Electrical Infrastructure Upgrade (Optics)
JUSTICE, DEPARTMENT OF
Notice type
Solicitation
Solicitation #
SV0218-26
NAICS
238210
PSC
N059
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
July 7, 2026
Response due
August 12, 2026
Place of performance
Butner, NC
Description
1.0 SCOPE
The scope of this project will be performed at FCI – Butner, Unicor 2 HWY 75, Butner, North
Carolina 27509. The scope of work is primarily electrical.
2.0 PERFORMANCE REQUIREMENTS
The performance requirements of this project include: New utility service which includes a
new pad-mounted transformer, and upgrades to the facility’s electrical service and
distribution equipment to accommodate the new and future Injection Molding Machines.
All work will be performed inside the secure zone of the facility, except for the new utility
service.
2.1 REQUIREMENTS
a. This statement of work provides an overview of the project and is not all
encompassing for the project scope of work. The project scope of work shall
include the statement of work, contract documents and specifications. The
documents include the following:
1) Drawings –
i. G000 - Title Sheet & Overall Plan
ii. E001 – Symbols and Abbreviations
iii. E100 - Partial Site Plan
iv. E101 – Floor Plan – Electrical
v. E102 – Partial Floor Plan – Electrical
vi. Electrical Feeder Diagrams
vii. Panel Schedules
2) General Conditions –
3) Technical Specifications –
i. 260050 – Basic Materials and Methods
ii. 260519 – Low-Voltage Electrical Power Conductors and Cables
iii. 260526 – Grounding and Bonding for Electrical Systems
iv. 260529 – Hangers and Supports for Electrical Systems
v. 260533 – Raceway and Boxes for Electrical Systems
vi. 260544 – Sleeves and Sleeve Seals for Electrical Raceways and
Cabling
vii. 262416 – Panelboards
viii. 262813 - Fuses
-- 1 of 5 --
b. All work shall be performed at a minimum in accordance with the latest applicable
edition adopted by the Authority having jurisdiction of the applicable standards and
codes. Reference General Electrical Notes on Sheet E001.
c. Drawings are diagrammatical. All electrical equipment locations are approximately
only. For all measurements use field surveys. Wiring and conduit systems are
strictly diagrammatic and do not indicate every required fitting, elbow, transition,
junction box or similar items that are required for a complete system.
d. A New Utility pad-mounted transformer to be furnished and installed by Duke
Energy. All work associated with new utility service is required to be coordinated
with Duke Energy. Reference Site Plan (Sheet E100) and Feeder Diagrams (Sheet
E201).
1) Contractor shall provide new concrete pad and required underground
conduits in accordance with Duke Energy’s standards. Refer to Sheets E100
and E201.
i. Contractor shall contact Duke Energy’s and obtain their Installation
Standards and Requirements prior to commencement of work. All
work shall be coordinated with Duke Energy.
ii. Contractor shall obtain Duke Energy’s list of approved vendors for
the new utility transformer pre-cast concrete pad.
iii. Contractor shall provide support and compaction of pad. Pad must
support the transformer weight with backfill and compacted to 95%
density as per ASTM D 698 to prevent uneven settling.
iv. Pad shall be installed to ensure water drains away from the
transformer.
v. Trenches shall be backfilled to provide a stable and level base.
2) Contractor shall provide transformer pad grounding. Refer to typical
grounding detail on sheet E100.
i. Contractor shall obtain Duke Energy’s pad mounted transformer’s
grounding requirements and provide grounding in accordance with
their requirements.
3) The underground service will require the installation of an in-ground pull box,
and extension of existing secondary feeders to new pad-mounted
-- 2 of 5 --
transformer. Refer to Sheet E100 for approximate location and Sheet E201
for demolition and new work.
i. It is the Contractor’s responsibility to field verify exact location of
existing pad mounted transformer, existing feeder locations, new in-
ground pull box, feeder extension to new pad-mounted transformer,
etc.
4) The existing utility transformer pad and associated conduits not to be reused
shall be removed. Contractor shall coordinate with Duke Energy for removal
of transformer. Refer to Sheets E100 and E201 for demolition and new work.
e. Existing service entrance panelboard “EP2” shall be replaced with new. Existing
panelboard shall be removed and new service entrance panelboard shall be
installed. Refer to Sheet E101 for existing location and Sheet E201 for new location.
1) New Service Entrance Panelboard “EP2” - Refer to Sheet E202 and
Specification Section 262416.
2) The installation of the new panelboard will require the connections of
existing panelboards (existing feeders) and new panelboards (new feeders) to
new service entrance panelboard.
i. Refer to Feeder diagrams on sheet E201 for demolition and new
work.
ii. It is the Contractor’s responsibility to field verify existing conditions
and obtain approved routing of new feeders in the field with Owner’s
representative.
iii. Field measurements are required for feeder lengths.
3) One existing panelboard “EP5” in shop area will require new feeders to be
provided to new panelboard “EP2”
i. Refer to Sheet E102 for location of panelboard and Sheet E201
Feeder diagram for demolition and new work.
ii. It is the Contractor’s responsibility to field verify existing conditions
and obtain approved routing of new feeders in the field with Owner’s
representative.
iii. Field measurements are required for feeder lengths.
-- 3 of 5 --
f. Two new branch panelboards shall be provided. One panelboard “EP6” located in
shop area and one panelboard “EP7” located in the electrical room. Refer to Sheet
E102 for panelboard locations.
1) New Panelboard “EP7” - Refer to Sheet E202 and Specification Section
262416.
2) Panelboard “EP7” shall be connected to the existing 300 kva transformer
located in the electrical room. This will require existing feeder connections
to existing 300 kva transformer to be removed and new provided. New
feeders for transformer include the primary and secondary sides of
transformer. Refer to Feeder Diagrams on sheet E201 for demolition and new
work.
i. It…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238210)
ELECTRICAL WORK
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 20, 2026
Insulation Resistance Testing Services
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due August 10, 2026
US Coast Guard Air Station Savannah Generator
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 19, 2026
22 MXS - Power Pitts & Jet Power Unit Troubleshooting - McConnell AFB
DEPT OF DEFENSE · Solicitation · due August 11, 2026