Replace Potable Water Valve on Pier for USCG in Natchez, MS
HOMELAND SECURITY, DEPARTMENT OF
Notice type
Combined Synopsis/Solicitation
Solicitation #
70Z02926QNEWO33
NAICS
237110
PSC
Z2NE
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
July 13, 2026
Response due
July 27, 2026
Place of performance
Natchez, MS
Description
CONTRACT SPECIFICATIONS
Replace potable water valve on pier at CGC GREENBRIER
AT
UNITED STATES COAST GUARD
CGC GREENBRIER UPH BUILDING,
NATCHEZ, MS 39120
PROJECT NUMBER 31769753
2026
-- 1 of 18 --
SecƟon 01 11 00
Page 2 of 18
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1. GENERAL DESCRIPTION
1.1.1. General Work Requirements
Furnish all labor, tools, equipment, and materials for a new potable water
connection.
The Base Bid work generally includes, but is not limited to, the following:
A. Contractor will replace inground 2.5-inch valve (Figure 1) that connects city
water to current underground piping for potable water hookups. Replacement
2.5-inch valve (Figure 2) is already purchased by unit and is in inventory.
Contractor will remove and replace all PVC piping aŌer the valve. There are
approximately 25 feet of below ground piping between the valve and where it
reaches the surface near the wooden fence.
B. Contractor will remove and replace 2.5-inch 80 Schedule PVC piping that
connects 2.5-inch inground valve to potable water hookups. There are
approximately 65 feet of piping from valve that comes above ground and runs
across wooden railing towards the tramway (Figure 3). The piping then reduces
to 2.0 inch and runs underneath the tramway and down approximately 88 feet
(Figure 4). Contractor will add a reducer from 2.5 inch to 2.0-inch 80 Schedule
for the PVC that will run underneath the tramway.
C. Contractor will have two secƟons of piping that tee off from the 2-inch PVC
piping under the tramway and reduce to 1.5-inch 80 schedule PVC piping. The
1.5-inch Piping will come around the side of the tram and serve as access to
the potable water hookup. The hookups will have a bleed valve on one side
and a cut off valve on the other side with a 1.5-inch NH thread adapter to act
as the potable water hook up locaƟon. The NH thread will be facing down
towards the boƩom of the tramway, and the bleed valve will be facing up.
These hook up locaƟons will be approximately located next to the two highest
pins next to the tram, 87 feet apart.
D. Contractor will need to coordinate with the city water company for shutoff and
turn back on. Potable water shall not be shut off to the building longer than
the workday.
-- 2 of 18 --
SecƟon 01 11 00
Page 3 of 18
E. Measurements and Quantities. All piping lengths and linear measurements
provided in this SOW (e.g., "approximately 25 feet," "approximately 65 feet")
are estimates intended for general scoping purposes only. Bidders are solely
responsible for conducting their own measurements, verifying routing, and
assessing all site conditions during the scheduled site visit. The Government
will not be liable for, nor entertain requests for equitable adjustment
regarding, discrepancies between the estimated lengths in this SOW and the
actual material quantities required to successfully execute the work.
F. Excavation, Backfill, and Surface Restoration. The contractor shall be
responsible for all trenching and excavation required to replace the below-
ground piping. Upon successful completion and hydrostatic testing of the
newly installed line, the contractor must:
Backfill the excavated trench using suitable material.
Compact the soil adequately to prevent future ground settling.
Restore the surface area to match the surrounding pre-construction
grade and condition (e.g., replacing sod, gravel, or topsoil as
applicable).
G. This summary is not all inclusive and delineates only that work items deemed
as major to the contract. Ancillary work items necessary to attain the
completed project shall be included in the contract as inherent to the work.
1.1.2. GOVERNMENT-FURNISHED MATERIAL (GFM)
The Government will furnish one (1) new 2.5-inch valve for installation.
Photos of government furnished valve are attached in this solicitation.
The contractor is fully responsible for providing all necessary adapters, transition
fittings, flanges, and hardware required to successfully connect this government-
furnished valve to the newly installed PVC piping system.
1.1.3. SPECIFIC WORK REQUIREMENTS
A. Qualifications
-- 3 of 18 --
SecƟon 01 11 00
Page 4 of 18
(1) The installation shall be performed by a contractor certified in the state
of Mississippi.
(2) The installation shall comply with the most current edition of the
International Plumbing Code (IPC) and the Uniform Plumbing Code
(UPC).
B. Additional Performance Requirements
(1) Contractor shall be responsible for disposing of the material that is being
replaced.
1.1.4. SPECIAL WORK REQUIREMENTS
A. Comply with all hot work requirements of the Coast Guard unit.
B. Coordinate all staging and laydown areas with the Coast Guard prior to work
starting.
1.2. TEMPORARY FACILITIES OR UTILITIES
None required.
1.3. PROJECT PERFORMANCE PERIOD
A. The total contract performance period shall include not only the time needed
to complete the base bid and approved option items, but it also includes the
time needed to submit, review, and approve all material submittals, and
complete all project record (closeout) documents. After work begins at the
site, perform the work continuously during normal working hours and show
daily progress until all work is complete.
B. The total contract performance period is 120 calendar days.
1.4. LOCATION
The work is located at:
U.S. Coast Guard Cutter GREENBRIER
44 L E Barry Rd
Natchez, Mississippi 33120
-- 4 of 18 --
SecƟon 01 11 00
Page 5 of 18
Arrangements for visiting the site may be made by contacting:
Chief Anthony DeLorenzo
Email: Anthony.B.Delorenzo@uscg.mil
Telephone: (601) 431-0879
1.5. VISUAL REFERENCES AND SITE CONDITIONS
The figures and photographs embedded within this document serve as the primary
visual reference for the required scope of work. Bidders must review all figures
carefully. Contractors are responsible for verifying all existing site conditions,
clearances, and dimensions prior to submitting a proposal.
1.6. WORK HOURS
1.6.1. Normal Working Hours
A. Perf…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 237110)
MONITORING WELL ABANDONMENT, EASTON MD
INTERIOR, DEPARTMENT OF THE · Solicitation · due August 6, 2026
USFWS FLINT HILLS NWR, KS - PUMP REPLACEMEN
INTERIOR, DEPARTMENT OF THE · Solicitation · due August 24, 2026
Contractor shall furnish and install a Septic Tank Drain Field for SR#584 in White Cloud, KS (Brown County)
HEALTH AND HUMAN SERVICES, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 3, 2026
TAFB MACC-BOA | Formal RFP for WWYK240146 - Design & Implement Monitoring & Control System for IWCS, Bldg. 62516
DEPT OF DEFENSE · Solicitation · due July 27, 2026
TAFB MACC-BOA | Formal RFP for WWYK240146 - Design & Implement Monitoring & Control System for IWCS, Bldg. 62516
DEPT OF DEFENSE · Solicitation · due July 27, 2026
Well 4 PFAS/PFOA Upgrade
DEPT OF DEFENSE · Solicitation · due September 8, 2026