Question – Virkon-S Dwell Time and Post Rinse Requirement
Does the PWS require a specific dwell/contact time for the 1% Virkon-S solution after
application? Additionally, is a post-application rinse required, or is the process limited to
applying the solution and allowing it to air dry? This has a direct impact on labor time, water
usage, and wastewater volume.
Answer:
Applied as a liquid (1% solution)
Can be done using the SKUMIX 20 also
Mildly CORROSIVE in 1% solution. Contractor must rinse vehicle off when finished,
especially soft metals (aluminum & copper)
Creates large amounts of wastewater that must be disposed of per local regulations &
requirements
requires 10 minutes contact time and air dry per manufacture label, then rinse. A 1%
solution must also be used during the 10 minute contact to keep the surface wet via
misting or other application.
Question – Equipment Condition Upon Delivery
The PWS states the Army will deliver equipment pre-cleaned and free of dirt and debris
prior to Virkon-S application. Can the Government confirm that all 50 pieces of equipment
will arrive at the wash site in that condition? If equipment requires pressure washing or pre-
cleaning prior to disinfectant application, would that constitute additional scope outside
the current PWS?
Answer:
Yes, all equipment will be located close to the AGWASH station prior to the application.
UTARNG will pressure wash/ pre-clean all the equipment before sanitizing.
Question - Is it acceptable to use a pressure washer for the disinfection process?
Answer:
Can be applied using sprayers, foggers or misting systems.
Ensure you read the PWS for full understanding. Most questions are addressed there.
Question: Will the government provide electricity and water source?
Answer: Yes
Question: Will the contractor be allowed to leave their equipment onsite at the end of the
workday?
Answer: Yes, the government can coordinate with a nearby unit on Camp Williams to leave
the equipment at their building.
-- 1 of 2 --
Question: Is it acceptable for the prime contractor to utilize qualified subcontractors for
the agricultural wash and disinfecting services, provided the prime contractor remains
responsible for overall contract management and performance?
Answer: Yes
Question: The PWS references the use of Virkon-S and required licensing. Is it acceptable
for the required commercial pesticide applicator license to be held by a subcontractor
performing that portion of the work, rather than by the prime contractor directly?
Answer: See PWS: 1.4.7 Special Qualifications: The contractor shall ensure all employees
possess all required licenses for operating Virkon-S Ag Washing used in the performance of
this contract.
Question: Will the Government provide the wash rack, water source, and wastewater
containment/disposal infrastructure at Camp Williams, or should offerors include all
wastewater collection and disposal capabilities within their proposal?
Answer: we will provide the wash rack and water source. The contractor needs to collect
the wastewater and disposal.
Question: The PWS estimates 50 pieces, but the Q&A list includes 45 items. Should
offerors price the Q&A list specifically or a total of 50 pieces?
Answer: It is (38) pieces of rolling stock and (7) 20ft MILVAN Box Ship Containers. Totaling
45 pieces to be sanitized. However, there still may be some variation.
Question: What volume of wastewater should offerors assume for pricing purposes?
Answer: Per the attached slide, Virkon-S 1% solution “creates large amounts of wastewater
that must be disposed of per host nation/local regulations and requirements”.
Question: Is pressure washing required, or is a spray application of 1% Virkon solution
acceptable for equipment that is already clean?
Answer All rolling stock and ship containers have already been pressure washed and wiped
down. No other cleaning should be required.
Question: Does the application include undercarriages or only visible exterior surfaces?
Answer: Yes, undercarriages are required. The equipment will be power washed prior to the
AGWASH to ensure there is no Dirt, soil, vegetable matter etc. not visible on any external
surfaces.
-- 2 of 2 --
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 562998)
J045--Drain and Grease Trap Maintenance
VETERANS AFFAIRS, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 28, 2026
ANC Solid Waste W91QV126RA018
DEPT OF DEFENSE · Solicitation · due July 24, 2026
NS Graywater Service
DEPT OF DEFENSE · Solicitation · due July 24, 2026
ANC Solid Waste W91QV126RA018
DEPT OF DEFENSE · Solicitation · due July 24, 2026
Grease Trap Clean Out
DEPT OF DEFENSE · Presolicitation · due August 3, 2026
J045--Drain and Grease Trap Maintenance
VETERANS AFFAIRS, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 28, 2026