E N C O N International, Inc.
Engineering, Environmental, & Technical Services
December 18, 2008
Mr. Henry Wilson Phone: (915) 568-2300
Asbestos & Lead Manager Fax: (915) 568-4304
DPW, Bldg. 777
Fort Bliss, TX 79916
RE: SUBMITTAL OF ASBESTOS & LEAD SURVEY REPORT
Ft. Bliss Bldg. #2414
ENCON Project #103-08-150
Dear Mr. Wilson,
This document summarizes the Asbestos & Lead Survey Report for the subject facility. The below-listed
information was utilized to complete the Scope of Work Tasks:
Project Location and/or Room No. Whole Building
Brief SOW:
Performed sampling prior to demolition or renovation activities.
ASBESTOS – One-hundred-seventeen (117) samples were collected and submitted for analysis. Results
indicated that Asbestos was not detected in the collected samples.
LEAD - Results indicate that thirty-two (32) of the one hundred thirty-nine (139) XRF readings tested
at or above the limit of 0.3 mg/cm2.
Technical Summary Were
Found
Were
Not
Found
Not
Tested
1. Asbestos Containing Materials (>1 %) X
2. Lead Based Paint Materials X
Contact me with any technical questions, or follow-up needs that you may have.
Sincerely:
Alex Woelper P.E.
Project Manager
Attachments:
Asbestos & Lead Survey Report
-- 1 of 49 --
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
Engineering, Environmental & Technical Services
ASBESTOS SURVEY REPORT
BUILDING 2414
FORT BLISS, TEXAS 79916
Prepared for:
Mr. Henry Wilson, P.E.
DPW
Building 777
Fort Bliss, Texas 79916
Prepared by:
ENCON International, Inc.
7307 Remcon Circle,
Suite 103
El Paso, Texas 79912
Dates of Inspection:
December 4th & 5th, 2008
ENCON Project No. 103-08-150
E N C O N INTERNATIONAL, INC.
-- 2 of 49 --
Engineering, Environmental & Technical Services
December 11, 2008
Mr. Henry Wilson, P.E. Phone: (915) 568-2300
Asbestos & Lead Manager Via email & hand delivery
DPW, Bldg. 777
Fort Bliss, TX 79916
RE: ASBESTOS SURVEY REPORT
Building 2414
Fort Bliss, TX 79916
Dear Mr. Wilson,
ENCON International, Inc., (ENCON) has submitted for your review the attached Asbestos
Survey Report. This Asbestos Survey was conducted in accordance with Asbestos National
Emissions Standards for Hazardous Air Pollutants (NESHAP): 40 CFR Part 61, Subpart M.
Sampling protocols were performed in accordance with the Texas Asbestos Health Protection
Rules (TAHPR).
This Asbestos Survey was properly performed by ENCON DSHS licensed personnel. ENCON’s
personnel have been trained and are in compliance with Texas Department of State Health
Services (DSHS) regulations. If you have any questions regarding this Asbestos Survey, please
feel free to contact us at your convenience.
Sincerely,
Alex Woelper, P.E.
Program Manager
Attachments:
Asbestos Survey Report
Asbestos Drawings
Photo Log
Laboratory Documentation
E N C O N INTERNATIONAL, INC.
-- 3 of 49 --
Asbestos Survey Report ENCON International, Inc.
Ft. Bliss, Bldg. 2414 Project No. 103-08-150
Page 1
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
ASBESTOS SURVEY REPORT
Ft. Bliss, Bldg. 2414
SUMMARY
ENCON International, Inc. (ENCON) personnel performed an Asbestos Inspection of a structure
designated as “Building 2414” on Fort Bliss, Texas. The following are the field sample
collection and analysis results for this inspection. The inspection was conducted to ensure
compliance with NESHAP – 40 CFR Part 61, Subpart M, which states that “prior to the
commencement of the demolition or renovation, thoroughly inspect the affected facility or part
of the facility where the demolition or renovation operation(s) will occur for the presence of
asbestos, including Category I and Category II non-friable ACM. ”
The sample collection and subsequent laboratory analytical results indicated that Asbestos
was not detected in the collected samples.
INTRODUCTION
This Asbestos Survey was performed by Mr. Tim Jones on December 4th and 5th, 2008. This
Asbestos Survey was conducted in accordance with Asbestos National Emissions Standards for
Hazardous Air Pollutants (NESHAP): 40 CFR Part 61, Subpart M. Sampling protocols were
performed in accordance with the Texas Asbestos Health Protection Rules (TAHPR). Building
2414 was to undergo renovations and was visually inspected and it was determined that the
suspect asbestos-containing materials could be divided into thirty-nine (39) homogeneous areas,
including the following: 2’ x 4’ ceiling panels (3 types), 2’ x 2’ ceiling panels, drywall/joint
compound (3 types), cove base mastic (8 types), textured drywall/joint compound (8 types),
carpet mastic (3 types), 12” x 12” floor tile & mastic (3 types), popcorn ceiling texture (4 types),
ductwork sealant, rubberized flooring mastic, expansion joint (2 types), stucco textured, and
HVAC sealant.
-- 4 of 49 --
Asbestos Survey Report ENCON International, Inc.
Ft. Bliss, Bldg. 2414 Project No. 103-08-150
Page 2
El Paso Office: 7307 Remcon Circle, Suite 103 El Paso, Texas 79912 Fax 915-581-2049 Phone 915-833-3740
DESCRIPTION
Building 2414 was being used as military personnel housing on Fort Bliss, Texas. The building
occupied approximately 38,527 SF. The building was a three-story structure constructed with
CMU walls on a concrete foundation. The interior was partitioned with drywall walls. The floors
were covered with floor tile, carpeting, and rubberized flooring material in the stairwells. At the
time this Asbestos Survey was performed, the date of construction was not known.
SAMPLING METHODOLOGY
A visual inspection of the building was conducted to develop a sampling plan. This included
determining sample collection points, homogeneous materials and areas. Friability was assessed
by manually manipulating the suspect asbestos materials utilizing hand pressure to determine if
the materials, when dry, can be crumbled, pulverized, or reduced to powder. Thirty-nine (39)
homogeneous areas were established and at least three (3) s…
Source: SAM.gov, as posted. Verify the current solicitation before responding.
Pursue this opportunity with Mindy
See who holds it now, who else is bidding, and draft your response — grounded in real government data, not generic AI.
View the original notice on SAM.gov ↗Similar Active Opportunities (NAICS 238160)
Installation of roof sealant
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 6, 2026
Office Roof Replacement Deer Creek Lake
DEPT OF DEFENSE · Solicitation · due August 3, 2026
Roof Leak Repairs Bldg. 1 and Bldg. 80
AGRICULTURE, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 28, 2026
USCG Station Siuslaw Roofing and Sheetrock Repair
HOMELAND SECURITY, DEPARTMENT OF · Combined Synopsis/Solicitation · due July 28, 2026
Roof Replacement Cheektowaga, NY
COMMERCE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 6, 2026
Deputy Chief of Mission Roof Replacement in Cairo, Egypt
STATE, DEPARTMENT OF · Combined Synopsis/Solicitation · due August 27, 2026