Description
Construct New Water Storage Facility
Veterans’ Healthcare System of the Ozarks (VHSO)
Fayetteville, AR
Project No: 564-19-101
Statement of Work
1 Foreword
1.1 Contractor shall provide all labor, materials, tools, equipment, expertise,
administration, supervision, and transportation as necessary to perform all work in accordance
with provided construction specifications, drawings, all documents attached to this contract, all
terms and conditions of this contract, and this statement of work.
1.2 This document does not relieve the Contractor of their professional responsibility to comply with
all local and federal construction and environmental codes and to perform and complete a fully
coordinated job.
2 General Project Description
2.1 This scope of work for the project involves the construction of a new water storage facility and
demolition of existing water storage facilities. All construction work shall be performed without
affecting VHSO Fayetteville, AR facility operation. Phasing of work is required. See attached
drawings.
2.2 Work includes construction, labor and supervision for civil, structural, architectural, fire
protection, plumbing, mechanical, electrical, security and electronics, and demolition work as
required by provided construction documents. This Scope of Work is not considered to be a
comprehensive description of work details for this project. All work shall be completed in
accordance with the plans/drawings and specifications.
2.3 Period of Performance (POP): Three hundred Thirty (330) calendar days after Notice-To-Proceed
(NTP).
3 General Construction Requirements
3.1 Prior to any mobilization and construction, the Contractor shall request and have an approved
Infection Control Construction Permit, Construction Safety Plan, and an Interim Life Safety
Measures Certification from VHSO Fayetteville, AR. Additionally, a project/construction
schedule, schedule of values/prices and construction phases shall be provided and approved by
VA’s Contracting Officer’s Representative (COR)/Project Engineer and/or Contracting Officer
(CO).
3.2 Contractor shall completely prepare site prior to the commencement of work and furnish labor,
equipment, and materials to perform work for this specific project as required by construction
documents.
3.3 The entire project’s associated construction and temporary work shall conform to the latest VA
specifications, VA Standards, energy conservation methods, EPA, OSHA, NFPA, NEC,
ASHRAE, LIFE SAFETY CODE, UBC, local, Federal and industry requirements and
regulations.
3.4 Project Record Drawings: The Contractor shall maintain a set of Record Drawings. The
Contractor shall maintain a set of construction documents (field as-built drawings) to record
actual construction changes during the construction process. The project record drawings shall
be available for review by the VA’s COR/Project Engineer, and/or CO at all times.
-- 1 of 6 --
3.5 The following milestone dates shall be incorporated into the Contractor’s schedule.
3.5.1 Submittal Schedule and log/register shall be provided within ten (10) calendar days
after Notice to Proceed. The Contractor shall provide the aforementioned documents to
the COR for approval and shall include the dates for submission of Shop Drawings,
Product Data, and Samples.
3.5.2 All Shop Drawings, Product Data and Samples shall be submitted and approved by the
VA within sixty (60) calendar days after Notice to Proceed. The VA shall provide the
Contractor with written comments within 15 business days after receiving each
submittal.
3.5.3 The Contractor shall submit a construction schedule within ten (10) calendar days after
Notice to Proceed. The construction schedule shall be prepared in terms of calendar days
(not working days). Once the construction schedule is submitted by the Contractor and
approved by the CO, no lateness in the schedule will be tolerated without the CO’s
approval.
3.5.4 A pre-construction meeting shall be held within ten (10) calendar days after award of
Contract. During construction, the Contractor shall attend all weekly construction
progress meetings. The meeting schedule and place will be discussed in the pre-
construction meeting.
4 General Contract Requirement
4.1 VA’s Normal Working Hours are 7:00 am to 4:30 p.m., Monday through Friday. Contractor shall
coordinate work with the COR in order to not disrupt VHSO Fayetteville, AR facility operations
which may include work earlier or later in the day and on weekends or federal holidays at no
additional cost to the VA. Noise disturbances and utility shutdowns/tie-ins shall be coordinated
with the COR and not interfere with VA daily operations.
4.2 Pursuant to clause 52.236-8 Other Contracts incorporated by reference under section 4.33 52.252-
2 Clauses Incorporated by Reference, Contractor shall fully cooperate with the other Contractors
and with Government employees and shall carefully adapt scheduling and performing the work
under this contract to accommodate the additional work, heeding any direction that may be
provided by the CO. If required by the CO, Contractor shall, at no additional cost to the VA,
coordinate with other VA’s activities including, but not limited to, construction activities near the
job site to ensure the construction work under this project will be in harmony with those activities.
This coordination shall include, but not limited to, the careful scheduling of work commencement,
equipment mobilization etc.
4.3 The following legal holidays are observed by this Government Agency:
New Year's Day January 1st
Martin Luther King's Birthday Third Monday in January
Presidents Day Third Monday in February
Memorial Day Last Monday in May
Juneteenth Independence Day June 19th
Independence Day July 4th
Labor Day First Monday in September
Columbus Day Second Monday in October
Veterans Day November 11th
Thanksgiving Day 4th Thursday in November
Christmas Day December 25th
and any day declared by the federal government as holiday.
5 Pr…