What this opportunity is
The Department of Defense is seeking information from potential sources for PFAS contaminated soil disposal services, specifically for the WMWD Sewer Rehabilitation Project at March ARB, CA. This opportunity is suitable for small businesses with NAICS code 562910, which includes hazardous waste disposal services. The notice type is a Sources Sought, indicating that the government is seeking information from potential sources rather than issuing a formal solicitation, and interested parties should track the opportunity for future updates.
Analysis by Mindy, grounded in the SAM.gov notice.
Description
STATEMENT OF WORK WMWD Sewer Rehabilitation Project - PFAS Groundwater Contamination
MARCH ARB, CA 1
CUI
CUI
STATEMENT OF WORK
FOR
WMWD Sewer Rehabilitation Project - PFAS Groundwater
Soil Contamination
PROJECT NO:
PDPG26-2400
452d CIVIL ENGINEER SQUADRON
452d MISSION SUPPORT GROUP
June 1, 2026
-- 1 of 5 --
STATEMENT OF WORK WMWD Sewer Rehabilitation Project - PFAS Groundwater Contamination
MARCH ARB, CA 2
CUI
CUI
TABLE OF CONTENTS
PART 1 - INTRODUCTION ........................................................................................................................... 3
1.1 SCOPE ......................................................................................................................................................... 3
1.2 O N -SITE HANDLING AND S TORAGE ...................................................................................................................... 3
1.2.1 Stockpile Control
1.2.2 Non-RCRA contaminated soil ................................................................................................................. 3
1.2.3 Air Monitoring
1.3 TESTING AND CLASSIFICATION ............................................................................................................................ 3
1.3.1 RCRA Hazardous .................................................................................................................................... 3
1.3.2 California Hazardous (Non-RCRA). ......................................................................................................... 4
1.4 TRANSPORTATION AND TRACKING............................................................................................................. 4
1.4.1 Hazardous Waste Manifest ................................................................................................................... 4
1.4.2 Licensed Haulers .................................................................................................................................... 4
1.4.3 Vehicles .................................................................................................................................................. 4
PART 2 - ADMINISTRATIVE AND MANAGERIAL REQUIREMENTS ................................................................. 4
-- 2 of 5 --
STATEMENT OF WORK WMWD Sewer Rehabilitation Project - PFAS Groundwater Contamination
MARCH ARB, CA 3
CUI
CUI
PART 1 - INTRODUCTION
This Statement of Work (SOW) defines the requirements for construction disposal services at
March ARB, CA.
The Contractor shall provide all equipment, labor, and supervision necessary for PDPG26-2400
WMWD Sewer Rehabilitation Project - PFAS Groundwater Soil Contamination disposal at March
Air Reserve Base, California in accordance with the terms and conditions of the contract, contract
statement of work contract specifications, federal, state, and local codes, laws, and regulations.
All quantities, dimensions and areas given within the statement of work are approximation only.
Contractor is responsible to verify all quantities, dimensions, and areas.
Work shall include, but is not limited to the following:
1.1 SCOPE
This SOW defines the scope for this task order to dispose of PFAS contaminated soil. Work shall
be in accordance with Air Force technical guidelines and regulatory requirements.
1.2 ON-SITE HANDLING AND STORAGE
To prevent cross-contamination and runoff during excavation, sites must follow best management
practices:
1.2.1 Stockpile Control: Soil piles must be covered with plastic sheeting or tarps and
surrounded by berms.
1.2.2 Non-RCRA contaminated soil can only be accumulated on-site for up to 90 days on
impermeable surfaces (like HDPE liners) before transport.
1.2.3 Air Monitoring: Dust and air quality must be continuously monitored during
excavation and loading.
1.3 TESTING AND CLASSIFICATION
Prior to disposing of any soils taken from the construction site, obtain samples representative of
possible PFAS. Do not transport material from the project site either for reuse or disposal until
tests have been approved. Positive test soils to be removed off site in accordance with Resource
Conservation and Recovery Act (RCRA) guidelines for off-site disposal. Excavated soil must be
analyzed at a certified laboratory to determine its hazard classification:
1.3.1 RCRA Hazardous: Exceeds federal EPA toxicity thresholds (e.g., highly toxic,
corrosive, or reactive). Must be disposed of in a specialized Class I hazardous waste
landfill.
-- 3 of 5 --
STATEMENT OF WORK WMWD Sewer Rehabilitation Project - PFAS Groundwater Contamination
MARCH ARB, CA 4
CUI
CUI
1.3.2 California Hazardous (Non-RCRA): Contains specific chemicals (like aerially
deposited lead or petroleum hydrocarbons) at levels exceeding California's Title 22
limits.
1.4 TRANSPORTATION AND TRACKING
Moving hazardous dirt off-site requires strict logistical and legal tracking.
1.4.1 Hazardous Waste Manifest: All shipments must be documented using the state's
tracking system.
1.4.2 Licensed Haulers: Soil must be hauled by registered hazardous waste transporters.
1.4.3 Vehicles: Transport trucks must be decontaminated before leaving the site to
prevent off-site tracking of hazardous material.
PART 2 - ADMINISTRATIVE AND MANAGERIAL REQUIREMENTS
The Contractor shall provide management, planning, performance measurement, and cost status
reporting pertinent to the performance of the requirements identified in this SOW.
Governing Codes, Criteria, Regulations and Industry Guidance.
Contractor shall comply with the following:
All applicable federal, state, and local statutes, instructions, manuals, handbooks, regulations,
guidance, policy letters, and rules (including all changes and amendments), and Presidential
Executive Orders, pertaining to the work. It is contractor responsibility to know the requirements
of the latest editions and changes and follow the requirements. Contractor must raise any question…