Description
FI-MUE Replace Zama DSN-HHD Generator – Updated SOW
78th Signal Battalion – Camp Zama, Japan | Page 1 of 14
STATEMENT OF WORK (SOW)
FI-MUE Replace Zama DSN-HHD Generator
78th Signal Battalion
Camp Zama, Japan
Updated: 10 November 2026
(Incorporates responses to Contractor Questions / Clarifications)
1. INTRODUCTION
This Statement of Work (SOW) defines the requirements, scope, responsibilities, and deliverables for
the replacement and disposal of the 150 kVA emergency power diesel generator located on Camp
Zama, Japan, Building 121.
This updated SOW incorporates clarifications provided in response to Contractor (KTR) questions.
Where a conflict exists between this document and prior drafts, this updated version governs. The more
stringent of applicable U.S. or Japanese requirements shall apply.
2. SCOPE OF WORK
The contractor shall provide all necessary materials, equipment, labor, and services to:
2.1. Decommissioning and Removal of Existing Generator
• Disconnection from the electrical distribution system.
• Safe removal of residual fuel and proper disposal in accordance with environmental regulations.
• Safe removal of coolant and oil and proper disposal in accordance with environmental
regulations.
• Disassembly and transport of the existing generator from the site (Bldg. 121, Camp Zama) to an
authorized disposal facility. "Authorized waste disposal facilities" means facilities licensed under
Japanese laws and regulations.
• Removal and disposal of old conduits and exhaust piping that cannot be re-used for the new
generator system.
• The existing stainless-steel diesel fuel tank (renewed 2008 and confirmed serviceable),
associated fuel piping, and electrical wiring shall be retained if they remain in a serviceable
condition after contractor inspection, testing, and certification. Section 4.1 intent is to remove the
generator unit itself while retaining serviceable tank, piping, and wiring.
2.1.1. Asbestos Abatement and Removal in Building 121, Room 112
The contractor shall utilize the bulk asbestos sample summary and laboratory analytical results for the
following materials located in Building 121, Room 112. These have been identified as Asbestos-
Containing Material (ACM) and require abatement and removal.
• Silver wrapped pipe insulation: Samples 162-01A and 162-02A from Room 112 contained 95%
Chrysotile asbestos.
• Silver wrapped duct insulation: Sample 162-03A from Room 112 contained 50% Chrysotile
asbestos.
---13
-- 1 of 40 --
FI-MUE Replace Zama DSN-HHD Generator – Updated SOW
78th Signal Battalion – Camp Zama, Japan | Page 2 of 14
• Gray flange gasket: Sample 300830.162-01 from Room 112 contained 7% Chrysotile asbestos.
• White flange gasket over metal casing: Sample 300830.162-02 from Room 112 contained 50%
Chrysotile asbestos.
• White flange gasket: Samples 300830.162-03 and 300830.162-04 from Room 112 contained 50%
Chrysotile asbestos.
o Note: Sample 300830.162-05, a black gasket from Room 112, was identified as Non-Detect (ND)
for asbestos and is therefore not considered ACM.
The contractor shall submit an Asbestos-Containing Material (ACM) Abatement Work Plan for the work
specified in paragraph 2.1.1.
The ACM Abatement Work Plan shall address and demonstrate compliance with all applicable
requirements of the following:
a. Japan Environmental Governing Standards (JEGS), 2024, Chapter 5, Asbestos;
b. 29 CFR 1926.1101, Asbestos, and 29 CFR 1926.103, Respiratory Protection, to the extent
incorporated into this Contract;
c. EM 385-1-1, Safety and Health Requirements Manual, current contract-applicable edition;
d. Industrial Safety and Health Act (Roudou Anzen Eisei Hou);
e. Ordinance on Prevention of Health Impairment due to Asbestos (Ishiwata Shougai Yobou
Kisoku), Ministry of Health, Labour and Welfare Ordinance No. 21 of 2005, as amended;
f. Air Pollution Control Act (Taiki Osen Boushi Hou);
g. Waste Management and Public Cleansing Act (Haikibutsu no Shori oyobi Seisou ni Kansuru
Houritsu), as amended; and
h. All applicable prefectural, municipal, installation, permit, notification, licensing, transportation, and
disposal requirements related to asbestos abatement and asbestos-containing waste.
The Contractor shall submit two hard copies of the ACM Abatement Work Plan to the Government
Representative (GR) for technical review not less than [10] calendar days prior to commencing any
asbestos-related work or disturbing ACM. The Contractor shall not commence asbestos-related work
until the plan has been accepted in writing by the Contracting Officer or designated Government official.
The ACM Abatement Work Plan shall include, at a minimum, the following:
a. Description of Work, including the location, type, condition, and estimated quantity of ACM to be
disturbed or removed;
b. Applicable codes, permits, notifications, standards, and installation requirements;
c. Regulated work area and abatement area, including containment, access control, warning signs,
and decontamination facilities;
d. ACM removal and abatement procedures, including work sequence, wet methods, cleanup
procedures, and measures to prevent asbestos fiber release;
e. Personnel training requirements, respiratory protection, and personal protective equipment;
f. Materials and equipment for abatement, including containment materials, HEPA vacuums,
negative-air equipment when required, and waste containers;
g. Air monitoring and sampling plan, including sampling locations, frequency, analysis, reporting,
and corrective actions;
-- 2 of 40 --
FI-MUE Replace Zama DSN-HHD Generator – Updated SOW
78th Signal Battalion – Camp Zama, Japan | Page 3 of 14
h. Waste handling and disposal procedures, including packaging, labeling, storage, transportation,
manifests, and disposal documentation; and
i. Emergency, unexpected discovery, and stop-work procedures.
j. Plan Preparer. Provide the name, title, qualifications, and applicable training certificates of the
person who prepared the ACM Abatement Work Plan.
Government rev…