PRICE SCHEDULE
Provide line-item prices, where indicated by blank underlines, for the following items:
Line Item Description Quantity Unit Unit Price Sub-Total Total Price
0001A Subtotal of Base Price: Subtotal
for the entire work for Phase IV
BEQ Repairs Building 1245 in
accordance with the drawings and
specifications, complete, but
excluding work in provided in
another line item.
1 EA $___________
0001B Subtotal of Base Price: B1245 -
Move furniture and appliances to
Supply warehouse, move back to
the Barracks
2 EA $_______ $___________
0001 BASE PRICE: Total Price for
Phase IV BEQ Repairs Building
1245 (includes subtotal of 0001A-
0001B) for the entire work for the
project in accordance with
drawings and specifications but
excluding work provided in
another line item.
1 EA $____________
0002A Subtotal of Base Price: Subtotal
for the entire work for Phase IV
BEQ Repairs Building 1246 in
accordance with the drawings and
specifications, complete, but
excluding work in provided in
another line item.
1 EA $___________
0002B Subtotal of Base Price: B1246 -
Move furniture and appliances to
Supply warehouse, move back to
the Barracks
2 EA $_______ $___________
0002 BASE PRICE: Total Price for
Phase IV BEQ Repairs Building
1246 (includes subtotal of 0002A-
0002B) for the entire work for the
project in accordance with
drawings and specifications but
excluding work provided in
another line item.
1 EA $____________
0003 BASE PRICE: Building 332
Repairs – PI2501M – Total for
the entire work on drawings and
specifications.
1 EA $____________
Phase IV BEQ Repairs Buildings 1245 and 1246 OPTIONS
0004 Option 01: Bldg. 1245 Unit price
for shower wall repair,, complete
in accordance with the drawings
and specifications, but excluding
work provided in another Line
Item.
*11,000 SF $_______ $____________
-- 1 of 7 --
0005 Option 02: Bldg. 1246 Unit price
for shower wall repair, complete
in accordance with the drawings
and specifications, but excluding
work provided in another Line
Item.
*11,000 SF $_______ $____________
0006 Option 03: Bldg. 1245 Unit price
for Gypsum wall in kitchenette,
complete in accordance with the
drawings and specifications, but
excluding work provided in
another Line Item.
*1,800 SF $_______ $____________
0007 Option 04: Bldg. 1246 Unit price
for Gypsum wall in kitchenette,
complete in accordance with the
drawings and specifications, but
excluding work provided in
another Line Item.
*1800 SF $_______ $____________
0008 Option 05: Bldg. 1245 Unit price
for replacing exterior guardrails
on walkways of second and third
deck, complete in accordance
with the drawings and
specifications, but excluding
work provided in another Line
Item.
*1,960 LF $_______ $____________
0009 Option 06: Bldg. 1246 Unit price
for replaceing exterior guardrails
on walkways of second and third
deck, complete in accordance
with the drawings and
specifications, but excluding
work provided in another Line
Item.
*1960 LF $_______ $____________
0010 Option 07: Bldg. 1245 Unit price
for replacing metal roof deck, per
current structural (hurricane and
seismic) code, and install rigid
insulation on top of the roof deck,
complete in accordance with the
drawings and specifications, but
excluding work provided in
another Line Item.. This will
require the new fascia size to
increase by 6”
*28,000 SF $_______ $____________
0011 Option 08: Bldg. 1246 Replace
metal roof deck, per current
structural (hurricane and seismic)
code, and install rigid insulation
on top of the roof deck, complete
in accordance with the drawings
and specifications, but excluding
work provided in another Line
Item. This will require the new
fascia size to increase by 6”
*28,000 SF $_______ $____________
-- 2 of 7 --
0012 Option 09: Bldg. 1245 Repair
offsite in ceiling from misaligned
pre-tensioned concrete attic floor
slabs, complete in accordance
with the drawings and
specifications, but excluding
work provided in another Line
Item.
*800 SF $_______ $____________
0013 Option 10: Bldg. 1246 Repair
offsite in ceiling from misaligned
pre-tensioned concrete attic floor
slabs, complete in accordance
with the drawings and
specifications, but excluding
work provided in another Line
Item.
*800 SF $_______ $____________
0014 Option 11: Bldg. 1245 Unit price
for 14Ga metal frames to the 72
door frames with new exterior
slabs, complete in accordance
with the drawings and
specifications, but excluding
work provided in another Line
Item.
See Attachment B for further
details.
72 EA $_______ $____________
0015 Option 12: Bldg. 1246 Unit price
for 14Ga metal frames to the 72
door frames with new exterior
slabs, complete in accordance
with the drawings and
specifications, but excluding
work provided in another Line
Item.
See Attachment B for further
details.
72 EA $_______ $____________
0016 Option 13: Bldg. 1245 Unit price
for updating current fire alarm
control panels, complete in
accordance with the drawings and
specifications, but excluding
work provided in another Line
Item.
2 EA $_______ $____________
0017 Option 14: Bldg. 1246 Unit price
for updating current fire alarm
control panels, complete in
accordance with the drawings and
specifications, but excluding
work provided in another Line
Item.
2 EA $_______ $____________
-- 3 of 7 --
0018 Option 15: Bldg. 1245 Remove
existing window blinds and install
new blinds, complete in
accordance with the drawings and
specifications, but excluding
work provided in another Line
Item.
120 EA $_______ $____________
0019 Option 16: Bldg. 1246 Remove
existing window blinds and install
new blinds, complete in
accordance with the drawings and
specifications, but excluding
work provided in another Line
Item.
120 EA $_______ $____________
0020 Option 17: Bldg. 1245 Mill 1” of
paving on the parking lots and
basketball court area (500SY),
install 1” thick of new wearing
course (500SY), restripe
approximately 7,500 LF,
complete in ac…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 236220)
North Mills River Campground
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due September 4, 2026
GAOA South Park Office Rehab Pike National Forest
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 11, 2026
North Mills River Campground
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due September 4, 2026
43d Air Mobility Squadron_ Request for Proposal_FA445226R0012_B753 Kitchen Renovation
DEPT OF DEFENSE · Solicitation · due August 5, 2026
CES Expansion UPS Upgrade
DEPT OF DEFENSE · Solicitation · due August 25, 2026
Greenhouse Phase V Renovation (Fargo, ND)
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 6, 2026