Repair MAF and Base Fire Alarms - DSN/CSN, IDIQ
DEPT OF DEFENSE
Notice type
Presolicitation
Solicitation #
FA4626-26-R-0012
NAICS
238210
PSC
Z2JZ
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
June 17, 2026
Response due
July 2, 2026
Place of performance
Malmstrom AFB, MT
What this opportunity is
The government is buying repair services for fire alarms at a base in Montana. This procurement is set aside for total small businesses. The notice is a presolicitation, indicating that businesses should track the opportunity for a potential future solicitation rather than bidding immediately. The NAICS code 238210 and PSC Z2JZ further specify the scope of the work.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
Repair MAF & Base Fire Alarms
Project Number NZAS 25-0008
341 CES
Malmstrom AFB, MT
GENERAL REQUIREMENTS
1.00 General Scope
The Contractor shall perform all design, submittals, materials, installation services, and system programming and
testing, required for the accomplishment of repair of fire protection systems located in Malmstrom Air Force Base
(AFB) facilities and in the Missile Alert Facilities. All work shall be accomplished at the work sites in accordance with
drawings, specifications, provisions, and terms of this contract, and according to the Statement of Work (SOW)
presented with each individual Task Order (T.O.).
1.01 Major Items of Work
The purpose of this effort is to provide design/report documents, installation, programming, and certification to
repair the fire protection systems at Malmstrom AFB facilities and Missile Alert Facilities to comply with current Air
Force Design Guide, Global Strike/Materials Command Design Directives, Base Standards, and referenced
publications. The intent is to provide an upgraded system that fully complies with current USAF design standards,
Unified Facilities Criteria (UFC). See the latest UFC Design Procedures at www.wbdg.org where applicable.
1.01.1 Design
Task orders may include some or all of the following:
a) Design shall provide for a new Potter Alarm Signal Company control panel (no substitutes), installation of
new detectors and alarm/notification devices, relocation of new detectors and alarm/notification devices
where applicable, installation/re-location of pull stations, and new conductor and raceways if required to
meet code requirements.
b) Design shall be completed by a person with National Institute for Certification in Engineering Technologies,
Fire Alarm System, Level III FAS certification, at a minimum. Design submittals must bear the review stamp
of a Qualified Fire Protection Engineer.
c) The design shall include all alarming and sensors for existing standpipe suppression systems.
d) The design shall provide for HVAC modifications in regard to automatic shutdown and necessary duct
dampers.
e) A 50% and a 100% design submittal to include all drawings and product data for all devices to be provided
for MAFB review.
f) Contractor shall provide an independent third party to perform asbestos and lead-based paint testing and
surveys and the results shall be included in a report. Any previous asbestos and lead-based paint surveys
shall be provided to the contractor and shall be included in the report, if available.
1.01.2 Construction
Electrical work must be performed by qualified personnel with credentials who are familiar with
applicable code requirements and shall provide credential documents upon request. A NICET Level 2
FAS or higher Fire Alarm Technician shall install and terminate fire alarm devices, cabinets and panels.
An electrician or NICET Level 1 FAS shall install conduit and conductors for the fire alarm system.
Verifiable credentials consist of State, National and Local Certifications or Licenses that a Master or
Journeyman Electrician may hold, depending on work being performed, and shall conform to all
-- 1 of 5 --
requirements of the project specifications. Provide Manufacturer's certificate of acceptance of the
qualifications of the installing contractor to install, test, conduct owner training, and maintain the
manufacturer's equipment.
No on-site or on-base facility will be furnished to the Contractor for storage or office use.
All non-hazardous waste shall be properly disposed of through a licensed landfill site. No landfill site is
available on base. The cost for cleanup of improperly disposed waste shall be the responsibility of the
contractor.
1.02 Period of Performance
Upon receipt of the approved delivery order, the contractor shall complete all work up to and including
solicitation document submittals according to the schedule in the associated SOW with each T.O., with “Day 1”
corresponding to the date of the signed delivery order. Submittals will be delivered to the government within
each scheduled period, in accordance with the submittal schedule shown in the SOW. Should a resubmittal be
required, the government will provide a date for which the resubmittal is due, and the remaining milestone
completion dates will be extended the same number of days. If any Government review period is completed in
fewer days than shown in the schedule, no change to the next due dates will be made. If any Government review
period takes longer than the indicated maximum number of days shown in the schedule, the contract will be
extended by the number of days that were exceeded.
1.03 Work Schedule
The Contractor shall notify the Contracting Officer at least five workdays in advance of the start of all work.
This shall include, but is not limited to, notifying CAO when the initial work shall begin and when work shall
resume following the end of all specified exclusion periods. The Contractor shall be aware that the Notice to
Proceed is not sufficient notification as to when initial work will begin.
Malmstrom AFB: Base-side work schedule shall be specified per T.O.
Missile Alert Facilities: The work schedule will be 6:45 am – 5:15 pm Monday through Thursday, and no work
will be conducted on Federal Holidays.
1.04 Government Furnished Information and Materials
The following information and materials will be made available to the Contractor:
Existing site and building plans and details, if they exist. It is the responsibility of the contractor to request
these items if required, and to verify their completeness and accuracy at the project location
Standard USAF title blocks and other drawing features to be used for final contract drawings on CD
Submittal schedule format for use with MS Excel
Unique fire protection or other design requirements, as applicable.
1.05 Codes, Criteria, and Regulations
The project will comply with all applicable laws, National Codes and Regulations for building construction …
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238210)
Lights & Electric Repairs
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 9, 2026
Wolf Creek, Cordell Hull, & Old Hickory Power Plants: VCB Repair
DEPT OF DEFENSE · Sources Sought · due June 24, 2026
ISP CAT-6 Cabling for B20388
DEPT OF DEFENSE · Combined Synopsis/Solicitation · due July 17, 2026
Z1NZ--657A5-26-111, Triennial Electrical l MA FY27 NRM
VETERANS AFFAIRS, DEPARTMENT OF · Sources Sought · due June 29, 2026
N--GC26 SCADA UPS REPLACEMENT
INTERIOR, DEPARTMENT OF THE · Solicitation · due June 26, 2026
Z--PEFO Replacement of Lighting
INTERIOR, DEPARTMENT OF THE · Solicitation · due June 30, 2026