STATEMENT OF WORK
FOR
DEMOLITION SERVICES
Demolish Fire Training Building, Facility 1345
PROJECT MUHJ 23-9004
JBLE-LANGLEY, VA
29 April 2026
-- 1 of 8 --
Draft
Solicitation
Attachment 3
2 of 8
STATEMENT OF WORK (SOW)
FOR
DEMOLITION SERVICES
1. DESCRIPTION OF SERVICE. The Contractor shall furnish all personnel, vehicles
and equipment required to perform Contractor services to demolish a Fire Training Build-
ing, Facility 1345 at JBLE-Langley, Virginia. All work shall be performed in accordance
with attached drawings, specifications, and all applicable laws, regulations, standards and
commercial practices as described in the statement of work with the focus on safety and
customer service. The period of performance is 60 days, (30 days for demolition and dis-
posal the structure and 30 days for seeding and grass establishment). The Contractor is
encouraged and expected to use innovative approaches to accomplish SOW requirements
efficiently and effectively in a timely manner at reduced costs, and in a way, which fosters
pride and ownership in the work performed.
1.1. SCOPE OF WORK.
The work under this project consists of demolishing a disused fire training building, Facil-
ity 1345 located at JBLE-Langley, VA. Demolish all appurtenances including (but not
limited to) foundation, footings, roofing, ceilings, walls, HVAC, concrete slab, and under-
ground utilities leaving a clean site.
The scope of work includes all required labor, equipment and material associated with the
demolition of one facility. The following is a list of principal items:
Ensure all utilities are disconnected at the point of entry for the facility. Disconnect and
cap any underground water, sewage electrical and Communication to the building. Dis-
connect electrical service from the closest electrical device serving the facility. Contractor
shall ensure demolition of all utilities will not disturb service to adjacent buildings to re-
main.
Upon completion of demolition, contractor shall refill ruts and other holes created by dem-
olition with suitable fill, then grade and reseed appropriately in accordance with 32 92 19
Seeding.
Adjoining property, roadways, parking areas, sidewalks and other adjacent items shall be
completely protected from damage during demolition activities.
All work shall be accomplished in accordance with specifications 01 11 00 Special Condi-
tions, 01 12 00 Environmental Management Special Conditions and 02 41 00 Demolition
and Deconstruction, 32 92 19 Seeding, drawings, and terms and conditions of the contract.
See Appendix A, B and C.
1.1.1. Demolition Notification. The Contractor shall provide written notification to the
Contracting Officer seven days prior to commencement of work identifying the following:
-- 2 of 8 --
Draft
Solicitation
Attachment 3
3 of 8
a. Building number
b. Demolition designation
c. Commencement date
d. Work hours, expected noise and vibration levels
e. Utility interruptions (dates and hours)
f. Demolition completion date
g. Contractor’s representative’s name and phone number for contract issues.
1.1.2. Demolition Debris. The Contractor shall use all reasonable means to divert demo-
lition and demolition waste from landfills and incinerators and to facilitate their recycling
or reuse. Revenues or other savings obtained from salvaging or recycling shall accrue to
the Contractor. The recycle materials shall be submitted to the Contracting Officer at con-
tract closeout. All demolished materials that cannot be recycled shall be legally disposed
of off base. All concrete and asphalt shall be recycled. All dump receipts shall be provided
to the Contracting Officer.
1.1.3. Drawings, Manuals and Checklists. The Contractor shall provide within 10 days
of final inspection, an AutoCAD version of as-built record drawings on computer disc and
one 24” x 36” paper copies of as-built record drawings. The drawings shall at a minimum
provide utility locations, correct grade and elevation if changed, and all changes or modi-
fications from the original design drawings. Ten days prior to final inspection, the Con-
tractor shall complete a DD Form 1354, Transfer and Acceptance of Military Real Property
for each building (see Appendix A).
2. SERVICE DELIVERY SUMMARY. The Service Delivery Summary (SDS) captures
the service requirements that can be measured and are considered to be critical operational
requirements. The SDS includes Performance Objectives that describe the desired end
result or outcome the Contractor shall achieve. The Performance Thresholds state the min-
imum acceptable level of performance in terms of quality, timeliness and quantity in real-
istic and achievable standards. These thresholds are critical to mission success. The SOW
paragraphs reference the details of the Performance Objective in the SOW. Each require-
ment includes a government-determined performance objective. (Note that the Perfor-
mance Objective is merely a reference point for government personnel and does not relieve
the Contractor of any other contractual requirements.)
2.1. SERVICE DELIVERY SUMMARY
PERFORMANCE OBJECTIVE PERFORMANCE THRESHOLD
Environmental Compliance: Comply
with all federal, state, local, and
JBLE-Langley, VA Environmental
Laws, Regulations, Instructions and
Publications and the National Emis-
sion Standards for Hazardous Air
The Contractor’s performance shall be deter-
mined ACCEPTABLE when the number of
discrepancies does not exceed 0 in any envi-
ronmental compliance requirement.
-- 3 of 8 --
Draft
Solicitation
Attachment 3
4 of 8
Pollutants (NESHAP) and attached
Specifications Sections
Demolish Building 1345 in accord-
ance with the SoW and standard com-
mercial practices
The Contractor’s performance shall be AC-
CEPTABLE when service does not exceed 2
valid customer complaints.
Utilities. Provide notification of any
disruption of service
The Contractor’s performance shall be deter-
mined ACCEPTABLE when service does
not exceed…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Open opportunities in NAICS 238910
F--Altus AFB Soil Excavation and Soil Fill
INTERIOR, DEPARTMENT OF THE · Presolicitation · due January 5, 2027
Forest Wide Decommissioning Project
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due December 7, 2026
Z--Garage Drywall Demolition at Udall Building
INTERIOR, DEPARTMENT OF THE · Combined Synopsis/Solicitation · due December 2, 2026
REMEDIATION AND RESTORATION ACTIVITIES
TRANSPORTATION, DEPARTMENT OF · Combined Synopsis/Solicitation · due November 23, 2026
Z--Garage Drywall Demolition at Udall Building
INTERIOR, DEPARTMENT OF THE · Combined Synopsis/Solicitation · due December 2, 2026
REMEDIATION AND RESTORATION ACTIVITIES
TRANSPORTATION, DEPARTMENT OF · Combined Synopsis/Solicitation · due November 23, 2026