What this opportunity is
The U.S. Department of Agriculture is seeking a contractor to replace a failed sewer lift station with a gravity sewer line at Building 32 in Tifton, Georgia. This opportunity is set aside for total small businesses under NAICS 237110, suitable for firms with expertise in sewer installation and demolition. Interested vendors should note that this is a combined synopsis/solicitation, indicating they should track the notice closely for bidding details and are encouraged to conduct a site visit to assess project conditions before submitting quotes.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Agricultural Research Service
U.S. DEPARTMENT OF AGRICULTURE
STATEMENT OF WORK
Building 32 Sewer Repair
Crop Genetics & Breeding Research Unit
2773 Davis Road
Tifton, Georgia 31793
Asset ID: 660200B032
-- 1 of 7 --
Solicitation Number and Building 32 Sewer Repair
Page 2 of 7
1. PROJECT INTRODUCTION
1.1. PROJECT TITLE
USDA Building 32 Gravity Sewer Installation
1.2. PROJECT BACKGROUND AND PURPOSE
The USDA, Agricultural Research Service (ARS), Crop Genetics & Breeding Research
Unit requires contractor assistance to replace the failed sewer lift station at Building 32
with a gravity sewer line.
2. SCOPE AND OBJECTIVES
2.1. DESCRIPTION OF WORK
The Contractor must furnish all personnel, equipment, tools, materials, supervision, and
quality control necessary to bypass and remove the sewer lift station and install a new
gravity feed line capable of evacuating sewage from USDA Building 32 and tying into
the City of Tifton Sewer system. All quotes should be submitted as turn-key completed
work. All work will be accomplished by certified technicians and in accordance with all
local, state, and federal codes and regulations. The Contractor must:
2.1.1. BASE BID
• Contractor will demolish current lift station
• Excavate area to facilitate installation of new sewer piping originating from
Building 32 and terminating into the City of Tifton Sewer system in the vicinity
of the arrow pictured below
• Provide connection to Building 32 & City of Tifton Sewer system, ensuring
proper fall/slope is achieved to facilitate removal of sewage water/material.
• Backfill any excavations to grade
• Remove and dispose of all materials as necessary
• Contractor will ensure the integrity of the sewer system post-repair and provide a
1 year warranty on parts and labor.
2.2. The Contractor will verify all dimensions and site conditions prior to beginning work.
No Government equipment will be available for use by the Contractor. The Contractor
must provide their own restroom facility.
2.3. LOCATION OF WORK
The project is located at/in the vicinity of 2773 Davis Road, Tifton, Georgia.
-- 2 of 7 --
Solicitation Number and Building 32 Sewer Repair
Page 3 of 7
2.4. PRE-BID SITE VISIT
Interested vendors are encouraged to visit the site and be escorted by a government
representative to confirm locations, dimensions, and conditions of the project before a
quote is submitted. The purpose of a site visit is to observe conditions relevant to the
completion of this project. No consideration will be given to claims based on lack of
knowledge of existing conditions, except where contract documents detail definite
provisions for adjustment in cost or extension due to existing conditions not readily
foreseeable.
3. PROJECT SCHEDULE
3.1. The completion of the project must not exceed sixty (60) calendar days from the date of
the Notice to Proceed (NTP).
-- 3 of 7 --
Solicitation Number and Building 32 Sewer Repair
Page 4 of 7
3.2. The Contractor must prepare an overall project schedule including milestone dates for
all phases of work and completion date; submit to the Contracting Officer’s
Representative (COR) for approval. This schedule is due fourteen (14) days after
contract award. The Contractor must track all work progress to ensure that the project
is completed according to the schedule. Include work week schedule with daily starting
and stopping time.
3.3. The Contractor must coordinate and confirm the dates for all work with the COR. If
necessary, any request for a time extension must be submitted to the Contracting Officer
(CO) in writing. Each request must include specific and detailed reasons in support of
the schedule alteration and provide an updated schedule for completion. No extension of
the period of performance may be given without the written authority of the CO.
3.4. Project work hours are 7:00 am and 4:00 pm, local time, Monday through Friday;
federal holidays excluded. The contractor is not required to provide services on
recognized Federal holidays established by Federal law (5 U.S.C. 6103). Any changes to
work schedule must be submitted to CO for written approval prior to any schedule
change.
4. GENERAL REQUIREMENTS
4.1. PERMITS
The Contractor must obtain all building and trade permits necessary to include any
drawings, plans, permit and inspection fees, utility location, site surveys, and any other
items necessary for compliance with state, local, and federal building authorities.
4.2. SAFETY
The Contractor must submit a Site Safety Specific Plan/Accident Prevention Plan (Plan)
in industry recognizable format to the COR within seven (7) days of contract award.
The Plan must include phone numbers and maps to local physician offices and the
nearest hospital. The Government will review and approve the Plan before issuance of
the NTP.
4.3. EXISTING INSTALLATIONS/DEMOLITION
Coordinate removal of existing installations with COR. All disturbances of existing
systems must be coordinated with the COR to prevent disconnecting equipment that
may jeopardize on-going research.
4.4. QUALITY CONTROL
Provide quality control to ensure that all components of project work meet the
requirements of the contract specifications. Ensure that all work not acceptable or
compliant with the specifications is corrected prior to inspection or review by the
COR. Quality control is the exclusive responsibility of the Contractor.
-- 4 of 7 --
Solicitation Number and Building 32 Sewer Repair
Page 5 of 7
4.5. PROTECTION OF WORK AND PROPERTY/SAFETY REQUIREMENTS
4.5.1. The Contractor must protect the work, the site, and all existing property and
structures within the limits of the construction activities or that may be affected
thereby until acceptance of the work. Any damage to property must be repaired at
the Contractor’s expense to pre-damaged condition to the satisfaction of the COR.
4.5.2. Safety and health matters, as they relate to the work, are the exclusive
responsibility of the Contractor. The Contractor must furnish, ere…
Source: SAM.gov, as posted. Verify the current solicitation before responding.