What this opportunity is
The Department of Defense is soliciting quotes for the replacement and disposal of a 150kVA emergency power diesel generator at Camp Zama, Japan. This opportunity is open to all businesses, as there is no set-aside for small businesses. Contractors must demonstrate relevant experience and provide employees with specific certifications related to emergency power generators and electrical work. Interested parties should note that this is a solicitation notice, indicating that they should track the opportunity rather than submit a bid immediately.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
FA520926Q0077
Attachment 1
STATEMENT OF WORK (SOW)
FI-MUE Replace Zama DSN-HHD Generator
78 th Signal Battalion
Camp Zama, Japan
24 Aug 2026
-- 1 of 12 --
FA520926Q0077
Attachment 1
1. INTRODUCTION
This Statement of Work (SOW) defines the requirements, scope, responsibilities, and deliverables for the
replacement and disposal of the 150kVA emergency power diesel generator located on Camp Zama
Japan Building 121.
2. SCOPE OF WORK
The contractor shall provide all necessary materials, equipment, labor, and services to:
2.1. Decommissioning and Removal of Existing Generator.
• Disconnection from the electrical distribution system.
• Safe removal of residual fuel and proper disposal as per environmental regulations.
• Safe removal of coolant and oil and proper disposal as per environmental regulations.
• Disassembly and transport of the existing generator from the site (Bldg. 121, Camp Zama) to an
authorized disposal facility.
• Removal disposal of old conduits and exhaust piping that cannot be re-used for the new
generator system.
2.2. Disposal and Environmental Compliance
• Disposal of the generator, engine, batteries, coolant, oils, shall be completed by the contractor
utilizing off-base location.
• Proper handling and disposal of hazardous materials, including oil, fuel, and battery
components.
• Contractor shall provide a copy of the receipt of disposal of any hazardous waste to the
Government Representative (GR) of this contract for recorded keeping.
2.3. Installation of New Generator
• Site preparation, including foundation modifications if required.
• Delivery and offloading of the new generator.
• Installation and secure anchoring of the generator unit.
• Electrical integration with the existing power panel and ATS. Contractor is permitted to reuse
existing wires and conduits from Panel L-M-2 to the generator pending they reach without the
need for splicing. Splicing of wires is not permitted.
• Connection and modification of exhaust system. The contractor may reuse existing exhaust
piping to avoid new holes and core drilling of the outside wall.
• The contractor shall also utilize all existing air intake ducts, both internal and external, for
compatibility. The contractor is encouraged and permitted to re-use the existing fuel piping and
radiator exhaust ducting, provided that they are thoroughly inspected, tested, and certified by
the contractor to be in fully functional, safe, and leak-free condition prior to the integration with
the new generator system.
• The existing Stainless Steel Diesel Tank, renewed in 2008 and confirmed serviceable, shall be
utilized by the contractor for compatibility with the replacement generator. Technical drawings
for this tank are available upon request [4]
-- 2 of 12 --
FA520926Q0077
Attachment 1
2.4. Testing and Commissioning
• Verification of electrical connections and power output.
• Contractor shall conduct a minimum 8-hour load test utilizing site loads as part of the post
installation test & commissioning plan.
• Contractor shall provide a draft post installation test and commissioning plan to the GR no later
than 30 days prior to final acceptance of the new generator system. This test plan will need to be
reviewed and approved by the GR prior to being implemented for acceptance.
2.5. Handover and Documentation
• Training for facility personnel on new generator operation and maintenance.
• The contractor shall submit three (3) sets of work performance and test result reports, as-built
drawings, operation manuals, and warranty documents in both English and Japanese, to the
GR(78th Signal Battalion/DPW) within 15 calendar days after the work completion date. Such
reports shall be submitted in booklet-type and digital forms with catalog cuts/manufacturer
drawings of replacement parts.
3. Technical Specifications
3.1. Existing Generator Details (To Be Disposed of)
• Capacity: 150 KVA / 120 KW
• Voltage Output: 208/120 VAC
• Maka/Model: Toyo Denki Seizo / TYND-215
• Fuel Type: Diesel
• Frequency: 50 Hz
• Current Status: Unserviceable and Obsolete, to be decommissioned
3.2. New Generator Specifications
• Capacity: 150 KVA / 120 KW
• Voltage Output: 208/120 VAC
• Frequency: 50 Hz
• Fuel Type: Diesel
• Wiring: 3 Phase, 4 Wire Plus 1 Ground.
• The new diesel generator shall be fully compatible and connected to the existing ATS inside of
B121 Camp Zama. The Contractor is responsible for conducting pre-proposal survey(s) prior to
quote submission to confirm that the compatibility of the proposed generator with the existing
ATS.
• New generator/engine shall come equipped with a water jacket heater to ensure the diesel
engine is maintained at a temperature of 40-50 degrees Celsius while in standby mode.
• New generator system shall have an output breaker local to the generator to ensure proper
isolation for maintenance.
• New generator shall have Phase to phase & Phase to neutral power, voltage, and amperage
indication gauges/meters affixed to the generator for operational trending.
-- 3 of 12 --
FA520926Q0077
Attachment 1
• New generator shall automatically adjust frequency based on load demands to maintain a tight
operational tolerance between 49.5 – 50.5 HZ.
• New generator shall automatically adjust AVR based on load demands to maintain a tight
operational tolerance between + or – 5% of nameplate per ANSI C84.1. (198V to 218V & 114V to
126V)
• Sound Level: Compliance with Japanese noise regulations for industrial zones
• Environmental Compliance: Meets Japan’s emissions standards for diesel generators
• Warranty: This contract shall include an extended 2-year warranty provided either by the
contractor or Original Equipment Manufacture (OEM) that covers any repairs or replacement of
premature failures of the system or its subcomponents under normal operations.
3.3. Existing Automatic Transfer Switches (ATS)
• Building 121 contains two (2) existing Automatic Transfer Switches (ATS) for the emergency
power sy…