What this opportunity is
The Department of Defense is buying a Closed-Circuit Television (CCTV) security system for Building 441A at Spangdahlem Air Base in Germany. This contract is open to all businesses, as there is no set-aside used. The notice type is a Combined Synopsis/Solicitation, meaning businesses should track this opportunity closely as it is both an announcement and a solicitation for bids.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
STATEMENT OF WORK (SOW)
FOR
INSTALLATION OF CLOSED-CIRCUIT TELEVISION (CCTV) SECUIRTY SYSTEM
SPANGDAHLEM AIR BASE, GERMANY
12 JUNE 2026
Installation of Closed-Circuit Television (CCTV) Security System
Building 441A
1. Overview
The purpose of this project is to provide and install a comprehensive Closed-Circuit Television
(CCTV) Security System for Building 441A. The system shall provide real-time monitoring,
video recording, storage, analytics, and security coverage for designated areas within the facility.
2. SUMMARY
The Contractor shall perform all work and furnish all labor, supervision, tools, materials,
equipment, transportation, permits, licenses, and incidentals necessary to accomplish the project
described herein. The work consists of the complete installation, configuration, testing,
commissioning, training, and maintenance of a CCTV security system in Building 441A.
The Contractor shall provide a fully operational CCTV system that includes infrastructure,
cameras, monitoring equipment, data storage, software licensing, programming, training, and
maintenance support as specified in this Statement of Work.
3. SCOPE OF WORK
The project consists of the following five components:
1. Infrastructure
2. Cameras
3. Monitoring System
4. Data Storage
5. Programming and Maintenance
The infrastructure portion of the project shall be completed prior to installation of cameras,
monitoring equipment, and system commissioning.
-- 1 of 5 --
Training shall be provided for all monitoring equipment and software, including extension of
camera visualizations to designated management offices.
4. CCTV SYSTEM REQUIREMENTS
4.1 Infrastructure
The Contractor shall provide and install all infrastructure necessary to support the CCTV system,
including but not limited to:
• Network switches
• SFP modules/transceivers
• Patch cords
• Cabling and connectors
• Mounting hardware
• Power supplies and associated equipment
• Network integration components
All cameras shall be connected to the Building 441A wireless network infrastructure unless
otherwise approved by the Government.
4.2 Cameras
The Contractor shall furnish and install a minimum of eight (8) cameras as required to provide
complete coverage of designated areas.
Camera requirements shall include:
• Day and night recording capability
• High-definition video quality
• Wide Dynamic Range (WDR)
• Color imaging capability
• Real-time video transmission
• Anti-vandal and tamper-resistant housing
• Continuous monitoring and recording capability
• Coverage of all designated areas including:
o Play Place
o Lobby
o Gymnasium
o Additional areas as determined during site survey
4.3 Monitoring System
The Contractor shall provide a complete monitoring solution including:
• Monitoring workstation(s)
• Video management software
-- 2 of 5 --
• Software licenses
• Video analytics capabilities
• User access controls
• Live and recorded video viewing functionality
The monitoring station shall include:
• Minimum of one (1) 27-inch monitor for every eight (8) cameras installed
• Extension of camera viewing capability to designated office locations
• Real-time viewing and playback functionality
4.4 Data Storage
The CCTV system shall provide:
• Minimum thirty (30) days of continuous video retention
• Secure storage of recorded video
• Search and playback functionality
• Protection against data loss and corruption
4.5 Programming and Maintenance
The Contractor shall:
• Configure and program all CCTV equipment
• Configure recording schedules and retention periods
• Configure user permissions and administrative access
• Test and commission the entire system
• Provide operator training and system documentation
5. TRAINING REQUIREMENTS
The Contractor shall provide comprehensive training for designated personnel covering:
• System operation
• Monitoring procedures
• Video retrieval and playback
• Administrative functions
• Basic troubleshooting procedures
• Software utilization
Training shall be completed prior to final system acceptance.
-- 3 of 5 --
6. WARRANTY AND MAINTENANCE
The Contractor shall provide a minimum two (2) year warranty covering defects in
workmanship, materials, equipment, and installation.
The Contractor shall be responsible for correcting any defects discovered during the warranty
period at no additional cost to the Government.
The Contractor shall also provide a separate renewable service package proposal for:
• Annual preventative maintenance
• Software updates
• Software license renewals
• Life-cycle replacement planning
• System support services
• Equipment replacement recommendations
7. SOFTWARE AND LIFE-CYCLE SUPPORT
The Contractor shall provide:
• All required software
• Software licenses
• Software updates during the warranty period
• Life-cycle replacement recommendations
• Ongoing support and maintenance capabilities
8. CLEANUP
The Contractor shall maintain a clean and safe work environment at all times.
Upon completion of each work period and at project completion, the Contractor shall:
• Remove debris and waste materials
• Clean work areas
• Dispose of materials in accordance with applicable regulations
• Restore affected work areas to original condition
9. ENVIRONMENTAL REQUIREMENTS
The Contractor shall comply with all applicable environmental laws, regulations, and
installation-specific environmental requirements.
-- 4 of 5 --
10. ANTITERRORISM AND SECURITY REQUIREMENTS
The Contractor shall comply with all applicable installation security requirements, force
protection measures, and antiterrorism regulations while performing work on site.
11. SAFETY REQUIREMENTS
The Contractor shall take all necessary precautions for the safety and protection of personnel,
property, and equipment.
The Contractor shall comply with all applicable:
• Federal regulations
• State regulations
• Local regulations
• Occupational safety requirements
• Installation safety requirements
• Applicable …
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 334220)
Fire Truck Wireless Headsets
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 7, 2026
HPX-1 Plus Computed Radiography System
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION · Special Notice · due July 29, 2026
High Power Amplifiers
HEALTH AND HUMAN SERVICES, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 3, 2026
Sources Sought 36 CES/CEF Radios for Engine 16 and 20
DEPT OF DEFENSE · Sources Sought · due July 31, 2026
59--COUPLER,DIRECTIONAL
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 3, 2026