation for the
exact time and date of the site visit. No quotes will be accepted from vendors that do not
attend the site visit.
3. PROJECT SCHEDULE
3.1. The completion of the project must not exceed ninety (90) calendar days from the date
of the Notice to Proceed (NTP).
3.2. The Contractor must prepare an overall project schedule including milestone dates for
all phases of work and completion date; submit to the COR for approval. This schedule is
due fourteen (14) days after contract award. The Contractor must track all work
progress to ensure that the project is completed according to the schedule. Include work
week schedule with daily starting and stopping time.
3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If
necessary, any request for a time extension must be submitted to the Contracting
Specialist in writing before the expiration of the Period of Performance. Each request
must include specific and detailed reasons in support of the schedule alteration and
provide an updated schedule for completion. No extension of the period of performance
may be given without the written authority of the CO.
3.4. Project work hours are 7:00 am and 3:30 pm, local time, Monday through Friday; federal
holidays are excluded. The contractor is not required to provide services on recognized
Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to work
schedule must be submitted to CO for written approval prior to any schedule change.
3.5. This work location is inside of a locked compound that houses animal research;
therefore, site security and animal welfare are serious concerns due to disease
transmission, etc. All work must be coordinated with the LPOC and RL to ensure that
safety and health protocols are observed and the research animals as well as workers are
protected.
-- 4 of 4 --
Source: SAM.gov, as posted. Verify the current solicitation before responding.