What this opportunity is
The Department of Defense is seeking a contractor for the procurement, hauling, and delivery of various aggregate stone materials to Fort Riley, Kansas, under a total small business set-aside. The materials include high-density base course, select aggregate, screened sand, and fill sand, all of which must meet specific technical specifications and quality control standards. As this is a presolicitation notice, interested small businesses should prepare to track the opportunity and be ready to respond once the solicitation is officially released.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
AGGREGATE STONE: W911RX-26-Q-A032
1.STATEMENT OF WORK (SOW)
1.1 This Statement of Work (SOW) defines the requirements for the procurement, hauling,
and delivery of various aggregate stone materials to multiple Directorate of Public Works
sites. The primary objective is to maintain tactical trails, base road infrastructure, and
erosion control measures essential for sustained mission readiness.
2. Technical Specifications
2.1 All aggregate materials must conform to the following specifications. The contractor is
responsible for providing laboratory certification (AASHTO or ASTM standards) for each
material lot prior to the initial delivery.
Material
Code
Specification
Reference
Primary Mission Application
AB-3 KDOT Section 1104 /
MoDOT Type 5
Aggregate Base Type 3: High-density base course for heavy-duty
tactical vehicle lanes and hardstands.
SA-1 Select/Stabilized
Aggregate (Grade 1)
Select Aggregate: Used for subgrade stabilization and shoulder
reinforcement where high shear strength is required.
SS-5 Screened/Special
Sand (Fine)
Special Sand: Ideal for pipe bedding, utility trench backfill, and as
a leveling course for interlocking pavers or masonry units.
Material
Code
Specification
Reference
Primary Mission Application
Fill Sand
(FA-3)
Unclassified
Structural Fill
Utility & Protection: General-purpose sand used for trench
backfill, leveling under slabs, and filling sandbags for force
protection/fortification. Applied to runways, helipads, and
tactical roads during winter operations to increase traction for
aircraft and heavy equipment.
-- 1 of 7 --
3. Gradation & Quality Control
3.1 The contractor is responsible for ensuring the following technical parameters are
maintained throughout the delivery cycle:
Property Requirement for AB-3 / SA-1 Requirement for SS-5
Plasticity Index
(PI)
Typically, 2 to 8 (Non-Plastic for SA-1) Non-Plastic (NP)
Sieve Analysis Must meet 1.5" to #200 sieve
gradation.
100% passing #4 sieve; restricted fines.
Moisture Content Maintained within ±2% of optimum. Free draining; max 5% moisture by
weight.
Deleterious Sub. Max 5% (Shale, Coal, or Soft Rock). Clean; free of organic matter or clay
balls.
Fill
Sand
(FA-3)
Unclassified
Structural Fill
Utility & Protection: General-purpose sand used for trench backfill,
leveling under slabs, and filling sandbags for force
protection/fortification. Safety Operations: Mixed with Road Salt during
winter operations to increase traction.
3.2 Technical Requirements for Sand
-- 2 of 7 --
• Purity: All sand codes (FA-1 through FA-4) must be free of organic matter, roots,
sod, or clay balls that could compromise structural integrity or drainage.
• Moisture Management: For Fill Sand intended for immediate sandbagging or
structural compaction, moisture content should be maintained between 3% and
7% to ensure maximum density and "stackability."
• Gradation Verification: The contractor must provide a Sieve Analysis for each
code. For example, FA-1 (Concrete Sand) must have a specific distribution of
grain sizes to fill voids between larger aggregates in a concrete mix.
3.3 Gradation Requirements (Sieve Analysis)
The following table outlines the allowable percentage of material passing through
standard sieve sizes for Concrete Sand (FA-1) and Masonry Sand (FA-2), based on ASTM
C33 and ASTM C144 standards.
Note: General Fill/Bedding Sand (FA-3/FA-4) generally follows the FA-1 curve but allows
for higher tolerances on the No. 100 and No. 200 sieves.
Sieve Size FA-1 (Concrete Sand) % Passing
3/8 Inch (9.5 mm) 100%
No. 4 (4.75 mm) 95% – 100%
No. 8 (2.36 mm) 80% – 100%
No. 16 (1.18 mm) 50% – 85%
No. 50 (300 μm) 5% – 30%
No. 100 (150 μm) 0% – 10%
No. 200 (75 μm) 0% – 3.0%
-- 3 of 7 --
4. Logistics and Delivery Requirements
4.1 The contractor shall coordinate deliveries to the following designated locations. All
deliveries must be completed using "tight-bed" semi-trailer trucks or dump trucks to
prevent material loss during transit.
Location Name Grid/Address Site Access Requirements
Tank Gunnery Range
South Range 18
Vinton School Road 24-hour advance notice Delivery between
0800-1530 hrs. only.
Tank Gunnery Range
North (MPRC)
North of Wakefield on US
HWY 77
24-hour advance notice Delivery between
0800-1530 hrs. only.
Main Post Public Works
Yard
Northeast Corner of Public
Works Yard
24-hour advance notice Delivery between
0800-1530 hrs. only.
Main Post North of Building 318 Salt
Barn
24-hour advance notice Delivery between
0800-1530 hrs. only.
5. Operational Standards
1. Notice to Proceed: Deliveries shall commence within five (5) business days of the
issuance of a Task Order.
2. Weight Verification: Every load must be accompanied by a certified weight ticket
from a state-certified public weigher and delivered to the Site Manager or
designated representative
The ticket must include the Truck ID, Gross Weight, Tare Weight, and Net Weight in tons.
3. Quality Control: The Site Manager reserves the right to reject any load containing
excessive fines, clay, or organic debris not specified in the grading requirements.
Rejected loads shall be removed and replaced at the contractor's expense.
-- 4 of 7 --
4. Stockpiling: If immediate spreading is not required, material shall be stockpiled at
least 200 feet away from any permanent structures or active waterways to prevent
runoff.
5. Administrative and Invoicing
5.1 All invoices must be submitted electronically to the Supply Department for processing.
Email to Yvonne Johnson-Wilson @yvonne.a.johnson-wilson.civ@army.mil and Gary J
Jungels @gary.j.jungels.civ@army.mil
• Contract and Task Order Number.
• Material Description and Unit Price per Ton.
• Consolidated total of Net Weight from attached weight tickets.
• Proof of Delivery (POD) signed by the receiving Site Manager or designated
representative.
6. Delivery Vehicle Requirements: Aggregate & Sand
6.1 Vehicle Selection (BLUF)
The contractor is responsible for selecting and deploying vehicles that are compatible with
both the material type …
Source: SAM.gov, as posted. Verify the current solicitation before responding.