The National Institutes of Health is soliciting a total small business set-aside contract for design/build services to replace the existing emergency electrical system in Building 49, including outdated switchgear, generators, and distribution panels. This project is suitable for small businesses with experience in electrical system design and construction, particularly those with expertise in high-capacity equipment installation. The solicitation is a formal bid process, requiring interested contractors to track the solicitation and submit a proposal. The project will be performed in Maryland.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
WR#: C104567 December 17, 2025 Page 1 of 27
NATIONAL INSTITUTES OF HEALTH Office of Research Facilities
Division of Design and Construction Management
Bldg 13, Rm. 2S275, 9000 Rockville Pike, Bethesda, MD 20892
STATEMENT OF WORK
WORK REQUEST # C104567
DESIGN/BUILD SERVICES for
BUILDING 49 – SWITCHGEAR REPLACEMENT AND
GENERATOR UPGRADES
1.0 BACKGROUND
1.1 PROJECT BACKGROUND
NIH’s building 49 is a 274,500 square foot rectangular building consisting of eight stories. Primary use is
for office, research, and various use laboratories including a CAF (Central Animal Facility). The building
was originally constructed in 1993 with a substantial number of renovations over subsequent years.
The existing emergency electrical system no longer meets NIH performance or readiness standards. Its
replacement is vital for ensuring compliant, reliable operation in the various use laboratories including
sensitive vivarium operating room suites within the CAF (Central Animal Facility), research laboratory
and offices suites throughout building 49.
NIH ORF (Office of Research Facilities) identified the need for the replacement of the existing emergency
equipment in electrical vault, which currently contains 1500kW Diesel Generator, Day tanks and
switchgear, Switchboard, distribution panels, transfer switch etc. that are outdated and no longer meet
present-day standards for capacity, efficiency, and reliability. Due to the age and deteriorating condition of
these components, their continued use poses operational and safety concerns. As part of the Design-Build
Contractor’s proposed design, the existing electrical equipment shall be removed and replaced with new,
with similar/higher-capacity equipment.
1. PROJECT CONTACT PERSONS:
A. CONTRACTING OFFICER (CO) - Overall authority in all matters for this project:
Mr. Brian Baek
National Institutes of Health
Office of Acquisition
13 South Drive, MSC
Building 13, Room 2E48
9000 Rockville Pike, Bethesda, MD 20892-5759
Telephone: 301-435-1604
Email Address: brian.baek@nih.gov
B. PROJECT OFFICER (PO) - Project management and the CO’s Representative (COR):
Mr. Earl Johnson
Division of Design & Construction Management Branch (DDCM)
Office of Research Facilities, National Institutes of Health (NIH)
Building 13, Room 275
-- 1 of 27 --
WR#: C104567 December 17, 2025 Page 2 of 27
Bethesda, Maryland 20892
Telephone: (301) 594-7964
C. In this scope of work, the official Government point of contact will be the CO (Contracting
Officer) on all contractual matters and all technical/ RFI (Request for Information) inquiries shall
be addressed by the PO/COR. ALL contractual matters/changes shall be addressed in writing to
both the CO and the PO/COR, and written responses from the CO are the ONLY authorized
changes to the statement of work, price, schedule, or any other contractual matter.
2. PROJECT DESCRIPTION
A. This project shall employ sustainable design features to achieve flexibility, energy efficiency, and
quality work environment. The Design/Builder (DCB) team, which is capable of the design
services required to successfully and competently develop the drawings and specifications for this
type of project, provide construction documents and other instruments as required to fully facilitate
the work as described herein:
1. Project Title: Building 49 - SWITCHGEAR REPLACEMENT AND GENERATOR
UPGRADES
2. Work Request Number: C104567
3. Location: Building 49
3. SUSTAINABILITY
A. The DCB shall address sustainability in their proposal in accordance with FAR 23.1; see attached
Sustainability Plan Form and Sustainable “Green” acquisition guidelines.
4. CODES & STANDARDS
A. This project shall be designed in compliance with applicable codes and industry standards for the
location of the facility.
1. Model Building Codes
a. This project shall be designed to meet or exceed the applicable model building
code(s) for the location of the facility. The design shall use other appropriate
codes and industry standards such as: the Life Safety Code (NFPA 101), Fire
Protection for Laboratories Using Chemicals (NFPA 45), Standard for the
Installation of Sprinkler Systems (NFPA 13), and Healthcare Facilities (NFPA
99), and Guidelines for Design and Construction of Health Care Facilities, The
American Institute of Architects Academy of Architecture for Health with the
assistance from the U.S. Department of Health and Human Services (Note: The
Department of Health and Human Services (DHHS) as an agency of the
Government of the United States of America, derives its authority from the
Congress of the United States, and is not subject to laws, ordinances, regulations
established by state and local governments or authorities of a lesser jurisdiction).
2. Federal Regulations
a. This project shall be designed and constructed in compliance with all
applicable Federal Regulations including but not necessarily limited to the
following: Uniformed Federal Accessibility Standards, OSHA 29CFR 1910; The
National Environmental Policy Act of 1969 (NEPA); The Endangered Species
Act; The National Historic Preservation Act of 1966; The Archeological and
Historic Preservation Act; The Wild and Scenic Rivers Act; 40CFR
Environmental which includes: Safe Drinking Water Act, Clean Air Act, Clean
Water Act, Toxic Substance Control Act, Solid Waste Disposal Act, and RCRA;
Executive Order 11990 (Wetlands); Executive Order 11988 (Floodplains);
Executive Order 12088 (Compliance with State environmental laws); National
-- 2 of 27 --
WR#: C104567 December 17, 2025 Page 3 of 27
Capital Planning Commission (NCPC) "Master Planning Regulations"; Energy
Policy Act of 1992; Executive Order 13423 (Strengthening Federal
Environmental, Energy, and Transportation Management), etc.
3. Agency Design Policies
a. This project shall be designed in compliance with the latest edition of the NIH
Design Requirements Manual (DRM). The DRM is available online at:
https://www.orf.od.nih.gov/PoliciesAndGuidelines/BiomedicalandAn…