What this opportunity is
The Department of Commerce is seeking services for the shipment of spent fuel cells under NAICS code 484230 and PSC V112. This opportunity is not set aside for small businesses, meaning any business can compete. The notice type is a Combined Synopsis/Solicitation, indicating that interested parties should prepare to submit proposals rather than simply track the opportunity. The work will be performed in Maryland.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
STATEMENT OF WORK
Spent Fuel Shipment
Requesting Lab: National Institute of Standards & Technology
Center for Neutron Research (NCNR)
BACKGROUND
The National Institute of Standards and Technology (NIST) Center for Neutron Research (NCNR) owns and operates a 20 MW test reactor called the National Bureau of Standards Reactor (NBSR). The NBSR is located on the NIST campus in Gaithersburg, Maryland, USA. The NBSR is a heavy water cooled and moderated reactor. The mission of the NBSR is to provide neutrons for world class measurements supporting the industrial, academic, and government needs of the United States. The NBSR is fueled by 30 highly enriched uranium fuel elements. During the course of a year, the NBSR produces approximately 28 spent fuel elements.
The fuel elements are made up of U3O8-Al Materials Testing Reactor (MTR) type dispersion fuel plates. There are two, 13-inch-tall stacks of fuel plates lodged in every fuel element with a gap of six inches between them. The fueled regions can be separated from the rest of the fuel element using an underwater saw to reduce high level radioactive waste shipments. The measurements for each fueled region are 13.5 in x 3.5 in x 3 in.
To be in accordance with the Nuclear Regulatory Commission (NRC), NIST is required to transfer its spent fuel to the Department of Energy (DOE) Savannah River Site (SRS) near Aiken, South Carolina.
OBJECTIVE
The goal of this procurement is for a qualified contractor to provide packaging and shipping services for spent fuel elements from the NCNR to DOE-SRS.
SCOPE
The action is for the packaging and shipment of the spent fuel cells in a single cask to the DOE-SRS. All the fuel sections will have been out of the reactor for at least two years.
BASE: Packaging and shipment of spent fuel cells to DOE-SRS.
OPTION 1: The scope will include an option for a second shipment within 2 years of the initial, base shipment.
REQUIREMENTS
General Requirements
The Contractor shall ensure all communications are on a need-to-know basis and in compliance with 10 CFR 73 requirements.
The Contractor shall ensure all paperwork is properly marked and handled according to pertinent NRC and Department of Transportation (DOT) regulations with copies being limited to only those required to complete the activity.
The Contractor shall submit a firm-fixed price quotation which meets or exceeds the requirements identified in this document. It shall address the required specifications and include descriptive literature, as required, to fully demonstrate how the technical approach will satisfy the task requirements.
The Contractor shall provide all project management, labor, materials, tools, and equipment to successfully meet the requirements in accordance with this Statement of Work, including providing the shipping cask, the transfer cask and basket, all rigging, and cranes and/or forklifts for movement of the transfer cask between the outdoor staging area and the designated indoor entry point in both directions. The Contractor shall also operate the cranes/forklifts they provide. The NCNR will provide indoor crane support above the pool area as well as the bridge over the pool. Only NCNR personnel will be permitted to operate NCNR-owned cranes. In the event the Contractor’s tools fail, to support the contingency situation and ensure the timed window for delivery is met, an attempt to aid the Contractor with tools will occur. However, this does not alleviate the Contractor’s responsibility to be prepared and provide all tools necessary to successfully complete this requirement. In the instance where the Government may provide tools, the Contractor shall take note and inventory to ensure the tools are returned after completion of this requirement.
The Contractor’s Project Manager shall be the single point of contact for all interaction. The Project Manager shall be onsite during the load and ship process.
The Contractor shall provide contact information for its designated main point of contact/Project Manager (i.e., Work Phone, Cell Phone, and email).
The Contractor shall provide all required security and badging information/paperwork to ensure timely access to NIST and the NCNR.
The Contractor shall submit a job-specific safety plan and project schedule for review and approval before notice to proceed is issued by the Contracting Officer.
The safety plan shall include radiological safety considerations. It shall, at a minimum, identify the risks associated with the loading and shipment of the spent fuel and how those risks will be mitigated. The Safety Plan shall address all safety risks from the commencement of the contract through the end of performance. The plan shall include an analysis of the significant hazards to life, limb, and property inherent in contract work performance and a plan for controlling these hazards.
The project schedule shall be coordinated with the NCNR and worked around the NBSR operating schedule.
All work shall be performed in compliance with industry, NIST, and OSHA standards, as well as all applicable Federal, State, and local regulations (DOT, NRC, etc).
The Contractor shall adhere to all relevant safety requirements and codes.
NCNR personnel will be onsite during normal business hours 7:00am – 5:00pm Monday through Friday. Services performed outside of this parameter shall be scheduled and approved 7 days in advance with the COR.
The Contractor shall ensure the work site is free of debris and trash upon job completion. The contractor shall remove its non-radiological waste from NIST premises.
The Contractor shall ensure existing site equipment and structures are protected while performing work. Any damage caused to existing site equipment and structures because of the work being performed shall be corrected by the Contractor prior to site acceptance.
Meeting Requirements
Kick-Off Meeting
The Contractor shall arrange a kick-off meeting…