What this opportunity is
The Department of the Interior is buying rooftop HVAC replacement services, which suits total small businesses due to the set-aside. The work will take place in Colorado, specifically at the Montrose Public Lands Center. As this is a solicitation notice, small businesses should prepare to bid on the project.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
United States Department of the Interior
Bureau of Land Management
Uncompahgre Field Office
Colorado
Montrose Public Lands Center
Rooftop Air Conditioning Unit (RTU) Replacement
SPECIFICATIONS
-- 1 of 14 --
Rooftop Air Conditioning Unit Replacement
SPECIFICATIONS
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 46 00 QUALITY CONTROL
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 84 50 HAZARDOUS MATERIAL REMOVAL
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 81 10 ROOFTOP AIR CONDITIONING UNIT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
-- 2 of 14 --
Rooftop Air Conditioning Unit Replacement
SPECIFICATIONS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 PROJECT DESCRIPTION
Replace an existing rooftop air conditioning unit (RTU).
1.2 LOCATION
The project is located at the Montrose public lands center.
Montrose Public Lands Center
2465 South Townsend Ave
Montrose, CO 81401
1.3 WORK SCHEDULE
Work shall occur Monday - Friday. Work shall not occur on Federal
.
1.4 PUBLIC SAFETY
The Montrose Public Lands Center will remain open to the public and
employees during the work. Contractor shall take precautions, as
necessary, to protect the public and employees from construction hazards.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 2
-- 3 of 14 --
Rooftop Air Conditioning Unit Replacement
SPECIFICATIONS
SECTION 01 32 01
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule; G
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, and pursuant
to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the
schedule the proposed sequence to perform the work and dates contemplated
for starting and completing all schedule activities. The scheduling of the
entire project is required.
3.2 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.2.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address
major milestones, work listed in the bid schedule, and to allow for
satisfactory project planning and execution.
3.2.2 Mandatory Tasks
Include the following activities/tasks in the initial project schedule and
all updates.
a. Submission, review and acceptance of submittals.
b. Long procurement activities.
c. Contractor's pre-final inspection.
d. Government's pre-final inspection.
e. Final inspection.
SECTION 01 32 01 Page 5
-- 4 of 14 --
Rooftop Air Conditioning Unit Replacement
SPECIFICATIONS
3.2.3 Government Activities
Include Government activities that could impact progress. These activities
include, but are not limited to: Government inspections of work,
Government approval of submittals.
3.3 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly
reviewing the actual progress of the project as compared to the as planned
progress and to review planned activities.
3.4 FAILURE TO ACHIEVE PROGRESS
Should the progress fall behind the approved project schedule, the
Contracting Officer may require provision of a written recovery plan for
approval. The plan must detail how progress will be made-up to include
which activities will be accelerated by adding additional crews, longer
work hours, extra work days, etc.
3.4.1 Failure to Perform
Failure to perform work and maintain progress in accordance with the
supplemental recovery plan may result in an interim and final
unsatisfactory performance rating and may result in corrective action
directed by the Contracting Officer pursuant to FAR 52.236-15 Schedules
for Construction Contracts, FAR 52.249-10 Default (Fixed-Price
Construction), and other contract provisions.
3.4.2 Recovery Schedule
Should the Contracting Officer find it necessary, submit a recovery
schedule pursuant to FAR 52.236-15 Schedules for Construction Contracts.
-- End of Section --
SECTION 01 32 01 Page 6
-- 5 of 14 --
Rooftop Air Conditioning Unit Replacement
SPECIFICATIONS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only.
1.2 INFORMATION ONLY SUBMITTALS
Normally submittals for information only will not be returned. Approval of
the Contracting Officer's Representative is not required on information
only submittals. The Government reserves the right to require the
Contractor to resubmit any item found not to comply with the contract.
This does not relieve the Contractor from the obligation to furnish
material conforming to the plans and specifications; will not prevent the
Contracting Officer from requiring removal and replacement of
nonconforming material incorporated in the work; and does not relieve the
Contractor of the requirement to furnish samples for testing by the
Government.
1.3 GOVERNMENT APPROVING AUTHORITY
The Contracting Officer's Representative will:
a. Note the date on which the submittal was received.
b. Review submittals for approval within 10 days of receipt.
c. Identify returned submittals with one of the actions defined in
paragraph REVIEW NOTATIONS and with markings appropriate for action
indicated.
Upon completion of review of submittals requiring Government approval, one
copy of the submittal will be retained by the Contracting Officer's
Representative and one copy of the submittal will be returned to the
Contractor.
1.3.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize the Cont…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238220)
Air Conditioning Repair
JUSTICE, DEPARTMENT OF · Justification
Air Conditioning Maintenance
JUSTICE, DEPARTMENT OF · Justification
Replace EVAP Cooler in Greenhouses - St. Paul, MN
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 13, 2026
89 AW HQ Water Bottle Stations
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 4, 2026
Water Treatment Service HVAC System
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 30, 2026
J--FY26 HIHW VC and LC HVAC Repair and Replacement
COMMERCE, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 28, 2026