CES Expansion UPS Upgrade
DEPT OF DEFENSE
Notice type
Solicitation
Solicitation #
W91SMC26QA016
NAICS
236220
PSC
Y1AZ
Set-aside
Total Small Business Set-Aside (FAR 19.5)
Posted
July 27, 2026
Response due
August 25, 2026
Place of performance
Springfield, IL
Description
SCOPE OF WORK (SOW) FOR CONSTRUCTION SERVICES
Uninterrupted Power Supply (UPS) Expansion Upgrades, Building 8
DCFT 262002
183d Wing, Abraham Lincoln Capital Airport, Air National Guard Base, Springfield, IL 62707
PART I: GENERAL INFORMATION.
1. Introduction/ Description Services. This is a non-personal services contract to provide
upgrades to Uninterrupted Power Supply (UPS) System in Building 8 at the 183d Wing
(183WG).
1.1 Background. In 2020, existing 10-kilowatt (kW) UPS unit for Building 8 was installed.
Since the UPS project, there have been building additions to equipment, causing overload issues
to existing UPS system in Building 8. Additionally, existing UPS is a fixed type system and not
capable of being added to or have an additional unit working in parallel. Identified as
deficiencies, the UPS needs to be scalable for future 30 kW power load requirements and capable
of handling 20 kW current loads properly for future equipment additions to building.
1.2 Objectives. To provide upgrades to UPS system by removal of existing and installation of
new static UPS system in Building 8 at the 183WG that meets all applicable commercial and
United States (US) military standards/specifications to include Unified Facilities Criteria (UFCs)
and DoD Supplemental Technical Documents to include TP-19 Static Uninterruptible Power
Supply, as well as Federal, State, and local laws and regulations.
1.3 Scope. Contractor to provide all personnel, equipment, supplies, transportation, tools,
materials, supervision, and non-personal services to provide upgrades to UPS system by removal
of existing and installation of new static UPS system in Building 8 at the 183WG. The
Contractor (KTR) shall conform to details and specifications outlined in Part V of this Statement
of Work (SOW), along with attached drawings and photos to include 183WG Base Map – Work
Location, Existing B8 – Electrical Drawings, and Existing UPS System Photos.
1.4 Period of Performance. 120 days or less
1.5 Quality Control (QC). The KTR shall develop and maintain an effective QC program to
ensure services are performed in accordance with this SOW. The KTR shall develop and
implement procedures to identify, prevent, and ensure non-recurrence of defective services. The
KTR’s QC program is the means by which the company assures that work complies with the
requirement of the contract. The KTR’s QC Plan shall be delivered with your proposal and
submitted again to the Contracting Officer (KO) prior to the issuance of the Notice to Proceed
(NTP). After acceptance of the QC plan the KTR shall receive the KO’s acceptance in writing of
any proposed change to his QC program.
1.6 RESERVED
1.7 Contracting Officer’s Representative (COR). The COR will be identified by separate letter.
The COR monitors all technical aspects of the contract and assists in contract administration.
1.8 Hours of Operation. The offices where the services will be conducted are usually open
between the office hours of [7:00 AM and 4:30 PM] Monday through Friday with alternating
-- 1 of 19 --
Fridays off. The KTR shall plan to perform their services between those hours. If the facility is
closed during Federal holidays or during inclement weather, the KTR shall be notified. The
KTR must at all times maintain an adequate workforce for the uninterrupted performance of all
tasks defined within this SOW.
1.8.1 Holidays. Please check with the KO or COR for any additional holidays other than listed
here. The following are recognized Federal Holidays:
1.8.1.1 New Year’s Day
1.8.1.2 Martin Luther King Jr’s Birthday
1.8.1.3 President’s Day
1.8.1.4 Memorial Day
1.8.1.5 Juneteenth
1.8.1.6 Independence Day
1.8.1.7 Labor Day
1.8.1.8 Columbus Day
1.8.1.9 Veteran’s Day
1.8.1.10 Thanksgiving Day
1.8.1.11 Christmas Day
1.8.2 Work Outside Normal Hours of Operation. When the KTR desires to work other than the
aforementioned times, KTR shall submit a written request to the KO for approval, and written
approval thereof shall be required prior to proceeding with work. The request shall be submitted
to at least five (5) workdays prior to the proposed performance of work. The request shall
indicate the day/days, time/amount of work, and reason why permission should be granted to
perform work during nonstandard hours. Approval for work to be performed during nonstandard
time will be given only in cases of necessity.
1.9 Place of Performance. The work will be performed at the 183WG, Illinois Air National
Guard Base, Abraham Lincoln Capital Airport, Springfield, IL 62707-5001
1.10 Type of Contract. This will be a Firm Fixed Price contract.
1.11 Security Requirements. The KTR shall comply with all applicable installation/facility
access and local security policies and procedures, which may be obtained from the KO or COR.
The KTR shall also provide all information required for background checks to meet installation
access requirements to be accomplished by installation Security Forces. The KTR shall ensure
compliance with all personal identity verification requirements as directed by Department of War
(DoW), USAF, ANG, and/or local policy. Should the Force Protection Condition (FPCON)
change, the Government may require changes in KTR security matters or processes.
1.11.1 COMSEC/IT Security. All communications with DoW organizations are subject to
communications security (COMSEC) review. All telephone communications networks are
continually subject to intercept by unfriendly intelligence organizations. DoW has authorized
the military departments to conduct COMSEC monitoring and recording of telephone calls
originating from, or terminating at, DoW organizations. Therefore, the KTR is advised that any
time KTR place or receive a call they are subject to COMSEC procedures. The KTR shall
ensure wide and frequent dissemination of the above information to all employees dealing with
DoW information. The KTR shall abide by all Government regulations concerning the
-- 2 of 19 --
authorized use of the Governm…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 236220)
North Mills River Campground
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due September 4, 2026
GAOA South Park Office Rehab Pike National Forest
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 11, 2026
North Mills River Campground
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due September 4, 2026
43d Air Mobility Squadron_ Request for Proposal_FA445226R0012_B753 Kitchen Renovation
DEPT OF DEFENSE · Solicitation · due August 5, 2026
Greenhouse Phase V Renovation (Fargo, ND)
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 6, 2026
Solicitation N4008526R0187 MULTIPLE BARRACKS RENOVATION AT SOUTH CAROLINA MARINE CORPS BASES
DEPT OF DEFENSE · Solicitation · due August 24, 2026